Miss Lucy
← All judgments

Dr. Nagendra Rai vs Howrah Improvement Trust And Ors

Calcutta High Court (Appellete Side)26 September 2014Joymalya Bagchi

Ratio decidendi

The rule this decision rests on

1. Where a writ petition is filed by a party challenging executive action in a matter involving a contractual dispute with a State or its instrumentality, and no objection to maintainability is raised at the stage of admission with the matter matured to final hearing and no significant disputed questions of fact remaining, the court may proceed to decide the matter on merits without relegating the petitioner to the alternative remedy of a suit, even if the party is seeking enforcement of contractual rights under Article 226 of the Constitution. 2. A concluded contract for sale between a government instrumentality and a private party may be inferred where: (a) the instrumentality by formal communication has unequivocally stated acceptance of an offer; (b) the parties have taken steps pursuant to that acceptance in performance of the terms (such as holding joint measurements); (c) the offeree has deposited earnest money; and (d) the instrumentality's pleadings in a directly connected preceding proceeding explicitly acknowledge the acceptance and completed steps. The instrumentality's previous self-serving statements made in a related proceeding concerning the same subject matter are probative of the stance and intention of the authority at that material time, and cannot be disregarded as wholly unconnected prior proceedings. 3. A public authority may rescind a duly concluded contract for sale of public property and invite fresh tender on the ground of exponential increase in market value due to supervening circumstances and delay beyond the authority's control, where: (a) the delay in performance was caused by third-party litigation not attributable to the authority's fault or procrastination; (b) the authority had offered to return earnest money when the initial tender was set aside; (c) the consequence is a short recovery of consideration that the authority seeks to remedy through re-auction; and (d) the authority's motivation is to maximize returns to the public exchequer in fulfilment of its fiduciary duty as trustee of public assets, without any element of mala fides or arbitrary action. 4. In the context of sale of public assets, the duty of the State to maximize returns to the public exchequer through auction at the prevalent market price, arising from public trust principles, is a relevant consideration in the exercise of the court's discretion to grant or refuse specific performance of a contract, and this public interest consideration may outweigh the private claim of a contracting party where the delay in performance is not attributable to the State's fault. Specific performance is not a legal right but a discretionary equitable remedy, and the court may exercise this discretion by refusing specific performance and granting the alternative equitable relief of refund of earnest money with interest.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

In the High Court at Calcutta
Constitutional Writ Jurisdiction
Appellate Side
Present:Hon'ble Mr. Justice Joymalya Bagchi

W.P. No. 38345 (W) of 2013 Dr. Nagendra Rai Vs. Howrah Improvement Trust and Ors. For the Petitioner : Mr. Kishore Dutta, Mr. Pradeep Kumar, Mr. Ashok Kr. Pandey For the Respondents : Mr. Ashok Banerjee,

Mr. Shyamal Sanyal, Mr. Sugata Mukhopadhyay.

Heard on : 02,07.2014, 18.07.2014, 08.08.2014,05.09.2014, Judgement on : 26.09.2014 Joymalya Bagchi, J. : The Writ Petition has been filed, inter alia, praying for

direction upon the respondents for accepting balance consideration money from

the petitioner and executing a registered deed of conveyance in favour of the

petitioner is respect of a plot of land measuring four cottahs five chittaks nine

square feet, i.e. 289.298 sq.mt. at premises no.147 Salkia School Road, PS‐

Golabari, Howrah (hereinafter referred to as the plot of land) and for a direction

to cancel, rescind and withdraw notice inviting tender dated 24.12.2013 issued by

respondent no.3 in Sanmarg Patrika inviting tender for sale of the plot of land.

The facts giving rise to the Writ Petition are as follows:‐

On or about 2001, respondent no.2, the Chairman, Howrah Improvement Trust

(HIT for short) issued a notice inviting a tender for sale of the plot of land. In response to such notice, petitioner submitted his bid. No other bid was received

by HIT. HIT extended time for submission of bids. Petitioner moved a writ

petition being WP no.8036 (W) of 2001. This Court by order dated 14.05.2001

quashed the aforesaid notice inviting tender and directed HIT to issue fresh

notice of tender. On 17.05.2001 fresh notice inviting tender of the plot of land was

issued by HIT and base price was fixed at 6.36 lakhs per cottah. In response to

such notice inviting tender, petitioner submitted his bid to purchase the plot at a

rate of Rs. 6.40 lakh per cottah. No other person submitted bid within the

stipulated time. One Omprakash Singh submitted a bid but was disallowed by

HIT as his bid had not been submitted within stipulated time. By letter dated 7th

June, 2001 Chief Executive Officer of HIT informed the petitioner that his offer

being the highest one had been accepted. He was also informed that HIT decided

to undertake a joint measurement of the plot of land for such purpose with the

petitioner to ascertain the actual quantum of the plot of land and for fixing of

poles for the purpose of actual demarcation of the plot of land and requested him

to be present himself personally or through his authorized representative on

15.06.2001 at 12 hours. It appears that on the stipulated date actual measurement

of the plot of land was undertaken in presence of the parties and the parties duly

signed the sketch map. On the self same date, Omprakash Singh filed a writ

petition being W.P. No. 10445 (W) of 2001, inter alia, challenging the tender

process.

A learned Single Judge of this Court was pleased to pass an interim order

directing the respondents not to give any further effect to the tender for a period

of three weeks. The respondents filed an application praying for vacating of the interim order passed by the Hon'ble Single Judge. By order dated 12th July, 2001

an Hon'ble Single Judge was pleased to allow the aforesaid writ petition filed by

Omprakash Singh directing the respondent authorities not to give effect to the

earlier tender and to initiate fresh tender process by publishing proper notice.

HIT called upon the petitioner to withdraw earnest money deposited by him.

The petitioner preferred an appeal being F.M.A. No. 187 of 2003 against the

judgement and order dated 12th July, 2001 passed by the Hon'ble Single Judge. A

Hon'ble Division Bench of this Court by judgement and order dated 17th October,

2001 admitted the appeal and granted stay of operation of the order passed by

the learned Single Judge till disposal of the appeal. Finally, by judgement and

order dated 27.07.2010 the said intra court appeal being F.M.A. No. 187 of 2003

preferred by the petitioner was dismissed and the judgement and order of the

Hon'ble Single Judge was upheld. Thereafter, HIT issued fresh notice inviting

tender for sale of the plot. Highest bid submitted was about Rs. 46,01,000/‐ per

cottah.

The petitioner preferred a Special Leave Petition before the Hon'ble

Supreme Court being SLP (Civil) No. 24285 of 2010. The SLP was admitted and

was converted into Civil Appeal No. 9364 of 2013. By judgement and order dated

21.10.2013 the Hon'ble Supreme Court set aside the orders passed by the learned

Single Judge and the Hon'ble Division Bench of this Court, inter alia, holding

that as the offer of the petitioner, pursuant to the notice inviting tender, had been

accepted, the notice inviting tender could not have been cancelled at that stage.

The Apex Court, however, made it clear that it was not expressing any opinion

on the merits of the claim of the petitioner or HIT with regard to the question as to whether or not there is a binding contract for sale of the plot of land in

question. Thereafter the petitioner by notice dated 28.11.2013 called upon HIT for

completion of the transaction and execution of the deed of conveyance of the plot

of land in his favour at an early date. The petitioner along with a letter

forwarded the documents and Pay Order of the balance consideration amount to

the tune of Rs. 24,88,000/‐ .

In view of the fact that circumstances have substantially changed and the

value of the plot of land had exorbitantly increased in the last 12‐13 years, HIT

called upon the petitioner to deposit balance consideration at the market rate and

as the petitioner refused to do so, HIT issued impugned notice inviting tender

dated 24.12.2013 in respect of the said plot of land.

Under such circumstances the petitioner moved the instant writ petition

challenging the impugned notice inviting tender dated 24.12.2013 and praying

for a direction upon HIT to accept the balance consideration money and execute

the registered deed of conveyance in favour of the petitioner in respect of the

plot of land.

HIT opposed the writ petition and filed affidavit‐in‐opposition thereto. It

is the specific case of HIT that after the tender process was set aside by a learned

Single Judge of this Court on 12.07.2001 in WP no.10445 (W) of 2001 they had

informed the petitioner to withdraw the application money. It was further

pleaded that the lapse of 12‐13 years in the meantime had substantially changed

the circumstances relating to the plot of land including exponentially increasing

the value thereof and it would operate against public interest and cause loss to

public exchequer to direct conveyance of the plot of land at the price offered by the petitioner in 2001. He was offered to replenish loss to the exchequer and

purchase the plot of land at the market price. Since he refused to do so, HIT was

constrained to issue notice inviting tender. It was also pleaded that delay in the

transaction was not attributable to HIT and the latter ought not to be penalised

for the same.

Mr. Dutta, Learned Senior Counsel appearing for the petitioner submitted

that a concluded contract for sale had come into being by HIT accepting the offer

of the petitioner to purchase the plot of land at the rate of Rs.6,40,000/‐ per cottah.

He further submitted that the petitioner was always ready and willing to

perform his obligations under the contract but was precluded from enforcing the

contract till the orders passed by the Hon'ble Division Bench and the Learned

Single Judge of this Court in FMA no.187 of 2003 and WP no.10445 (W) of 2001

respectively were not set aside by the Apex Court. He submitted that escalation

of price of the plot of land in the meantime is no legitimate ground to deny him

relief by purchase of the plot of land at the rate accepted by HIT. HIT acted

illegally and contrary to the terms of the concluded contract in issuing the notice

inviting tender and refusing to accept the balance consideration money and

execute the sale deed in terms of the agreement entered by and between them in

respect of the plot of land.

Mr. Ashok Banerjee, learned Senior counsel appearing for HIT at the

outset submitted that the writ petition was not maintainable in the facts of the

case. The petitioner was seeking to enforce a contractual obligation and cannot be

granted relief in public law domain. He ought to have filed a suit for such relief.

Without prejudice to the aforesaid he submitted that there was no

concluded contract by and between the parties. Letter dated 12.07.2001 was

merely an arrangement between the parties to enter into a formal contract for

sale. The same did not give rise to any legal right to the petitioner to seek

conveyance of the plot of the land at the rate offered by him in 2001. He

submitted that the Apex Court in its order dated 21.10.2013 had clarified that it

had not expressed any opinion that a concluded contract had come into being.

He further submitted HIT cannot be held responsible for the delay in the

instant case. He submitted that in view of the passage of time and bearing in

mind the public interest and loss to public exchequer, HIT took a decision to

issue a fresh notice inviting tender. Such action of HIT cannot be said to be

unfair, arbitrary or whimsical so as to be set aside in judicial review.

First let me consider whether the writ petition is maintainable for the

reliefs, as claimed.

In the instant case I find that writ petitioner is seeking to enforce his rights

under the agreement which he claims to constitute a concluded contract for sale

of the plot of land. No objection was raised as to the maintainability of the writ

petition at the stage of its admission. Affidavits were exchanged and the matter

is at the stage of final hearing. In ABL International Ltd. & Anr. Vs. Export

Credit Guarantee Corporation of India Ltd. & Ors., (2004) 3 SCC 553, the Apex

Court held that if a State acts in an arbitrary manner even in a matter of contract

an aggrieved person can approach the Court by way of a writ petition under

Article 226 of the Constitution and the Court depending on the facts of the said

case is empowered to grant relief. No disputed questions of fact arise in this case.

It is trite law that alternative remedy by way of a suit is not an absolute

bar and bearing in mind the matured stage of the proceeding I am not inclined to

relegate the petitioner to the alternative remedy of a suit but proceed to decide

the matter on merits.

Issues which crop up for decision on merits in the instant case are (1)

whether there is a concluded contract for sale of the plot of land in question; (2) if

so, whether petitioner is entitled to the reliefs as prayed for in the writ petition?

By letter dated 07.06.2001 the petitioner was intimated by HIT that his

offer for purchase of the plot of land at the rate of RS. 6.40 lakhs per cottah was

accepted. In the selfsame letter, HIT intimated the petitioner that joint

measurements for ascertaining actual quantum of plot of land to be transferred

in his favour as per terms and conditions of the tender would be undertaken on

15.06.2001 at 12 noon in the presence of both the parties. Thereafter joint

inspection was held on 15.06.2001 for measurement of the actual quantum of plot

of land. The writ petitioner had already deposited earnest money in respect of

the said offer. On the selfsame date, writ petition being W.P. No. 10445 (W) of

2001 was moved by an unsuccessful bidder, namely Omprakash Singh

challenging the tender process. Stay order was passed by the learned Single

Judge not to give further effect to the tender. It has been argued on behalf of the

writ petitioner that in the vacating application preferred by HIT praying for

vacating of the said interim order, it was the specific stance of HIT that the offer

of the writ petitioner had been finally accepted and joint measurement was

completed. Reference was made to the pleadings in the said vacating application.

It was also argued that the Apex Court observed in its order that the offer of HIT was duly accepted and hence there was no question of quashing the tender

process at that stage.

Mr. Banerjee, Senior Counsel has strenuously argued that pleading in the

earlier petition cannot bind HIT. He referred Smt. Krishnawati Vs. Shri Hans

Raj, AIR 1974 SC 280. He further submitted that after delivery of judgement by

the learned Single Judge cancelling the tender process, HIT had offered to return

the earnest money of the petitioner and on 07.08.2010 had issued fresh notice

inviting tender for sale of the plot of land wherein it had received highest offer of

around Rs. 46 lakhs per cottah in respect of the plot of land.

Mr. Dutta submitted that acceptance of reciprocal promises is sufficient in

law to form a binding contract. He further submitted that acceptance of an offer

may be inferred by the conduct of the offeree which would constitute an

agreement sub silentio. He relied on Pankaj Bhargava & Anr. Vs. Mohinder

Nath & Anr. (1991) 1 SCC 556 (para 12), Bharat Petroleum Corporation Ltrd. Vs.

Great Eastern Shipping Co. Ltd., (2008) 1 SCC 503 (Para 19) in support of his

contention.

I find that HIT by letter dated 07.06.2001 had unequivocally stated that it

accepted the offer of the petitioner and had expressed his desire to hold joint

measurements in order to determine the actual quantum of the plot of land to be

conveyed to him. Accordingly, joint measurements were also held on 15.06.2001.

Petitioner had already deposited earnest money with HIT in respect of the

aforesaid offer. Thereafter no further steps were undertaken by the parties as

they were injuncted by this Court in the earlier writ petition instituted by an

unsuccessful tenderer, namely, Omprakash Singh.

In the vacating application filed in the said writ proceeding, HIT took a

stance that the offer of the petitioner had been finally accepted and that joint

measurements to convey the actual quantum of the plot of land to the petitioner

had also been undertaken. In Smt. Krishnawati (supra) it has been held that

previous self serving statement by a party in other proceeding cannot be used as

substantive evidence in subsequent proceeding against that party. Writ Petition

being No. 10445 (W) of 2001 instituted by Om prakash Singh challenging the self

same tender process cannot be said to be "other proceeding" in the sense as

referred in the cited decision vis a vis in the instant case. The subject matter of

challenge in the earlier proceeding was the same tender process wherein the

offer in question was accepted by HIT. Both petitioner and HIT were parties in

the earlier proceeding. Such proceeding therefore is a precursor to the present

writ petition and cannot be held to be a wholly unconnected proceeding.

Pleading of HIT therein clearly divulges the stances and intention of the

authority at that material point of time qua the offer of the petitioner. Hence,

there is no escape from the conclusion that in 2001, HIT had accepted the offer of

the petitioner for sale of the plot of land at the rate of Rs. 6.40 lakhs in accordance

with the terms and conditions of the tender and an agreement by and between

the parties had come into being.

However, after the judgement and order dated 12.07.2001, passed by the

learned Single Judge in W.P. No. 10455 (W) of 2001, HIT accepted the same and

called upon the petitioner to take back his application money. Petitioner declined

to do so and chose to prefer appeal against the said judgement and order of the

learned Single Judge before the Hon'ble Division Bench of this Court. After the appeal preferred by the petitioner was dismissed by the Hon'ble Division Bench

on 27th July, 2010, HIT issued fresh notice inviting tender on 07.08.2010 for sale of

the said plot of land as supervening circumstances and inordinate delay had

resulted in exponential rise in market price of the plot.

The petitioner filed Special Leave Petition against the judgement and

order passed by the Hon'ble Division Bench which was finally allowed by the

Apex Court by order dated 21.10.2013, whereby the orders of the Hon'ble

Division Bench and the learned Single Judge setting aside the earlier tender

process, were quashed. The Apex Court, however, clarified that it is expressing

no opinion that concluded contract had come into being in between the parties.

Under such circumstances, when the petitioner called upon HIT by letters dated

07.08.2013 and 20.08.2013 to accept the balance consideration money and execute

the deed of conveyance, HIT asked the petitioner to pay balance consideration

money in terms of the current market rate. As the petitioner refused to do so, it

rescinded the contract and proceeded to issue the impugned notice inviting

tender on 24.12.2013, inviting offers for purchase of the plot of land.

Mr. Dutta argued that as the offer of the petitioner had been accepted and

a binding agreement had come into being it was not open to HIT to rescind the

contract and invite fresh tender on the ground of escalation of market price of the

plot of land in question. He accordingly prayed for setting aside of the impugned

notice inviting tender and a direction on HIT to execute sale deed in favour of his

client at the rate agreed pursuant to its letter dated 07.06.2001. He submitted that

inadequacy of price is not a relevant ground to avoid specific performance of an

agreement for sale. He referred to Section 20 of the Specific Relief Act, 1963. He submitted that the petitioner was always ready and willing to perform his part of

the contract and was not in a position to enforce the same till the orders passed

by the Hon'ble Division Bench and the learned Single Judge in the earlier writ

proceeding were set aside. He submitted that such fact has been accepted by the

Supreme Court it its order dated 21.10.2013 while disposing of Civil Appeal No.

9364 of 2013. He referred to S.V.R. Mudaliar (Dead) by Lrs. & Ors. Vs. Rajabu

F. Buhari (Mrs.) (Dead) by Lrs. & Ors., (1995) 4 SCC 15 (para 27), Narinderjit

Singh Vs. North Star Estate Promoters Ltd., (2012) 5 SCC 712 (para 25), Union

of India Vs. Hariram Shamji Thakkar & Ors., (1974) UJ (SC) 562 (para 16) in

support of his contention that mere escalation of price cannot be constituted

construed to constitute 'undue hardship' on the part of the vendor to resist

specific performance of an agreement for sale.

Mr. Banerjee on the other hand, submitted that supervening circumstances

had intervened necessitating the HIT to take a decision to issue fresh tender so

that there is maximization of returns to the public exchequer. Such decision was

taken bearing in mind public interest and the wholesome purpose of

aggrandizement of public exchequer through auction of public property.

Decision of HIT was therefore fair, bonafide and in consonance to public good.

Public good must override private interest and in case of conflict, the Court in

exercise of its discretionary jurisdiction may refuse to grant the relief of specific

performance.

In response, Mr. Dutta submitted that State in the contractual field is

bound by the same obligations as a private party. He relied on Bareilly

Development Authority Vs. Vrinda Gujarati & Ors., (2004) 4 SCC 606 (para 15). It was argued that there was no justification for rescission of the concluded

contract by HIT. Reference was made to Kumar Dhirendra Mullick & Ors. Vs.

Tivoli Park Apartments (P) Ltd., (2005) 9 SCC 262 (Para 18).

It appears that in view of supervening circumstances arising out of

inordinate delay in executing the agreement with the petitioner due to factors

beyond the control of the parties and exponential increase in the market price of

the plot, HIT decided to go for re‐tender to ensure maximum returns to public

exchequer through auction of public assets.

The question is whether such action of HIT to rescind the contract entered

with the petitioner in 2001 and seek re‐tender of the plot is a reasonable one.

In ITC Ltd. Vs. State of Uttar Pradesh & Ors., (2011) 7 SCC 493 the Apex

Court was called upon to decide the issue of rescission of a contract which had

been erroneously entered into by a statutory authority causing loss to public

exchequer.

Drawing a distinction between the contractual obligations of a private

party qua a public authority entering the field of contract, the Apex Court held as

follows : ‐

"105. If after effecting a transfer, the transferor finds that he had stipulated a lesser consideration (sale price or lease premium) for the transfer, due to a mistake of fact or wrong understanding or misreading of any law (and such mistake was not caused on account of any fraud, coercion or misrepresentation by the transferee) what is the remedy of the transferor? In private law, the transferor may have no remedy, as completed transactions of transfers cannot be re‐opened or cancelled.

106. A `transferʹ of property is an executed contract. Section 4 of Transfer of Property Act, 1882 provides that the chapters and sections of that Act relating to contracts, shall be taken as part of the Indian Contract Act, 1872. Section 20 of Contract Act provides that :

"20. Agreement void where both parties are under mistake as to matter of fact. ‐ Where both the parties to an agreement are under a mistake as to a matter of fact essential to the agreement, the agreement is void."

But the Explanation thereto provides that:

"Explanation.‐ An erroneous opinion as to the value of the thing which forms the subject matter of the agreement is not to be deemed a mistake as to a matter of fact."

Section 21 of Contract Act provides that a contract is not voidable because it was caused by a mistake as to any law in force in India. Therefore, having regard to the provisions of Transfer of Property Act and Contract Act, a transfer can not be cancelled on the ground that parties were mistaken about the consideration.

107. The position is however different in public law. Breach of statutory provisions, procedural irregularities, arbitrariness and mala fides on the part of the Authority (transferor) will furnish grounds to cancel or annul the transfer. But before a completed transfer is interfered on the ground of violation of the regulations, it will be necessary to consider two questions. The first question is whether the transferee had any role to play (fraud, misrepresentation, undue influence etc.) in such violation of the regulations, in which event cancellation of the transfer is inevitable.

107.1. If the transferee had acted bona fide and was blameless, it may be possible to save the transfer but that again would depend upon the answer to the further question as to whether public interest has suffered or will suffer as a consequence of the violation of the regulations:

(i) If public interest has neither suffered, nor likely to suffer, on account of the violation, then the transfer may be allowed to stand as then the violation will be a mere technical procedural irregularity without adverse effects.

(ii) On the other hand, if the violation of the regulations leaves or likely to leave an everlasting adverse effect or impact on public interest (as for example when it results in environmental degradation or results in a loss which is not reimbursable), public interest should prevail and the transfer should be rescinded or cancelled.

(iii) But where the consequence of the violation is merely a short‐recovery of the consideration, the transfer may be saved by giving the transferee an opportunity to make good the short‐fall in consideration.

107.2. The aforesaid exercise may seem to be cumbersome, but is absolutely necessary to protect the sanctity of contracts and transfers. If the government or its instrumentalities are seen to be frequently resiling from duly concluded solemn transfers, the confidence of the public and international community in the functioning of the government will be shaken. To save the credibility of the government and its instrumentalities, an effort should always be made to save the concluded transactions/transfers wherever possible, provided (i) that it will not prejudice the public interest, or cause loss to public exchequer or lead to public mischief, and (ii) that the transferee is blameless and had no part to play in the violation of the regulation.

107.3. If the concluded transfer cannot be saved and has to be cancelled, the innocent and blameless transferee should be reimbursed all the payments made by him and all expenditure incurred by him in regard to the transfer with appropriate interest. If some other relief can be granted on grounds of equity without harming public interest and public exchequer, grant of such equitable relief should also be considered."

In the instant case HIT had accepted the bid of the appellant at a rate

which it considered reasonable in 2010. Litigations intervened at the behest of an

unsuccessful tenderer and the same continued upto the Apex Court till 2013.

Hence, delay in non‐performance of the aforesaid agreement with the petitioner

was not due to the fault of HIT. On the other hand, after the tender process was

set aside by the learned Single Judge in the earlier writ proceeding HIT offered to

refund the earnest money of the petitioner when such order was upheld by the

Hon'ble Division Bench of this Court. HIT took a decision to re‐tender the plot of

land in question in 2010. However, the Apex Court quashed the orders passed by

the Hon'ble Division Bench and the learned Single Judge setting aside the tender

process on the premise that a tender process could not have been called into

question after the offer had been accepted by the authority. The Apex Court however kept the question as to whether there was a concluded contract for sale

between the parties open for decision.

In the meantime the value of the property has gone up exponentially. In

fact in 2010 the highest offer received by HIT in respect of the plot of land was

about 46.1 lakhs per cottah. HIT has fixed such sum as the base price in the

impugned notice inviting tender in 2013 after giving an option to the petitioner

to purchase the plot at market rate. Decision of HIT to cancel the tender in order

to achieve maximum returns from auction of public assets cannot be said to be

contrary to public good or public interest.

Right of the petitioner to seek specific performance of the contract for sale

is an equitable right which may be exercised after balancing the equities qua the

parties to the contract. Overwhelming public good in maximizing return by way

of auction of public assets at the highest price is a relevant consideration in

respect of sale of public assets, particularly when delay in effecting the sale,

cannot be attributed to the State or its functionaries. The present case is not one

where the State by way of procrastination or indifference had held up the

performance of the contract and now is trying to refuse specific performance

thereof under the guise of escalation of price. In Barielly Development

Authority (supra) issue of loss of public exchequer did not fall for decision as a

relevant consideration for enforcement of contractual obligation.

It is true ordinarily inadequacy of price is not to be construed as 'undue

hardship' to a vendor to avoid a concluded contract and any increase in price in

the meantime ought to enure to the vendee. However, in ITC Ltd. (supra) the Apex Court held that parameters applicable to a public authority while

rescinding a contract in public interest to avoid loss to public exchequer is

somewhat different. It must be borne in mind that Courts in India have

recognised the bounden duty of the State as a trustee of public assets vested in it.

"Public trust" principles therefore enjoin upon the State a pious duty to

maximize returns to exchequer from auction of such assets. Such duty is not

enjoined on a private party whose obligations are governed simpliciter by the

terms of the contract.

Judged from this angle, rescission of the agreement by HIT entered with

the petitioner in 2001 due to exorbitant escalation of the value of the plot, in

exercise of its 'public trust' responsibility to fetch maximum price from auction

of such plot cannot be said to be unjustified. Ratios in the cited cases deal with

adjudication of rights of private parties in contractual domain where the issue of

public interest and loss to public exchequer do not fall for consideration as

relevant factor to constitute 'undue hardship' to the vendor as a ground to resist

the prayer for specific performance. In Union of India Vs. Hariram (supra) the

title in movable goods had already passed to the buyers unlike the present case

which relates to immovable property.

Duty of the State to ensure maximum return to exchequer from sale of

public assets, in the realm of public law, is a relevant consideration which ought

to be borne in mind while fashioning discretionary relief relating to disposal of

such public assets/largesse. Delay in executing the agreement for sale of the plot

in the instant case does not fall at the doorstep of the public authority. Prayer for

specific performance is not a legal right of a party to the contract but is a

discretion of the Court to be decided on equitable principles. Public interest

arising out of maximization of returns to public exchequer is a relevant consideration to be kept in mind while considering such discretionary relief and

the same would naturally eclipse the private claim of the petitioner to enforce the

contract at a rate prevailing in 2001.

In view the aforesaid discussion, I am of the opinion that the decision of

HIT to rescind the agreement with the petitioner and issue fresh notice inviting

tender to maximize the returns to the public exchequer by auction of the plot of

land at the prevalent market price cannot be said to be arbitrary, unreasonable or

unjust so as to necessitate interference in judicial review. Petitioner is entitled to

the alternative relief of refund of earnest money along with interest at the rate of

10% per annum from the date of its deposit till its payment. Writ petition is

accordingly disposed of directing HIT to refund earnest money of the petitioner

along with interest 10% per annum thereon from the date of its deposit till

repayment within 15 days from date.

The parties shall, however, bear their respective costs.

Later :

Mr. Kishore Dutta, learned senior counsel appearing on behalf of the

petitioner prays for stay of operation of the order.

Let status quo in respect of plot of land prevail till 30th October, 2014.

(Joymalya Bagchi, J.)

P.A. to J. Bagchi, J.

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free