Miss Lucy
← All judgments

Godrej Projects Development Limited vs Anil Karlekar

Supreme Court3 February 2025B.R. Gavai

Ratio decidendi

The rule this decision rests on

Where an apartment buyer's agreement between a developer and purchaser contains terms that are one-sided, unfair and unconscionable—permitting the developer to forfeit a substantial proportion of earnest money upon the buyer's cancellation while limiting the developer's liability for delay in delivery to nominal compensation—the court will not enforce such terms as written, applying the doctrine established in Central Inland Water Transport Corporation that courts will not enforce unfair and unreasonable contracts between parties unequal in bargaining power, notwithstanding clear and explicit contractual language. Where a real estate agreement provides for forfeiture of earnest money in excess of 10% of the basic sale price upon cancellation by the buyer after possession is offered, the excessive portion is unreasonable and will be reduced to 10%, which the court treats as the reasonable quantum of earnest money that a developer may retain. Earnest money forfeiture will be treated as a penalty subject to Section 74 of the Indian Contract Act if it is disproportionate to the actual loss suffered by the developer, and reasonableness is determined by reference to the proportionality of the forfeiture to legitimate losses, such as carrying costs and the developer's inability to re-sell, as distinguished from windfall gains. Where a buyer seeks cancellation after possession is offered, not due to defect in the property or developer breach but due to changed market conditions favourable to the buyer, no interest is awarded on the refund of amounts in excess of reasonable earnest money forfeiture, on the ground that the buyer would have invested the amounts elsewhere at advantage.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

2025 INSC 143

REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO. 3334 OF 2023

GODREJ PROJECTS DEVELOPMENT LIMITED …APPELLANT(S)

VERSUS

ANIL KARLEKAR & ORS. …RESPONDENT(S)

JUDGMENT

B.R. GAVAI, J.

1. The present appeal takes exception to the final judgment

and order dated 25th October, 2022 passed in Consumer

Complaint No. 262 of 2018, whereby the National Consumer

Disputes Redressal Commission (hereinafter, “NCDRC”)

disposed of the Consumer Complaint filed by the Respondents

No. 1 and 2 (hereinafter referred to as, “Complainants” or Signature Not Verified Digitally signed by DEEPAK SINGH Date: 2025.02.03 16:24:44 IST Reason: “Respondents”) thereby directing the Appellant to deduct only

1 10% of the Basic Sale Price (“BSP” for short) towards

cancellation of the Complainants’ Apartment and refund the

balance amount along with simple interest @ 6% per annum

from the date of each payment till the date of refund. Aggrieved

thereby, the present appeal has been filed under Section 23 of

Consumer Protection Act, 1986.

2. The facts, in brief, giving rise to the present appeal are as

given below.

2.1 On 10th January, 2014 the Complainants had booked an

Apartment with the Appellant in the project by the name

“Godrej Summit” situated at Sector 104, Gurgaon, Haryana by

an Application Form and submitted Rs. 10,00,000/- as

application money.

2.2 On 20th June, 2014 by an allotment letter, the Appellant

allotted an Apartment being Apartment No. C-1501 on the 14th

floor in Tower ‘C’ to the Complainants in the above-mentioned

project, pursuant to which an Apartment Buyer Agreement

(hereafter referred to as “the Agreement”) was entered into

between the Parties.

2 2.3 On 20th June, 2017 the Appellant upon completion of

construction applied to and subsequently received the

Occupation Certificate from the Director, Town & Country

Planning Department, Haryana.

2.4 On 28th June, 2017 the Appellant offered possession to

the Complainants. The Complainants, however, sought

cancellation of the allotment and further sought full refund of

the amount paid.

2.5 On 29th September, 2017, the Complainants served a

legal notice to the Appellant for refund of the amount paid

totaling Rs. 51,12,310/-.

2.6 Thereafter, on 14th November, 2017, the Complainants

filed a Consumer Complaint (No. 262 of 2018) before the

NCDRC inter-alia praying that Appellant be directed to refund

the sum totaling Rs. 51,12,310/- paid by the Complainants so

far, with interest @ 18% per annum, calculated from the date

of making each payment till the date of realization of the sum.

2.7 Vide impugned order dated 25th October, 2022, the

NCDRC disposed of the Consumer Complaint by directing the

Appellant to deduct only 10% of the BSP i.e. Rs. 17,08,140/-

3 only towards cancellation of the Complainants’ Apartment and

refund the balance amount Rs.34,04,170/- (i.e. Rs.

51,12,310/- minus Rs. 17,08,140/-) along with simple interest

@ 6% per annum from the date of each payment till the date of

refund within three months.

2.8 On 5th December, 2022, the NCDRC also dismissed the

Review Application filed by the Appellant challenging the

impugned order.

2.9 Aggrieved thereby, on 10th January 2023 the Appellant

filed the present appeal challenging only the order dated 25th

October, 2022.

2.10 By an order dated 24th April, 2023, this Court while

issuing notice had granted stay of the impugned order on the

condition that the Appellant refunds the amount deposited by

the Complainants after deducting 20% (earnest money deposit)

along with interest @ 6% per annum from the date of

cancellation of the contract.

3. We have heard Shri Dhruv Mehta, learned Senior Counsel

appearing on behalf of the Appellant and Shri Ashwarya Sinha,

learned Counsel appearing on behalf of the Respondents.

4

4. Shri Dhruv Mehta submits that the NCDRC has grossly

erred in interfering with the contractual terms as entered into

between the Parties. It is submitted that the Agreement

between the parties specifically provided for a forfeiture clause.

The Agreement provided that the Appellant was entitled to

forfeit the entire earnest money and any other due payable by

the buyer including interest on delayed payment.

5. He further submits that the NCDRC has specifically come

to a conclusion that the Appellant was entitled to cancel the

Apartment and forfeit the amount as per the terms and

conditions of the Application Form and/or the Agreement

between the parties. He submits that having arrived at such a

finding, the NCDRC could not have come to a conclusion that

the condition of forfeiture of 20% of BSP, being the earnest

money liable for forfeiture in case of cancellation, was

unreasonable and interfered with the same by reducing it to

10% of the BSP.

6. He further submits that, from the perusal of the email

addressed by the Respondents to the Appellant, it was clear

that though the Appellant had called upon the Respondents to

5 take possession of the Apartment, they had opted out of the

deal only because there was a recession in the market. He

submits that since the Respondents themselves have cancelled

the deal on account of recession in the market, the Appellant

was fully justified in forfeiting the earnest money deposit.

7. He relies on the judgments of this Court in the cases of

Satish Batra v. Sudhir Rawal1 and Desh Raj and others v.

Rohtash Singh2 in support of his submissions.

8. Per contra, Shri Ashwarya Sinha, learned counsel for the

Respondents, relying on the judgments of the NCDRC in the

cases of Komal Aggarwal v. Godrej Projects Development

Ltd.3, DLF Ltd. v. Bhagwanti Narula4 and Ramesh

Malhotra and Another v. Emaar Mgf Land Limited and

Another5, submits that the NCDRC has consistently held that

the condition of forfeiture of 20% of the BSP was not

reasonable and reduced it to 10% of the BSP. 1 (2013) 1 SCC 345 2 (2023) 3 SCC 714 3 Consumer Case No.2139 of 2018 dated 9.11.2022 4 2015 SCC OnLine NCDRC 1613 5 2020 SCC OnLine NCDRC 789

6

9. He further relying on the judgments of this Court in the

cases of Ireo Grace Realtech Private Limited v. Abhishek

Khanna and others6 and Pioneer Urban Land and

Infrastructure Limited v. Govindan Raghavan7 submits

that the condition of forfeiture of 20% of the BSP was one-sided

and unconscionable and, therefore, not enforceable in law.

10. He lastly relying on “The Real Estate (Regulation and

Development) Act, 2016” and “The Haryana Real Estate

Regulatory Authority Gurugram (Forfeiture of earnest

money by the builder) Regulations, 2018”, submits that in

view of the aforesaid Act and Regulations, the forfeiture of

earnest money deposit cannot be more than 10% of the BSP.

11. In the present case, it is not in dispute that the

Complainants had booked an Apartment with the Appellant for

BSP of Rs.1,70,81,400/- on 10th January 2014. Accordingly,

an Agreement was entered into between the Appellant and the

Complainants on 20th June 2014. The Complainants were also

allotted an Apartment on the 14th Floor in Tower ‘C’ on 20th

6 (2021) 3 SCC 241 7 (2019) 5 SCC 725

7 June 2014. On 20th June 2017, the Appellant received the

Occupation Certificate. On 28th June, 2017, the Appellant

issued an intimation to the Respondents calling upon them to

take possession. However, instead of taking possession, by

email dated 22nd August 2017/31st August 2017, the

Respondents refused to take possession and sought

cancellation.

12. The Appellant vide communication dated 1st September

2017 informed the Respondents that out of the amount

deposited by the Respondents, the Respondents were entitled

to refund of Rs.4,22,845/-. However, the Respondents filed a

complaint seeking refund of an amount of Rs.51,12,310/-

along with other ancillary reliefs. The NCDRC, as aforesaid,

passed the impugned order.

13. It will be relevant to refer to clauses 2.6 and 8.4 of the

Agreement entered into between the Parties, which read thus:

“2.6 It has been specifically agreed between the Parties that, 20% of the Basic Sale Price, shall be considered and treated as earnest money under this Agreement (“Earnest Money”), to ensure the performance, compliance and fulfillment of the obligations

8 and responsibilities of the Buyer under this Agreement.

It has been made clear by the Developer and the Buyer has understood that the Sale Consideration and Statutory Charges as mentioned in Schedule VI hereto have been computed on the basis of Super Built Up Area of the Apartment. The Buyer agrees that the calculation of Super Built Up Area in respect of the Apartment is tentative at this stage and subject to variations till the Completion of Construction. In case such variations are beyond +/- 5%, then the Developer shall take prior consent of the Buyer.

*** *** ***

8.4 On and from the date of such termination on account of Buyer’s Event of Default as mentioned above (“Termination Date”), the Parties mutually agree that-

(i) The Developer shall, out of the entire amounts paid by the Buyer to the Developer till the Termination Date, forfeit the entire Earnest Money and any other dues payable by the Buyer including interest on delayed payments as specified in this Agreement.

(ii) After the said forfeiture, the Developer shall refund the balance amount to the Buyer or to his banker/financial institution, as the case may be, without any interest;

(iii) On and from the Termination Date, the Buyer shall be left with no right, title, interest, claim, lien, authority whatsoever either in

9 respect of the Apartment or under this Agreement and the Developer shall be released and discharged of all its liabilities and obligations under this Agreement.

(iv) On and from the Termination Date, the Developer shall be entitled, without any claim or interference of the Buyer, to convey, sell, transfer and/or assign the Apartment in favour of third party(ies) or otherwise deal with it as the Developer may deem fit and appropriate, in such a manner that this Agreement was never executed and without any claim of the Buyer to any sale proceeds of such conveyance, sale, transfer and/or assignment of the Apartment in favour of third party(ies).”

14. It can thus be seen that as per the Agreement between

the Parties, the Complainants were required to pay earnest

money deposit of 20% of the BSP, which undisputedly has

been paid. As per clause 8.4, on termination on account of

Buyer’s Event of Default, the Developer was entitled to forfeit

the entire earnest money deposit and other dues including

interest on delayed payments as specified in the Agreement.

15. Undisputedly, only upon the Appellant calling upon the

Respondents to take possession, the Respondents informed

the Appellant vide email dated 22nd August 2017 as under:

10

“Some of the promised connections from internal roads to externals have been abandoned. Overall the place falls to invite you, entice your And the most painful part is the fact that the market prices have sharply fallen and a similar flat to a new buyer is available at a substantially lower price, not only in secondary market but even by Godrej themselves. This is unfair, and one feels cheated that an old customer of 4 years is a loser compared to the new one. Under the circumstances, am pained to state that I want to cancel my booking of the said flat and demand that the amount paid till date be refunded along with applicable interest. We shall appreciate a prompt action on our request. Kindly share the cancellation formalities, and the refund amount.”

16. The stand taken by the Respondents was specifically

borne out by the NCDRC from the written statement filed by

the Appellant.

17. It is thus clear that the Respondents had cancelled the

deal since there was recession in the market. Not only that,

but the NCDRC has specifically observed as under:

“Hence, the action of the OPs in cancelling the apartment and forfeiting the amount as per terms and conditions of the application form and/or the BBA cannot be faulted with. However, the condition of forfeiture of 20% of BSP, being the earnest money liable for forfeiture in case of cancellation appears unreasonable. It will be in the interest of

11 justice and fair play to both sides, if OPs are allowed to deduct only 10% of the BSP as earnest money i.e. Rs.17,08,140/- and refund the balance amount to the complainants.”

18. This Court in the case of Satish Batra v. Sudhir Rawal

(supra), after considering the earlier judgments of this Court,

has observed thus:

“15. The law is, therefore, clear that to justify the forfeiture of advance money being part of “earnest money” the terms of the contract should be clear and explicit. Earnest money is paid or given at the time when the contract is entered into and, as a pledge for its due performance by the depositor to be forfeited in case of non- performance by the depositor. There can be converse situation also that if the seller fails to perform the contract the purchaser can also get double the amount, if it is so stipulated. It is also the law that part-payment of purchase price cannot be forfeited unless it is a guarantee for the due performance of the contract. In other words, if the payment is made only towards part- payment of consideration and not intended as earnest money then the forfeiture clause will not apply.

16. When we examine the clauses in the instant case, it is amply clear that the clause extracted hereinabove was included in the contract at the moment at which the contract was entered into.

It represents the guarantee that the contract would be fulfilled. In other words, “earnest” is given to bind the contract, which is a part of the

12 purchase price when the transaction is carried out and it will be forfeited when the transaction falls through by reason of the default or failure of the purchaser. There is no other clause that militates against the clauses extracted in the agreement dated 29-11-2011.

17. We are, therefore, of the view that the seller was justified in forfeiting the amount of Rs 7,00,000 as per the relevant clause, since the earnest money was primarily a security for the due performance of the agreement and, consequently, the seller is entitled to forfeit the entire deposit. The High Court has, therefore, committed an error in reversing the judgment of the trial court.”

19. This Court has held that to justify the forfeiture of

advance money being part of “earnest money” the terms of the

contract should be clear and explicit. It has been observed that

the earnest money is paid or given at the time when the

contract is entered into and, as a pledge for its due

performance by the depositor to be forfeited in case of non-

performance by the depositor. However, this Court clarified

that if the payment is made only towards part-payment of

consideration and not intended as earnest money then the

forfeiture clause will not apply.

13

20. Recently, this Court in the case of Desh Raj and others

(supra), after considering the earlier judgments, has reiterated

the aforesaid legal position.

21. We, therefore, find that Shri Dhruv Mehta, learned Senior

Counsel is justified in placing reliance on the aforesaid

judgments of this Court.

22. However, the issue does not rest at that. It will be

relevant to consider the reciprocal obligations of the Appellant

i.e., the Developer in case the Developer does not comply with

the timelines in the Agreement. Clauses 4.2 and 4.3 of the

Agreement are as follows:

“4.2. The Apartment shall be ready for occupation within 42 months from the date of issuance of Allotment Letter. (“Tentative Completion Date"), however the Developer is entitled for a grace period of 6 months over and above this 42 month's period. Upon the Apartment being ready for possession and occupation the Developer shall issue the Possession Notice to the Buyer of the Apartment.

Notwithstanding the above, the Developer shall be entitled to an extension of time from the Tentative Completion Date for issue of the Possession Notice, if the Completion of Construction of the said Apartment or the part/portion of the

14 Project where the said Apartment is situated is delayed on account of any of the following reasons –

(i) Non-availability of steel, cement, other building materials, water or electric supply or labour, or

(ii) Any change in the Applicable Law or existence of any injunction, stay order, prohibitory order or directions passed by any Court, Tribunal, Body or Competent Authority; or

(iii) Delay in securing any permission, Approvals, NOC, sanction building plan, building completion and/or occupation certificate, water, electricity, drainage or sewerage connection from the Competent Authority for reasons beyond the control of the Developer, or

(iv) Force Majeure Event or any other reason (not limited to the reasons mentioned above) beyond the control of or unforeseen by the Developer, which may prevent, restrict, interrupt or interfere with or delay the construction of Project on the Subject Lands or which may prevent the Developer in performing its obligations under this Agreement;

15 In case there are is any delay on account of the aforesaid reasons, the Developer shall keep the Buyer fully informed about the same along with a revised tentative date of possession.

4.3. Subject to the provisions of Clause 4.2 herein above, in the event the Developer fails or neglects to issue the Possession Notice on or before the Tentative Completion Date and/or on such date as may be extended by mutual consent of the Parties, then the Developer shall be liable to pay to the Buyer a compensation for the entire period of such delay computed at the rate of Rs. 5/- (Rupees Five only) per month per square feet of the Super Built Up Area of the Apartment.

In the alternative, the Developer, at the request of the Buyer, may refund the total amounts already received in respect of the said Apartment together with simple interest at the rate of 15% per annum to the Buyer. It has been agreed between the Parties that upon such repayment, the Agreement shall stand terminated and the Buyer shall not be entitled to claim any loss and/or damages whatsoever. The said refund by the Developer to the Buyer, sent through cheque/demand draft by registered post acknowledgement due or by courier at the address of the Buyer mentioned herein, shall be full and final satisfaction and settlement of all claims of the Buyer under this Agreement, irrespective of whether the Buyer accepts/encashes the said cheque/demand draft or not. Thereafter

16 the Buyer shall cease to have any interest or claim on the said Apartment and the proportionate undivided interest in the Common Areas and Facilities and Limited Common Areas and Facilities whatsoever or howsoever. The Developer thereafter shall be entitled to sell the said Apartment along with undivided interest in the Common Areas and Facilities and Limited Common Areas and Facilities to any prospective buyer/third party of its choice.”

23. If we consider the obligations of the Developer in the event

it does not comply with the timelines, a very meagre

compensation is provided to the Apartment purchaser. Not

only that clause 4.2 of the Agreement, which provides that the

Apartment shall be ready for occupation within 42 months

from the date of issuance of Allotment Letter, also provides that

the Developer would be entitled for a grace period of 6 months

over and above this 42 months’ period. The said clause 4.2

further provides for various eventualities in case of which the

Developer would be entitled to further extension of period for

handing over the possession.

24. In any case, clause 4.3 of the Agreement provides that,

subject to the provisions of clause 4.2 of the Agreement, if the

17 Developer fails or neglects to issue the Possession Notice on or

before the Tentative Completion Date and/or on such date as

may be extended by mutual consent of the Parties, the

Developer shall be liable to pay to the Buyer a meagre

compensation for such a delay at the rate of Rs.5/- per month

per square feet of the Super Built Up Area of the Apartment.

25. It can thus be seen that the Agreement is one-sided and

totally tilted in favour of the Developer.

26. In the case of Central Inland Water Transport

Corporation Limited and Another v. Brojo Nath Ganguly

and Another8, this Court, by taking recourse to Article 14 of

the Constitution of India, has held that the courts will not

enforce an unfair and unreasonable contract or an unfair and

unreasonable clause in a contract, entered into between

Parties who are not equal in bargaining power. It will be

relevant to refer to the following observations of this Court in

the said case:

“89. ……We have a Constitution for our country. Our judges are bound by their oath to “uphold the Constitution and the laws”. The Constitution was enacted to secure to all the 8 (1986) 3 SCC 156

18 citizens of this country social and economic justice. Article 14 of the Constitution guarantees to all persons equality before the law and the equal protection of the laws. The principle deducible from the above discussions on this part of the case is in consonance with right and reason, intended to secure social and economic justice and conforms to the mandate of the great equality clause in Article 14. This principle is that the courts will not enforce and will, when called upon to do so, strike down an unfair and unreasonable contract, or an unfair and unreasonable clause in a contract, entered into between parties who are not equal in bargaining power. It is difficult to give an exhaustive list of all bargains of this type. No court can visualize the different situations which can arise in the affairs of men. One can only attempt to give some illustrations. For instance, the above principle will apply where the inequality of bargaining power is the result of the great disparity in the economic strength of the contracting parties. It will apply where the inequality is the result of circumstances, whether of the creation of the parties or not. It will apply to situations in which the weaker party is in a position in which he can obtain goods or services or means of livelihood only upon the terms imposed by the stronger party or go without them. It will also apply where a man has no choice, or rather no meaningful choice, but to give his assent to a contract or to sign on the dotted line in a prescribed or standard form or to accept a set of rules as part of the contract, however unfair, unreasonable and unconscionable a clause in that contract or form or rules may be. This principle, however,

19 will not apply where the bargaining power of the contracting parties is equal or almost equal. This principle may not apply where both parties are businessmen and the contract is a commercial transaction.”

27. This Court in the case of Pioneer Urban Land and

Infrastructure Limited (supra) was considering similar

clauses in an Agreement between a Developer and an

Apartment Purchaser. This Court observed thus:

“6.4. A perusal of the apartment buyer's agreement dated 8-5-2012 reveals stark incongruities between the remedies available to both the parties. For instance, Clause 6.4(ii) of the agreement entitles the appellant builder to charge interest @18% p.a. on account of any delay in payment of instalments from the respondent flat purchaser. Clause 6.4(iii) of the agreement entitles the appellant builder to cancel the allotment and terminate the agreement, if any instalment remains in arrears for more than 30 days. On the other hand, as per Clause 11.5 of the agreement, if the appellant builder fails to deliver possession of the apartment within the stipulated period, the respondent flat purchaser has to wait for a period of 12 months after the end of the grace period, before serving a termination notice of 90 days on the appellant builder, and even thereafter, the appellant builder gets 90 days to refund only the actual instalment paid by the respondent flat purchaser, after adjusting the

20 taxes paid, interest and penalty on delayed payments. In case of any delay thereafter, the appellant builder is liable to pay interest @9% p.a. only.

6.5. Another instance is Clause 23.4 of the agreement which entitles the appellant builder to serve a termination notice upon the respondent flat purchaser for breach of any contractual obligation. If the respondent flat purchaser fails to rectify the default within 30 days of the termination notice, then the agreement automatically stands cancelled, and the appellant builder has the right to forfeit the entire amount of earnest money towards liquidated damages. On the other hand, as per Clause 11.5(v) of the agreement, if the respondent flat purchaser fails to exercise his right of termination within the time limit provided in Clause 11.5, then he shall not be entitled to terminate the agreement thereafter, and shall be bound by the provisions of the agreement.

6.6. Section 2(1)(r) of the Consumer Protection Act, 1986 defines “unfair trade practices” in the following words:

“2.(1)(r) “unfair trade practice” means a trade practice which, for the purpose of promoting the sale, use or supply of any goods or for the provision of any service, adopts any unfair method or unfair or deceptive practice.…”,

21 and includes any of the practices enumerated therein. The provision is illustrative, and not exhaustive.

xxx xxx xxx

6.8. A term of a contract will not be final and binding if it is shown that the flat purchasers had no option but to sign on the dotted line, on a contract framed by the builder. The contractual terms of the agreement dated 8-

5-2012 are ex facie one-sided, unfair and unreasonable. The incorporation of such one- sided clauses in an agreement constitutes an unfair trade practice as per Section 2(1)(r) of the Consumer Protection Act, 1986 since it adopts unfair methods or practices for the purpose of selling the flats by the builder.

7. In view of the above discussion, we have no hesitation in holding that the terms of the apartment buyer's agreement dated 8-5-2012 were wholly one-sided and unfair to the respondent flat purchaser. The appellant builder could not seek to bind the respondent with such one-sided contractual terms.”

28. The view taken by this Court in the case of Pioneer Urban

Land and Infrastructure Limited (supra) was followed in the

case of Wing Commander Arifur Rahman Khan and Aleya

Sultana and others v. DLF Southern Homes Private

Limited (Now Known as Begur OMR Homes Private Limited)

22 and others9.

29. Further, a three-judge Bench of this Court in the case of

Ireo Grace Realtech Private Limited (supra) approved the

legal position as laid down in the case of Pioneer Urban Land

and Infrastructure Limited (supra).

30. It is further to be noted that when the cases of Pioneer

Urban Land and Infrastructure Limited (supra), Wing

Commander Arifur Rahman Khan and Aleya Sultana and

others (supra) and Ireo Grace Realtech Private Limited

(supra) were decided, they were decided based on the

provisions of the Consumer Protection Act, 1986. Relying on

the provisions of Section 2(1)(r) of the Consumer Protection

Act, 1986, which defines the term “unfair trade practice”, this

Court held that the contractual terms which are ex facie one-

sided, unfair and unreasonable would constitute unfair trade

practice as per the aforesaid definition of “unfair trade

practice”.

31. Now, Parliament in 2019 has enacted the Consumer

Protection Act, 2019, which has specifically provided a

9 (2020) 16 SCC 512

23 definition for “unfair contract”. It will be apposite to refer to the

relevant part of clause (46) of Section 2 of the Consumer

Protection Act, 2019, which reads thus:

2. Definitions.- In this Act, unless the context otherwise requires,-

xxx xxx xxx

(46) “unfair contract” means a contract between a manufacturer or trader or service provider on one hand, and a consumer on the other, having such terms which cause significant change in the rights of such consumer, including the following, namely:-

(i) requiring manifestly excessive security deposits to be given by a consumer for the performance of contractual obligations; or

(ii) imposing any penalty on the consumer, for the breach of contract thereof which is wholly disproportionate to the loss occurred due to such breach to the other party to the contract; or xxx xxx xxx

(vi) imposing on the consumer any unreasonable charge, obligation or condition which puts such consumer to disadvantage;”

24

32. No doubt that the aforesaid definition would be applicable

after the Consumer Protection Act, 2019 came into effect,

however, even prior to that while considering the term “unfair

trade practice”, this Court has found that such one-sided

Agreements, as in the present case, would be covered by the

definition of term “unfair trade practice”.

33. Insofar as the judgment in the case of Satish Batra

(supra) is concerned, the clause providing for “forfeiture of

earnest money deposit” cannot be said to be one-sided. It will

be relevant to refer to the term which fell for consideration

before this Court in the aforesaid case, which reads thus:

“(e) If the prospective purchaser fails to fulfil the above condition, the transaction shall stand cancelled and earnest money will be forfeited. In case I fail to complete the transaction as stipulated above, the purchaser will get double the amount of the earnest money. In both conditions, the dealer will get 4% commission from the faulting party.”

34. It can thus be seen that in the aforesaid case though the

term in the Agreement provided for forfeiture of the earnest

money in the event the prospective purchaser fails to fulfill the

25 conditions, it also provided for payment of double the amount

of earnest money by the vendor to the purchaser in case the

vendor fails to complete the transaction. As such, the said

term cannot be said to be one-sided.

35. Similarly, in the case of Desh Raj and others (supra),

this Court was considering an Agreement to Sell with respect

to the landed property. A perusal of the judgment would reveal

that it was a case of an Agreement between two equal Parties

and there are no terms in the Agreement which could be said

to be one-sided and tilted totally in favour of one of the Parties.

36. We are, therefore, of the view that the present case would

not be governed by the law laid down by this Court in the cases

of Satish Batra (supra) and Desh Raj and others (supra), but

would be governed by the law as laid down in the cases of

Pioneer Urban Land and Infrastructure Limited (supra),

Wing Commander Arifur Rahman Khan and Aleya

Sultana and others (supra) and Ireo Grace Realtech

Private Limited (supra).

37. It will further be relevant to refer to the following

observations by a Bench consisting of three learned Judges of

26 this Court in the case of Maula Bux v. Union of India10:

5. Forfeiture of earnest money under a contract for sale of property — Movable or immovable — If the amount is reasonable, does not fall within Section 74. That has been decided in several cases: Chiranjit Singh v. Har Swarup; Roshan Lal v. Delhi Cloth and General Mills Company Ltd. Delhi [1910 SCC OnLine All 98 : ILR (1911) 33 All 166] ; Mohd Habibullah v. Mohd Shafi [1919 SCC OnLine All 87 : ILR 41 All 324] ; Bishan Chand v. Radhakishan Das.

[1897 SCC OnLine All 52 : ILR (1897) 19 All 490] These cases are easily explained, for forfeiture of reasonable amount paid as earnest money does not amount to imposing a penalty. But if forfeiture is of the nature of penalty. Section 74 applies. Where under the terms of the contract the party in breach has undertaken to pay a sum of money or to forfeit a sum of money which he has already paid to the party complaining of a breach of contract, the undertaking is of the nature of a penalty.”

38. It can be seen that this Court has held that if the

forfeiture of earnest money under a contract is reasonable,

then it does not fall within Section 74 of the Indian Contract

Act, 1872, inasmuch as, such a forfeiture does not amount to

imposing a penalty. It has further been held that, however, if

10 (1969) 2 SCC 554

27 the forfeiture is of the nature of penalty, then Section 74 would

be applicable. This Court has further held that under the

terms of the contract, if the party in breach undertook to pay

a sum of money or to forfeit a sum of money which he had

already paid to the party complaining of a breach of contract,

the undertaking is of the nature of a penalty.

39. Relying on the aforesaid observations of this Court, the

NCDRC, in a series of cases right from the year 2015, has held

that 10% of the BSP is a reasonable amount which is liable to

be forfeited as earnest money. The NCDRC has initially taken

this view in the case of DLF Ltd. v. Bhagwanti Narula

(supra). The said view has been followed subsequently in

various judgments of the NCDRC. We see no reason to upset

the view consistently taken by the NCDRC based on the

judgment of this Court in the case of Maula Bux (supra).

40. Though we are not inclined to interfere with the direction

of the NCDRC for refund of the amount in excess of 10% of the

BSP, we however find that the NCDRC was not justified in

awarding interest on the amount to be refunded.

41. As has been pointed out herein above, after the

28 Agreement was entered into between the Parties in the year

2014, only after the possession was offered by the Appellant to

the Respondents, they sought cancellation of the allotment.

The reason given by them is that on account of sharp decline

in the prices, a person would be able to buy a flat at a

substantially lower price even in Primary market.

42. It is quite probable that the Respondents would have

utilised the money which was payable by them to the Appellant

for purchasing another property at a lower rate.

43. In the facts and circumstances, therefore, we find that the

NCDRC was not justified in awarding interest on the amount

to be refunded by the Appellant.

44. In pursuance of our order dated 24th April 2023, the

Appellant has refunded an amount of Rs.22,01,215/- to the

Respondents. After deducting an amount of Rs.17,08,140/-

(i.e. 10% of the BSP) from Rs.51,12,310/- (amount paid by the

Respondents to the Appellant), the amount comes to

Rs.34,04,170/-. The Appellant is, therefore, required to pay

balance amount of Rs.12,02,955/- [Rs.34,04,170/- minus

Rs.22,01,215/-] to the Respondents. We, therefore, direct the

29 Appellant to pay the said amount of Rs.12,02,955/- to the

respondents within a period of six weeks from today.

45. The appeal is partly allowed in the above terms.

46. Pending application(s), if any, shall stand disposed of.

..............................J (B.R. GAVAI)

..............................J (S.V.N. BHATTI)

NEW DELHI;

FEBRUARY 03, 2025

30

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free