Elecon Engineering Company Limited vs Bhartiya Rail Bijlee Company Limited
- Neutral2026 INSC 458
Ratio decidendi
The rule this decision rests on
A non-signatory to a contract may invoke an arbitration clause contained in that contract if the non-signatory is a veritable party to the contract itself, demonstrated by being an essential and inextricable part of its performance as required by the contract's express terms, even where the non-signatory has not directly signed the principal agreement between the contracting parties. Where a bidding process for a contract expressly requires a contractor to collaborate with another party to satisfy eligibility criteria, and mandates execution of a joint undertaking by both the contractor and collaborator in favour of the employer establishing their joint and several liability for contract performance, the collaborator becomes a veritable party to the contract and is entitled to invoke any arbitration clause contained in the principal contract between the contractor and employer. Where the employer has, in the course of contract execution, called upon a collaborator to fulfil contractual obligations as per the joint undertaking executed at the inception of the contract, the employer is estopped from later asserting absence of privity of contract with the collaborator and refusing consent to arbitration on that ground, as such conduct amounts to a reaffirmation of the collaborator's obligation under the original contract.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
Non-Reportable
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
Civil Appeal No..........of 2026 [@ Special Leave Petition (C) No.33128 of 2025]
Elecon Engineering Company Limited ...Appellant Versus
Bhartiya Rail Bijlee Company Limited & Anr.
...Respondents
JUDGMENT
K. Vinod Chandran, J.
Leave granted.
2. A Collaborator’s request for arbitration, which
collaboration was essential to technically qualify the
Contractor to proffer a bid was declined on the ground of
there being no privity of contract. The High Court
considering a petition under Section 11(6) of the Arbitration
and Conciliation Act, 1996 (Act of 1996) rejected the same Signature Not Verified Digitally signed by babita pandey against which the present appeal is filed. We refer to the Date: 2026.05.07 16:53:39 IST Reason:
parties as the Employer; the 1st respondent herein, the
Page 1 of 10 CA @ SLP(C) No.33128 of 2025 Contractor; the 2nd respondent and the Collaborator; the
appellant.
3. The High Court noticed the trite principle that even
non-signatories to an agreement with an arbitration clause
would be entitled to invoke it, if such non-signatory is a
veritable party to the arbitration agreement. However,
finding that there was nothing in the notice under Section 21
of the Act of 1996 to find such inextricable connection; the
notice also having specifically sought for a consent to initiate
an arbitration, declined the prayer.
4. Learned Senior Counsel Sri Sridhar Potaraju,
appearing for the appellant took us through the initial bid
document itself to urge that without the collaboration, the
Contractor would not have been able to satisfy the eligibility
criteria of experience in design and commissioning of an
integrated bulk material handling plant with rated capacity
of 1000 Metric tonnes per hour or above for coal/other
minerals of a minimum period of one year. The Collaborator
was thus an inextricable party to the contract, which also
required submission of ‘Deed of Joint Undertaking’ (DJU)
Page 2 of 10 CA @ SLP(C) No.33128 of 2025 executed jointly by the Collaborator and the Contractor.
Later, the Contractor having slipped into liquidation the
Employer called upon the Collaborator to take up the full
responsibility for the successful performance of the contract
as per the DJU dated 22.02.2010 submitted along with the bid
documents.
5. Sri Aman Lekhi, learned Senior Counsel on the other
hand submits that the very notice under Section 21, as has
been found by the High Court, sought a consent for
arbitration, which reveals the understanding of the
Collaborator itself that the contract between the parties, did
not contain a clause for resolving the disputes through
arbitration. The tripartite agreement entered into by the
Collaborator with the Employer and the Contractor does not
contain such a clause which eclipses any earlier contract.
Though a combined, complementary role was contemplated
initially as of now, the Contractor having gone into
liquidation, no claim can be raised against the Employer by
the Collaborator.
Page 3 of 10 CA @ SLP(C) No.33128 of 2025
6. The bid document along with the special conditions of
contract and general conditions of contract produced as
Annexure P1 clearly stipulates the qualification requirements
for bidders and provides for the eligibility to be satisfied
through collaborations in which event the bidder is required
to furnish DJU’s executed by the bidder and the
collaborator/associate for successful performance of the
relevant system, as per the NTPC format enclosed with the
bid documents. The contract awarded was for installing a
Coal Handling Plant Package for Nabinagar Thermal Power
Project of the respondent, the Employer. The successful
bidder/Contractor, the 2nd respondent collaborated with the
appellant for its design capabilities and supply of certain
equipment/materials based on the latter’s experience in a
project of the required strength and its successful operation
for one year. The bid form also contains various DJUs to be
executed by ‘a Collaborator/Associate’ along with the
Contractor for the Coal Handling Plant for Nabinagar
Thermal Power Project. The DJU was executed by the
Collaborator with the Contractor, in favour of the Employer
Page 4 of 10 CA @ SLP(C) No.33128 of 2025 which clearly indicates that the Collaborator was an
inseparable part of the contract and its execution.
7. The DJU was executed on 22.02.2010, as is available at
Annexure P2 and there is no dispute that the contract entered
into between the Contractor and the Employer has an
arbitration clause. The question to be decided is as to
whether the Collaborator/Associate is a veritable party to the
contract, which from the very terms of the contract and those
discernible from the bid document and requirements
thereof, has to be answered in the affirmative.
8. The fact also remains that in the course of the
execution of the contract, the Contractor was faced with a
liquidation proceeding and ordered to be liquidated on
16.01.2020. The High Court in rejecting the arbitration
request had referred to and extracted the letters invoking
arbitration, issued by the Collaborator on 02.07.2022 and
responded to by the Employer, on 29.07.2022, to decline the
request. We see from the letter dated 02.07.2022 produced
as Annexure P10 that the Collaborator had specifically
referred to the DJU and the delay caused in the execution of
Page 5 of 10 CA @ SLP(C) No.33128 of 2025 the project by reasons only of the default of the Contractor,
upon which there was even an encashment of the bank
guarantee submitted by the Collaborator, which was also
described as wrongful. It was specifically pointed out that, on
the Contractor failing to fulfil its obligations, the Collaborator
was called upon to fulfil its obligations as a sub-vendor of the
Contractor for the Coal Handling Project. It was pursuant to
the decisions taken in the meetings convened, pursuant to
the above referred communication; which was also attended
by the Contractor, that a tripartite agreement was entered
into between the Contractor, the Collaborator and the
Employer dated 05.04.2016; produced as Annexure P8. The
tripartite agreement specifically authorized payments to the
Collaborator with respect to the outstandings against the
earlier supplies and those to be supplied in future by the
Collaborator, to be paid directly to the Collaborator.
9. Subsequently, communication dated 08.10.2021,
Annexure P9, was issued by the Employer which again called
upon the Collaborator to fulfil its obligations as per the DJU
furnished at the inception and it was also threatened that on
Page 6 of 10 CA @ SLP(C) No.33128 of 2025 failure, the Employer will be constrained to execute the
balance work at the risk and cost of the Collaborator. It is also
to be noticed that the consent required by the Collaborator
in the letter dated 02.07.2022 was for reference of the matter
to the Delhi International Arbitration Centre and not
necessarily a consent for resolving the dispute through
arbitration; which provision was already available in the
agreement executed by the contractor to which the
Collaborator is an essential and inextricable part. The
communications issued pursuant to the default of the
Contractor is a reaffirmation of the obligation of the
Collaborator as per the contract executed, of which the DJU
is an inextricable part. The tripartite agreement only
asserted the responsibility of the Collaborator to fulfill the
contract and was only a measure of ensuring payments to the
Collaborator directly, in the wake of the inability of the
Contractor and does not wipe out the earlier contract.
10. In response to the notice under Section 21, the
Employer specifically referred to the DJU and the ‘joint and
several’ responsibilities of the Contractor and the
Page 7 of 10 CA @ SLP(C) No.33128 of 2025 Collaborator to complete the project. The tripartite
agreement was also referred to along with various letters
issued by the Employer to the Collaborator for effective
completion of the project. Despite the Employer having
called upon the Collaborator to fulfil its obligations as per the
DJU, due to the disability of the Contractor, the Employer
asserted absence of privity of contract and refused consent
for adjudication of the dispute between themselves in its
letter dated 29.07.2022.
11. We are of the opinion that the contract by itself
necessitated the execution of joint undertaking by the
Contractor and the Collaborator who had the ‘joint and
several’ liability for the due completion of the contract. The
arbitration clause applied both to the Collaborator and the
Contractor in so far as the disputes with the Employer and
between themselves the agreement of collaboration
provided a like clause for dispute resolution. On the
Contractor defaulting in the completion of the project, the
Employer had also called upon the collaborator to fulfil the
obligations as per the DJU specifically raising the issue of
Page 8 of 10 CA @ SLP(C) No.33128 of 2025 joint and several responsibilities. The meetings convened
between the Employer, the Contractor and the Collaborator,
after delay in execution of the contract, the tripartite
agreement entered into between them and the further
communications addressed to the collaborator to take up his
responsibility as per the DJU makes the Collaborator a
veritable party to the contract who is also entitled to invoke
the arbitration clause as available in the contract between the
Contractor and the Employer in which the DJU executed by
the Collaborator and the Contractor, in favour of the
Employer is an inextricable part.
12. On the above reasoning, we find the High Court to
have wrongly declined the prayer for arbitration. We set
aside the judgment impugned and allow the petition filed
under Section 11(6) of the Act of 1996. Justice (Retd.)
Chakradhari Sharan Singh, (former Chief Justice of the Orissa
High Court, Mobile No.: +91 94310 15002) is appointed as the
sole Arbitrator to adjudicate upon the disputes between the
parties. All contentions available to the parties are left open
to be urged before the Arbitrator.
Page 9 of 10 CA @ SLP(C) No.33128 of 2025
13. The learned Arbitrator will proceed in accordance
with law and make his declaration in terms of Section 12 of
the Arbitration and Conciliation Act, 1996 within a period of
15 days from the date a copy of this judgment is received by
him. He shall be paid in terms of the Fourth Schedule to the
Act of 1996.
14. The Registry is directed to intimate/inform the
appointment made by us to the learned Arbitrator.
15. The above appeal is allowed with the above
directions.
.......…….……………………. J.
(SANJAY KUMAR)
....……….……………………. J.
(K. VINOD CHANDRAN)
NEW DELHI;
MAY 07, 2026.
Page 10 of 10 CA @ SLP(C) No.33128 of 2025
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free