Miss Lucy
← All judgments

Devendra Kumar Tyagi & Ors vs State Of U.P. & Ors

Supreme Court23 August 2011H.L. Dattu · G.S. Singhvi

Ratio decidendi

The rule this decision rests on

(1) Where a notification under Section 4 of the Land Acquisition Act, 1894 is published in two daily newspapers in the regional language and circulates in the locality where the land is situated, and the people in that locality are well conversant with that language, such publication constitutes sufficient and complete compliance with Section 4(1) of the Act. Subsequent publication of the notification in English translation does not extend or restart the period of limitation prescribed by the proviso to Section 6(1) for making a declaration. The period of limitation for declaring acquisition under Section 6 commences from the date of last publication satisfying the statutory requirement of Section 4(1), and a declaration made beyond one year from that date is time-barred. (2) Acquisition of land for public purpose by itself does not justify the invocation of urgency provisions under Sections 17(1) and 17(4) of the Land Acquisition Act, 1894. The urgency provisions can be invoked only where the purpose cannot brook delay of even a few weeks or months, and where delay of that duration would frustrate the public purpose in all probability. Where the government machinery has functioned at a slow pace both before and after issuing the notification under Section 4—such as a gap of two years before issuing Section 4 notification and a gap of more than seventeen months between Section 4 and Section 6 notifications—the conduct demonstrates absence of real urgency and lack of justification for excluding the application of Section 5-A of the Act. (3) For a project located in the National Capital Region, acquisition of land cannot proceed without prior approval of the NCRPB in terms of Section 19(2) of the National Capital Region Planning Board Act, 1985. Section 27 of that Act has overriding effect over inconsistent provisions in any other law, and Section 29 prohibits any development activity inconsistent with the Regional Plan. Acquisition proceedings undertaken in the absence of such statutory approval are illegal and vitiated.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL ORIGINAL JURISDICTION
WRIT PETITION (CIVIL) NO. 66 OF 2007

Devender Kumar Tyagi & Ors. .............. Petitioners

versus

State of U.P. & Ors. ...........Respondents

WITH

WRIT PETITION (CIVIL) NO. 67 OF 2007

Jai Prakash Tyagi & Ors. .............. Petitioners

versus

State of U.P. & Ors. ...........Respondents

J U D G M E N T

H.L. Dattu, J.

1) The petitioners have filed this writ petition under

Article 32 of the Constitution of India, inter alia,

challenging the Notification dated 03.7.2006 issued under

Section 4 and the Notification dated 18.12.2007 issued under

Section 6 of the Land Acquisition Act, 1894 (hereinafter

referred to as "the LA Act") for acquiring their lands for a

planned development of the Leather City Project in order to

relocate bone mills and allied industries by invoking the

urgency provisions under Section 17(1) and 17(4) of the LA

Act.

2) This Court is monitoring the re-location of the bone

mills and allied industries in the various parts of State of

Uttar Pradesh including the district of Ghaziabad in the

public interest proceedings, which were initiated in the year

1994. Since then, this Court has time and again issued

various orders and directions including inspection of

polluting bone industries in Ghaziabad by the U.P. Pollution

Control Board (hereinafter referred to as "the UPPCB") and

Central Pollution Control Board (hereinafter referred to as

"the CPCB"). This Court, vide its Order dated 17.08.2004 in

the Civil Appeal No. 3633-3634 of 1999 (U.P. Pollution

Control Board v. Anil K. Karnwal & Ors.), which is still

pending before us, had directed the respondents to relocate

the bone mills and allied industries as per the

recommendations of the CPCB and further directed the

2

respondents to identify the definite area suitable for

relocation of the said industries. Pursuant to this Order, the

respondents had filed an affidavit before this Court in the

month of December, 2004, inter alia, proposing the Leather

City Project for relocation of the said bone industries.

3) In this backdrop, the respondents had issued a

Notification dated 03.7.2006 under Section 4 read with

Section 17 (4) of the LA Act for acquisition of 28.804

hectares of the land at village Imtori, Chitoli, Sabli of Hapur-

Pargana in the district of Ghaziabad for the public purpose of

planned development of the Leather City Project by

invoking the urgency provision under the LA Act, thereby,

dispensing with inquiry under Section 5-A of the LA Act.

The same was published in two daily Hindi newspapers on

04.07.2006. Subsequently, the English version of the said

Notification was also published in two daily newspapers

dated 24.01.2007. The relevant part of the Notification is

extracted below:

"The Governor is pleased to order the publication

of the following English translation of Notification

No. 1588/VIII-3-2006-183 LA-2005, dated July 03,

2006:

No. 1588/VIII-3-2006-183 LA-2005

3

Dated Lucknow, July 3, 2006

Under subsection (1) of section 4 of the Land

Acquisition Act, 1894 (Act No. 1 of 1894), the

Governor is pleased to notify for general

information that the land mentioned in the

schedule below is needed for the public purpose

namely, for construction of Leather City Scheme at

Villages-Chitoli, Sabli and Imtori, Pargana-Hapur,

district-Ghaziabad by the Hapur-Pilkhuwa

Development Authority, Hapur.

The Governor being of the opinion that provisions

of subsection (1) of section 17 of the said Act are

applicable to the said land in as much as the said

land is urgently required for construction of

Leather City Scheme at Villages-Chitoli, Sabli and

Imtori, Pargana-Hapur, district-Ghaziabad by the

Hapur-Pilkhuwa Development Authority, Hapur

under planned development Scheme, it is as well

necessary to eliminate to delay likely to be caused

by an enquiry under section 5-A of the said Act the

Governor is further pleased to direct, under

subsection (4) of section 17 of said Act, that the

provisions of section 5-A shall not apply."

4) Thereafter, the respondent had issued a Notification

dated 18.12.2007 under Section 6 read with Section 17 (1) of

the LA Act, whereby, it directed the Collector of Ghaziabad

to take possession of the said land on the expiry of 15 days

from the date of publication of the Notice under Section 9(1)

even though no award has been made under Section 11. The

same was published in two newspapers on 05.01.2008. The

relevant portion of the Notification is extracted below:

4

"The Governor is pleased to order the publication

of the following English translation of notification

No. 2647/VIII-3-2006-136L.A.-2006, dated

September 18, 2006:

No. 2647/VIII-3-2006-136L.A.-2006

Dated Lucknow, September 18, 2006

UNDER, sub-section (1) section 4 of the Land

Acquisition Act, 1894 (Act No. 1 of 1894) the

Governot is pleased to notify for general

information that the land mentioned in the schedule

below, is needed for a public purpose namely for

construction of planned Leather City scheme at

village Rampur, Paragana Hapur, District

Ghaziabad by the Hapur Pilkhuwa Development

Authority, Hapur.

2. The Governor, being of the opinion that

the proivision of sub-section (1) of section 17 of the

said Act are applicable to the said land in as much

as the said land is urgently required, for the

construction of planned Leather City scheme at

village Rampur, Paragna Hapur, District

Ghaziabad by the Hapur Pilkhuwa Development

Authority, Hapur under planned development

scheme, it is as well necessary to eliminate the

delay likely to be caused by an inquiry under

section 5A of the said Act. The Governor is further

pleased to direct under sub-section (4) of section 17

of the said Act that the provisions of section 5A of

the said Act shall not apply."

5) Since the Petitioners' land situated at Hapur is included in

these Notifications, the petitioners have filed present Writ

Petition under Article 32 of the Constitution praying for

issuance of appropriate writ or directions to quash these

5

Notifications issued under Section 4 and Section 6 of the LA

Act.

6) In this Writ Petition, the issues before us are :

I. Whether the Notification dated 18.12.2007 issued by the

respondents under Section 6 read with Section 17 (1) of the LA

Act is within the period of limitation as contemplated by

proviso (ii) to Section 6 (1) of the LA Act.

II. Whether the respondent is justified in invoking the urgency

provision under Section 17(1) and excluding the application of

Section 5-A in terms of Section 17(4) of the LA Act for

acquisition of the land for the development of the Leather City

Project.

7) Mrs. Pinky Anand, the learned senior counsel for the

petitioners, submits that declaration of Notification dated

18.12.2007 under Section 6 is beyond the period of limitation of

one year from the date of the publication of Notification under

Section 4, as mandated by proviso (ii) to Section 6(1) of the LA

Act. In other words, she submits that respondents had failed to

make the declaration of Notification under Section 6 within a

6

period of one year starting from the last date of publication of

Notification under Section 4 in two newspapers as contemplated

by Section 4(1) of the LA Act. The learned senior counsel would

argue that the publication of Notification under Section 4 in two

newspapers in the Hindi language on 04.07.2006 was sufficient

compliance of Section 4(1) of the LA Act in order to commence

the period of limitation for the purpose of proviso (ii) to Section

6(1) of the LA Act from the said date. In other words, she

contends that since the people residing at Hapur, Ghaziabad are

well conversant and acquainted with the Hindi language, the

publication of the Notification under Section 4 in two newspapers

in the Hindi language on 04.07.2006 duly fulfils the requirement

of the publication of the Notification as contemplated by Section

4(1) of the LA Act. Therefore, the period of limitation for

declaration of Notification under Section 6 would commence

from 04.07.2006 and not from the date of subsequent publication

of the said Notification under Section 4 on 24.1.2007. She

submits that the declaration of Notification dated 18.12.2007

under Section 6 by the respondents is made after the expiry of

one year and is beyond the period of limitation in terms of the

proviso to Section 6 (1) of the LA Act. In other words, the period

of limitation commences from date of completion of the

7

necessary requirement of publication as contemplated by Section

4(1) of the LA Act. She further submits that in view of this, the

acquisition proceedings are vitiated and should be set aside.

8) Per Contra, Shri. Pallav Sisodia, learned senior counsel for

the respondents, submits that the declaration of Notification

under Section 6 of the LA Act is well within the period of

limitation of one year starting from the date of the last publication

of the Notification under Section 4 of the LA Act, as mandated

by proviso to Section 6(1) of the LA Act. He further submits that

it is amply clear that the last date of publication of the

Notification under Section 4 would be treated as the date of

publication of the said Notification for all purposes in terms of

Section 4(1) of the LA Act. He states that the respondents, after

publishing the Notification under Section 4 on 4.07.2006 in the

regional language, that is, Hindi, had also published the said

Notification in English language on 05.01.2007. In this regard,

the learned senior counsel argues that the period of limitation of

one year in terms of proviso to Section 6(1) of the LA Act would

commence only from 05.01.2007, that is, the date of the last

publication of the Notification under Section 4 of the Act. He

further submits that the proviso to Section 6(1) refers only to the

8

declaration of the Notification under Section 6 within the period

of one year from the date of publication of the Notification under

Section 4 of the LA Act and not the publication of the declaration

under Section 6 (2). In other words, the proviso to Section 6(1)

whilst prescribing the period of limitation, only refers to the

declaration under Section 6, which is in the nature of order and

excludes the publication of the declaration from its ambit.

Therefore, the subsequent publication of declaration of

Notification under Section 6 will not be taken into consideration

in order to calculate the period of limitation in terms of proviso to

Section 6(1) of the LA Act. The learned senior counsel, in

support of his contention, has placed reliance on the decisions of

this Court in S.H. Rangappa v. State of Karnataka & Anr., (2002)

1 SCC 538 and Sriniwas Ramnath Khatod v. State of

Maharashtra & Ors., (2002) 1 SCC 689.

9) To appreciate the point in issue, it would be appropriate to

set out relevant portion of Sections 4(1) and 6 of the LA Act.

"4. Publication of preliminary notification and

powers of officers thereupon.--(1) Whenever it

appears to the appropriate Government that land in

any locality is needed or is likely to be needed for

any public purpose or for a company, a notification

to that effect shall be published in the Official

Gazette and in two daily newspapers circulating in

9

that locality of which at least one shall be in the

regional language and the Collector shall cause

public notice of the substance of such notification

to be given at convenient places in the said locality

(the last of the dates of such publication and the

giving of such public notice, being hereinafter

referred to as the date of the publication of the

notification).

* * *

6. Declaration that land is required for a public

purpose.--(1) Subject to the provisions of Part VII

of this Act, when the appropriate Government is

satisfied, after considering the report, if any, made

under Section 5-A sub-section (2), that any

particular land is needed for a public purpose, or

for a company, a declaration shall be made to that

effect under the signature of a Secretary to such

Government or of some officer duly authorised to

certify its orders and different declarations may be

made from time to time in respect of different

parcels of any land covered by the same

notification under Section 4 sub-section (1),

irrespective of whether one report or different

reports has or have been made (wherever required)

under Section 5-A sub-section (2):

Provided that no declaration in respect of any

particular land covered by a notification under

Section 4 sub-section (1),--

(i) published after the commencement of the

Land Acquisition (Amendment and Validation)

Ordinance, 1967, but before the commencement of

the Land Acquisition (Amendment) Act, 1984, shall

be made after the expiry of three years from the

date of the publication of the notification; or

(ii) published after the commencement of the

Land Acquisition (Amendment) Act, 1984, shall be

made after the expiry of one year from the date of

the publication of the notification:

10

Provided further that no such declaration shall be

made unless the compensation to be awarded for

such property is to be paid by a company, wholly or

partly out of public revenues or some fund

controlled or managed by a local authority.

2) Every declaration shall be published in the

Official Gazette, and in two daily newspapers

circulating in the locality in which the land is

situate of which at least one shall be in the regional

language, and the Collector shall cause public

notice of the substance of such declaration to be

given at convenient places in the said locality (the

last of the dates of such publication and the giving

of such public notice, being hereinafter referred to

as the date of the publication of the declaration),

and such declaration shall state the district or other

territorial division in which the land is situate, the

purpose for which it is needed, its approximate

area, and, where a plan shall have been made of

the land, the place where such plan may be

inspected.

(3) The said declaration shall be conclusive

evidence that the land is needed for a public

purpose or for a company, as the case may be; and,

after making such declaration, the appropriate

Government may acquire the land in manner

hereinafter appearing."

10) The Notification under Section 4 has to be published in the

manner laid down therein. As against this, under Section 6, a

declaration has to be first made and that declaration is then to be

published in the manner provided in Section 6(2) of the LA Act.

Also, the proviso (ii) to Section 6(1) lays down a time-limit

within which declaration has to be made. The said proviso (ii)

11

significantly only provides a time-limit for a declaration and not

for publication as it has been incorporated in sub-section (1) of

Section 6 of the LA Act.

11) It is not in dispute that the declaration of the Notification

under Section 6 was issued on 18.12.2007. It is also not in

dispute that the Notification under Section 4 was issued on

03.07.2006 and the same was published in two daily newspapers

in Hindi language on 04.07.2006 having circulation in the locality

where the land is situated. Also, the people at Pargana Hapur in

the Ghaziabad district are well conversant with the Hindi

language. In our considered view, the publication of the

Notification in two newspapers having circulation in the locality

where the land is situated and where people are well conversant

with Hindi amounts to ample compliance with the requirement of

the publication under Section 4(1) of the LA Act. In view of this,

the subsequent publication of English translation of the said

Notification under Section 4 in two newspapers on 05.01.2007 is

unnecessary and will not assist the respondents to extend the

period of limitation envisaged in the proviso to Section 6(1) of

the LA Act. Hence, the last date of publication for the purpose

Section 4(1) of the LA Act, which can be treated as date of

12

publication, is the date on which, the second Notification under

Section 4 was published in the newspaper, that is, 04.07.2006.

Therefore, the period of limitation commences from 04.07.2006,

which is the date of publication of the Notification under Section

4(1) of the LA Act. If the declaration under Section 6 of the LA

Act is made before the expiry of the period of one year starting

from 04.07.2006, then, only such declaration will be considered

as valid for the purpose of the acquisition of land. However, in

the present case, the declaration under Section 6 was issued on

18.12.2007 which is clearly beyond the period of limitation of

one year as mandated by the proviso to Section 6(1) of the LA

Act. Therefore, the declaration of Notification under Section 6

and its subsequent publications are clearly beyond the period of

limitation of one year starting from the date of publication of

Notification under Section 4 of the LA Act. In our opinion, due

to the aforesaid reasons, the reliance placed by Shri. Pallav

Sisodia, learned senior counsel for respondents, on the decisions

of this Court in S.H. Rangappa v. State of Karnataka & Anr.,

(2002) 1 SCC 538 and Sriniwas Ramnath Khatod v. State of

Maharashtra & Ors., (2002) 1 SCC 689 in support of his

contention that the proviso to Section 6(1) whilst prescribing

time-limit, contemplates and refers only to the date of declaration

13

and not publication under Section 6 of the LA Act will not come

to the rescue of the respondents.

12) The second point in issue before us is the invocation of the

urgency clause by the respondents to acquire the lands in dispute.

Mrs. Pinky Anand, learned senior counsel, submits that this Court

has issued direction to relocate the bone industries in Ghaziabad

vide its Order dated 17.08.2004, since then, the State Government

had not shown any kind of urgency and was only considering the

proposal of the Leather City Project in order to relocate the said

industries for public purpose as they were located in the dense

human habitation and causing environmental pollution and health

hazards. It was only in July, 2006 that the State Government had

issued the Notification under Section 4 on 3.7.2006, in

continuation with this, after the lapse of more than a year, the

State Government has issued Notification under Section 6 on

18.12.2007 by invoking urgency provision as contemplated by

Section 17(1) and 17(4) of the LA Act. In other words, the

lackadaisical attitude of the State Government since the direction

of this Court in 2004 nearly 2 years ago and in making the

declaration under Section 6 after the lapse of more than one year,

form the issuance of the Notification under Section 4 of the LA

14

Act does not exhibit or depict any kind of urgency but only

lethargy on their part in acquiring the lands. Therefore, the

urgency contemplated in the LA Act cannot be equated with

dereliction of responsibility on the part of the State Government.

The learned senior counsel contends that the respondents had

unnecessarily invoked the urgency provisions under

Section 17 (1) read with 17 (4) for the acquisition of the land for

construction of the Leather City Project in order to relocate the

said industries in view of the delay of two years in the issuance of

the Notification under Section 4 and delay of more than

seventeen months in making declaration under Section 6 from the

date of publication of the Notification under Section 4. The

learned senior counsel argues that the invoking of the urgency

provision under Section 17(4), which excludes the application of

the Section 5-A, by the respondents in the absence of any real

urgency as contemplated by Section 17 amounts to illegal

deprivation of the right to file objection and hearing of the

appellants and inquiry under Section 5-A of the LA Act. She

submits that an expropriatory legislation like the LA Act must be

given strict construction. She further submits that Section 5-A is a

substantial right and akin to fundamental right which embodies a

principle of giving of proper and reasonable opportunity to the

15

land loser to persuade the authorities against the acquisition of

their lands which can be dispensed with only in exceptional cases

of real urgency and not by side-wind. The learned senior counsel

also submits that the entire acquisition proceedings are vitiated as

the respondents have failed to obtain the approval of development

of the Leather City Project as a sub-regional plan under Section

19 of the National Capital Region Planning Board Act, 1985

(hereinafter referred to as "NCRPB Act"). She further submits

that such approval is mandatory in view of Section 27 of the

NCRPB Act, which has overriding effect on any other

inconsistent law or instrument.

13) Per contra, Shri. Pallav Sisodia, learned senior counsel for

respondents, submits that the bone mills and allied industries

were causing environmental pollution and health hazards to the

public at large in the district of Ghaziabad. This Court has issued

directions to relocate the said industries in accordance with the

recommendation of the CPCB. The State Government, in strict

compliance of the Order of this Court dated 17.08.2004, acquired

the lands for construction of the Leather City Project by invoking

the urgency provisions under Section 17 of the LA Act. He

further submits that in view of the said urgency, the State

16

Government had issued a Notification dated 3.4.2006 under

Section 4 of the LA Act for the acquisition of the said land for

public purpose of urgent construction of the Leather City Project

by invoking Section 17(4) of the LA Act in order to eliminate

delay likely to be caused by enquiry under Section 5-A of the LA

Act. The same was published in Hindi and English in two daily

newspapers on 4.03.2006 and 24.01.2007, respectively.

Subsequently, the State Government had issued the Notification

dated 18.12.2007 under Section 6 read with Section 17(1) of the

LA Act and published it in the newspapers dated 5.01.2008. The

learned senior counsel submits that there is no lethargy or

negligence on the part of the State Government to acquire the

said land. He contends that the construction of the Leather City

Project, in view of the pollution of environment caused by these

industries as observed by this Court, is an urgent matter requiring

acquisition of the land by invoking the urgency provisions under

Section 17(1) and Section 17(4), thereby, dispensing with the

enquiry under Section 5-A of the LA Act. The learned senior

counsel, by placing reliance on the decision of this Court in Jai

Narain and Ors. v. Union of India, (1996) 1 SCC 9, would argue

that the invoking of the urgency provisions is justified in a

situation where the entire acquisition proceedings are initiated in

17

compliance with the series of directions of this Court, which itself

indicates the existence of urgency in acquiring the land for

relocating the polluting industries. He further contends that the

right of the land owner for filing of objections and opportunity of

hearing under Section 5-A are subject to the provisions of Section

17 and the same can be legally curtailed in the event of any

pressing need and urgency for the acquisition of land in order to

eliminate delay likely to be caused by an enquiry under Section

5-A of the LA Act. The learned senior counsel further submits

that the Hapur Pilkhuwa Development Authority (hereinafter

referred to as "the HPDA") vide its resolution dated 19.04.2005,

has authorized the National Capital Region Planning Board

(hereinafter referred to as "the NCRPB") to prepare master plan

for Hapur containing the Leather City Project termed as Sub-

regional plan. Subsequently, the NCRPB in June, 2009, issued

draft Sub-regional plan but without indicating the Leather City

Project. Thereafter, the HPDA has made series of requests dated

27.08.2009, 18.08.2010 and 22.04.2011 to the NCRPB to include

the Leather City Project in its Sub-regional plan. The respondents

are keenly awaiting reply to these requests and hence, the grant of

approval is still pending. Arguendo, the learned senior counsel

submits that the Leather City Project pending approval of the

18

NCRPB will not adversely affect the acquisition of the Land in

any manner in view of the presence of the Chief Coordinator

Planner of the NCR Cell, Ghaziabad in almost all the meetings

wherein the Leather City Project has been discussed and

deliberated upon as he is a nominated member of the HPDA

Board vide the Government Order and the Office Memo dated

08.06.2004 and 26.05.2011, respectively, amounts to implied

consent or approval of the NCRPB.

14) We have heard the learned counsel for the parties before us.

The second point in issue before us is no more res integra as it

has already been decided by this Court in Radhy Shyam v. State

of U.P. (2011) 5 SCC 553, to which one of us was the party (G.S.

Singhvi, J.), wherein this Court has considered the development

of the jurisprudence and law, with respect to invoking of the

urgency provisions under Section 17 vis-`-vis right of the

landowner to file objections and opportunity of hearing and

enquiry under Section 5-A, by reference to a plethora of earlier

decisions of this Court. This Court had culled out the various

principles governing the acquisition of the land for public

purpose by invoking urgency thus:

19

"77. From the analysis of the relevant statutory

provisions and interpretation thereof by this Court

in different cases, the following principles can be

culled out:

(i) Eminent domain is a right inherent in every

sovereign to take and appropriate property

belonging to citizens for public use. To put it

differently, the sovereign is entitled to reassert its

dominion over any portion of the soil of the State

including private property without its owner's

consent provided that such assertion is on account

of public exigency and for public good --

Dwarkadas Shrinivas v. Sholapur Spg. and Wvg.

Co. Ltd., Charanjit Lal Chowdhury v. Union of

India and Jilubhai Nanbhai Khachar v. State of

Gujarat.

(ii) The legislations which provide for compulsory

acquisition of private property by the State fall in

the category of expropriatory legislation and such

legislation must be construed strictly -- DLF

Qutab Enclave Complex Educational Charitable

Trust v. State of Haryana, State of Maharashtra v.

B.E. Billimoria and Dev Sharan v. State of U.P.

(iii) Though, in exercise of the power of eminent

domain, the Government can acquire the private

property for public purpose, it must be

remembered that compulsory taking of one's

property is a serious matter. If the property

belongs to economically disadvantaged segment of

the society or people suffering from other

handicaps, then the court is not only entitled but is

duty-bound to scrutinise the LA Action/decision of

the State with greater vigilance, care and

circumspection keeping in view the fact that the

landowner is likely to become landless and

deprived of the only source of his livelihood and/or

shelter.

(iv) The property of a citizen cannot be acquired by

the State and/or its agencies/instrumentalities

without complying with the mandate of Sections 4,

5-A and 6 of the LA Act. A public purpose,

however, laudable it may be does not entitle the

State to invoke the urgency provisions because the

20

same have the effect of depriving the owner of his

right to property without being heard. Only in a

case of real urgency, the State can invoke the

urgency provisions and dispense with the

requirement of hearing the landowner or other

interested persons.

( v ) Section 17(1) read with Section 17(4) confers

extraordinary power upon the State to acquire

private property without complying with the

mandate of Section 5-A. These provisions can be

invoked only when the purpose of acquisition

cannot brook the delay of even a few weeks or

months. Therefore, before excluding the

application of Section 5-A, the authority concerned

must be fully satisfied that time of few weeks or

months likely to be taken in conducting inquiry

under Section 5-A will, in all probability, frustrate

the public purpose for which land is proposed to be

acquired.

(vi) The satisfaction of the Government on the

issue of urgency is subjective but is a condition

precedent to the exercise of power under Section

17(1) and the same can be challenged on the

ground that the purpose for which the private

property is sought to be acquired is not a public

purpose at all or that the exercise of power is

vitiated due to mala fides or that the authorities

concerned did not apply their mind to the relevant

factors and the records.

vii) The exercise of power by the Government

under Section 17(1) does not necessarily result in

exclusion of Section 5-A of the LA Act in terms of

which any person interested in land can file

objection and is entitled to be heard in support of

his objection. The use of word "may" in sub-

section (4) of Section 17 makes it clear that it

merely enables the Government to direct that the

provisions of Section 5-A would not apply to the

cases covered under sub-section (1) or (2) of

Section 17. In other words, invoking of Section

17(4) is not a necessary concomitant of the

exercise of power under Section 17(1).

21

( viii ) The acquisition of land for residential,

commercial, industrial or institutional purposes

can be treated as an acquisition for public

purposes within the meaning of Section 4 but that,

by itself, does not justify the exercise of power by

the Government under Sections 17(1) and/or 17(4).

The court can take judicial notice of the fact that

planning, execution and implementation of the

schemes relating to development of residential,

commercial, industrial or institutional areas

usually take few years. Therefore, the private

property cannot be acquired for such purpose by

invoking the urgency provision contained in

Section 17(1). In any case, exclusion of the rule of

audi alteram partem embodied in Sections 5-A(1)

and (2) is not at all warranted in such matters."

15) In view of the above it is well settled that acquisition of land

for public purpose by itself shall not justify the exercise of power

of eliminating enquiry under Section 5-A in terms of Section 17

(1) and Section 17 (4) of the LA Act. The Court should take

judicial notice of the fact that certain schemes or projects, such as

the construction of the Leather City Project for public purpose,

which contemplate the development of residential, commercial,

industrial or institutional areas, by their intrinsic nature and

character require the investment of time of a few years in their

planning, execution and implementation. Therefore, the land

acquisition for said public purpose does not justify the invoking

of urgency provisions under the LA Act. In Radhy Shyam

(Supra), this Court, whilst considering the conduct or attitude of

the State Government vis-`-vis urgency for acquisition of the

22

land for the public purpose of planned industrial development in

District Gautam Budh Nagar, has observed:

"82. In this case, the Development Authority sent

the proposal sometime in 2006. The authorities up

to the level of the Commissioner completed the

exercise of survey and preparation of documents by

the end of December 2006 but it took one year and

almost three months for the State Government to

issue notification under Section 4 read with

Sections 17(1) and 17(4). If this much time was

consumed between the receipt of proposal for the

acquisition of land and issue of notification, it is

not possible to accept the argument that four to five

weeks within which the objections could be filed

under sub-section (1) of Section 5-A and the time

spent by the Collector in making enquiry under

sub-section (2) of Section 5-A would have defeated

the object of the acquisition."

16) Moreover, in Dev Sharan & Others v. State of U.P. (2011)

4 SCC 769, the acquisition of land for the construction of a new

district Jail by invoking urgency provision under Section 17 was

quashed on the ground that the government machinery had

functioned at very slow pace after issuance of the Notification

under Section 4 in processing the acquisition proceedings which

clearly evinces that there was no urgency to exclude the

application of Section 5-A of the LA Act. This Court observed:

"35. From the various facts disclosed in the said

affidavit it appears that the matter was initiated by

23

the Government's Letter dated 4-6-2008 for

issuance of Section 4(1) and Section 17

notifications. A meeting for selection of a suitable

site for construction was held on 27-6-2008, and

the proposal for such acquisition and construction

was sent to the Director, Land Acquisition on 2-7-

2008. This was in turn forwarded to the State

Government by the Director on 22-7-2008. After

due consideration of the forwarded proposal and

documents, the State Government issued Section 4

notification, along with Section 17 notification on

21-8-2008. These notifications were published in

local newspapers on 24-9-2008.

36. Thereafter, over a period of 9 months, the State

Government deposited 10% of compensation

payable to the landowners, along with 10% of

acquisition expenses and 70% of cost of

acquisition was deposited, and the proposal for

issuance of Section 6 declaration was sent to the

Director, Land Acquisition on 19-6-2009. The

Director in turn forwarded all these to the State

Government on 17-7-2009, and the State

Government finally issued the Section 6

declaration on 10-8-2009. This declaration was

published in the local dailies on 17-8-2009.

37. Thus the time which elapsed between

publication of Section 4(1) and Section 17

notifications, and Section 6 declaration in the local

newspapers is 11 months and 23 days i.e. almost

one year. This slow pace at which the government

machinery had functioned in processing the

acquisition, clearly evinces that there was no

urgency for acquiring the land so as to warrant

invoking Section 17(4) of the LA Act.

38. In Para 15 of the writ petition, it has been

clearly stated that there was a time gap of more

than 11 months between Section 4 and Section 6

notifications, which demonstrates that there was no

urgency in the State action which could deny the

petitioners their right under Section 5-A. In the

counter which was filed in this case by the State

24

before the High Court, it was not disputed that the

time gap between Section 4 notification read with

Section 17, and Section 6 notification was about 11

months.

17) In the facts and circumstances of the present case, it is clear

that this Court, vide its Order dated 17.08.2004, has issued a

direction to the respondents to relocate the bone mills and allied

industries causing environment pollution and health hazards as

per the recommendations of the CPCB and, inter alia,

respondents were also directed to identify the area for relocation.

Pursuant to this, respondents have filed an affidavit in the month

of December, 2004 specifying the construction of the Leather

City Project at Hapur in Ghaziabad. Subsequently, it was only

after the lapse of two years, the State Government had issued a

Notification under Section 4 on 03.07.2006 and the same was

published on 04.7.2006. Thereafter, the State Government took

more than 17 months in order to make a declaration of the

Notification under Section 6 from the date of publication of the

Notification under Section 4 of the LA Act. In view of the above

circumstances, it is crystal clear that the government functionary

has proceeded at very slow pace at two levels, that is, prior to the

issuance of the Notification under Section 4 and post the issuance

25

of the Notification under Section 4, for acquisition of the land for

construction of the Leather City Project, which undoubtedly is a

public purpose. Therefore, the above series of the events amply

exhibit the lethargical and lackadaisical attitude of the State

Government. In the light of the above circumstances, the

respondents are not justified in invoking the urgency provisions

under Section 17 of the LA Act, thereby, depriving the appellants

of their valuable right to raise objections and opportunity of

hearing before the authorities in order to persuade them that their

property may not be acquired.

18) Shri. Pallav Sisodia, learned senior counsel for

respondents, heavily relied on Jai Narain and Ors. v. Union of

India (Supra) in support of his contention that the acquisition

proceedings were initiated under the directions of this Court

which itself recognized the existence of urgent situation to

relocate polluting industries. We are afraid that this decision will

not come to the rescue of the respondents. In that case, this Court

had monitored the setting up of sewage treatment plant and also

directed the Delhi Administration to acquire land on war footing

mentioning urgent situation of supply of pure water and avoiding

any health hazards. The said urgency pointed out by this Court

26

was duly reciprocated by the Delhi Administration by issuing a

Notification under Section 4 and subsequently, a Notification

under Section 6 of the LA Act within a time period of 2 months.

19) The directions or orders issued by this Court must be abided

by within the four corners of the legal framework and statutory

provisions. The State Government is not allowed to transgress the

express legal provisions and procedure thereunder in the garb or

guise of implementing our guidelines or directions. The

directions of this Court are issued with a purpose and the said

purpose is supposed to be followed in the realm of legal structure

and principles. Therefore, the respondents are not justified in

invoking the urgency provisions of the LA Act in an arbitrary

manner by referring to our earlier directions as a defense for their

illegal and arbitrary act of acquiring land without giving an

opportunity of raising objections and hearing to the petitioners in

terms of Section 5-A of the LA Act.

20) Admittedly, the respondents had not obtained the approval of

the NCRPB for construction of the Leather City Project as Sub-

regional plan in terms of Section 19 (2) of the NCRPB Act. The

purpose or aim of the NCRPB Act is to provide for co-ordinated,

harmonized and common plan development of the National

27

Capital Region at the central level in order to avoid haphazard

development of infrastructure and land uses in the said region,

which includes the district of Ghaziabad in the Uttar Pradesh.

Under this Act, the NCRPB has been constituted with the Union

Minister for Urban Development as the Chairperson and the

Chief Ministers of Haryana, Rajasthan and Uttar Pradesh and Lt.

Governor of Delhi as its members in order to undertake the task

of development of the National Capital Region. The object of the

NCRPB is to prepare, modify, revise and review a regional and

functional plan for the development of said region and, further, to

co-ordinate and monitor its implementation. Section 19(1)

mandates the State government or Union Territory to submit their

sub-regional plan to the NCRPB for examination in order to

ensure that it is in conformity with the regional plan. Once the

NCRPB affirms the conformity of the said plan with regional

plan, only then the State government can finalize it. Thereafter,

the State Government is entitled to implement the Sub-regional

plan by virtue of Section 20 of the NCRPB Act. In M.C. Mehta

v. Union of India, (2004) 6 SCC 588, this Court has discussed the

purpose and overriding effect of the NRCPB Act thus:

"27. The National Capital Region Planning Board

Act, 1985 (for short "the NCR Act") was enacted to

28

provide for the constitution of a Planning Board for

the preparation of a plan for the development of the

National Capital Region and for coordinating and

monitoring the implementation of such plan and for

evolving harmonised policies for the control of land

uses and development of infrastructure in the

National Capital Region so as to avoid any

haphazard development of that region and for

matters connected therewith or incidental thereto.

The areas within the National Capital Region are

specified in the Schedule to the NCR Act. The

National Capital Region comprises the area of

entire Delhi, certain districts of Haryana, Uttar

Pradesh and Rajasthan as provided in the

Schedule. "Regional plan" as provided in Section

2(j) means the plan prepared under the NCR Act

for development of the National Capital Region and

for the control of land uses and the development of

infrastructure in the National Capital Region. What

the regional plan shall contain is provided in

Section 10. Section 10(2) provides that the regional

plan shall indicate the manner in which the land in

the National Capital Region shall be used, whether

by carrying out development thereon or by

conservation or otherwise, and such other matters

as are likely to have any important influence on the

development of the National Capital Region..."

28. Section 27 provides that the provisions of the

NCR Act shall have effect notwithstanding anything

inconsistent therewith contained in any other law

for the time being in force or in any instrument

having effect by virtue of any law other than the

NCR Act; or in any decree or order of any court,

tribunal or other authority."

21) In Ghaziabad Development Authority v. Delhi Auto &

General Finance (P) Ltd., (1994) 4 SCC 42, this Court has

considered the overriding effect of the NCRPB Act over the UP

29 Urban Planning and Development Act, 1973, in relation to the

conversion of land user by State of UP which was not in

consonance with the Regional Plan approved by the NCRPB for

the National Capital Region, by virtue of Section 27 read with

Section 29 of the NCRPB Act. This Court, after referring to

various provisions and analysing the scheme of the NCRPB Act,

has observed thus:

"16. The four villages in question in which the

lands of Delhi Auto and Maha Maya are situate

form part of the U.P. Sub-Region of the National

Capital Region. In the master plan of 1986

operative till 2001 A.D. (Annexure I) the lands of

Delhi Auto and Maha Maya are included in the

area set apart for `recreational' use only. On this

basis the Regional Plan was prepared and

approved under the NCR Act on 3-11-1988 and

finally published thereunder on 23-1-1989

according to which the area in question was set

apart for `recreational' use only. Admittedly no

change in this Regional Plan to alter the land use

of that area to `residential' purpose was made any

time thereafter in accordance with the provisions of

NCR Act. The overriding effect of the NCR Act by

virtue of Section 27 therein and the prohibition

against violation of Regional Plan contained in

Section 29 of the Act, totally excludes the land use

of that area for any purpose inconsistent with that

shown in the published Regional Plan. Obviously,

the permissible land use according to the published

Regional Plan in operation throughout, of the area

in question, was only `recreational' and not

residential since no change was ever made in the

published Regional Plan of the original land use

shown therein as `recreational'. This being the

situation by virtue of the overriding effect of the

30

provisions of NCR Act, the amendment of land use

in the master plan under U.P. Act from

`recreational' to `residential' at an intermediate

stage, which is the main foundation of the

respondents' claim, cannot confer any enforceable

right in them. However, if the first amendment in

the master plan under the U.P. Act altering the

land use for the area from `recreational' to

`residential' be valid, so also is the next amendment

reverting to the original land use, i.e.,

`recreational'. Intervening facts relating to the

private colonisers described as planning

commitments, investments, and legitimate

expectations do not have the effect of inhibiting the

exercise of statutory power under the U.P. Act

which is in consonance with the provisions of the

NCR Act, which also has overriding effect and lays

down the obligation of each participating State to

prepare a Sub-Regional Plan to elaborate the

Regional Plan at the Sub-Regional level and holds

the concerned State responsible for the

implementation of the Sub-Regional Plan. The

original land use of the area shown as

`recreational' at the time of approval and

publication of the Regional Plan under the NCR

Act having remained unaltered thereafter, that

alone is sufficient to negative the claim of Delhi

Auto and Maha Maya for permission to make an

inconsistent land user within that area."

22) In Sheikhar Hotels Gulmohar Enclave v. State of Uttar

Pradesh, (2008) 14 SCC 716, this Court has allowed the

invocation of the urgency clause by the State Government for the

widening of the National Highway in the National Capital Region

in the light of completion of the procedural requirement of

31

approval of the master plan of the U.P. Government by the

NCRPB. This Court observed thus:

"9. Traffic congestion is a common experience of

one and all and it is very difficult to negotiate the

traffic congestion in Delhi and National Capital

Region. Therefore, in the present situation, it

cannot be said that the invocation of Section 5-A

was for ulterior purpose or was arbitrary exercise

of the power. Since the master plan has already

been prepared and it has been approved by the

Planning Board and they have sanctioned a sum of

Rs 20.65 crores for the development of this

Transport Nagar and widening of National

Highway 91 into four lanes. Therefore, the

proposal was approved by the Board and it got the

sanction from the National Capital Regional

Planning Board and ultimately the Government

invoked the power under Section 17(4) read with

Section 5-A of the LA Act dispensing with the

objections. In the light of these facts it cannot be

said that invoking of power was in any way an

improper exercise. There is need for decongestion

of traffic and it is really the dire need of the hour

and earlier it is implemented, the better for the

people at large."

23) In the facts and circumstances of the present case, the

respondents, vide its resolution dated 19.04.2005, had authorized

the NCRPB to prepare Sub-regional plan of construction of the

Leather City Project at Hapur in the district of Ghaziabad for the

HPDA. Subsequently, the NCRPB issued a draft Sub-regional

plan, wherein the Leather City Project was not mentioned. The

32

respondents had made several requests to NCRPB to include

Leather City Project but no reply granting approval has come in

terms of Section 19(2) of the NCRPB Act. Section 19 of the

NCRPB Act contemplates the grant of approval by the NRCPB,

and finalization by the State Government, of the Sub-Regional

Plan if it is in consonance and consistent with the Regional Plan

for the National Capital Region. Furthermore, Section 29 of the

NCRPB Act contemplates that the State Government shall not

undertake any development activity, which is inconsistent with

the Regional Plan for the National Capital Regional. Also,

Section 27 of the NCRPB Act has overriding effect on any other

inconsistent law or instrument. The overall scheme of the

NCRPB Act contemplates common plan, coordination and

harmony in the formulation of policy of land uses and

development of infrastructure in the National Capital Region.

Therefore, in our opinion, the acquisition of land in the absence

of express approval in terms of Section 19 and operation of

Section 27 of the LA Act renders the entire acquisition

proceedings illegal and hence vitiated.

24) In view of above discussion, we hold that the declaration of

Notification dated 18.12.2006 under Section 6 of the LA Act is

33

beyond the period of limitation as envisaged by proviso to

Section 6(1) of the LA Act. We also hold that the State

Government was not justified, in the facts and circumstances of

this case, to invoke the urgency provision of Section 17(4) of the

LA Act. Therefore, the appellants cannot be denied of their

valuable right under Section 5-A of the LA Act.

25) In the result, the Writ Petitions are allowed. The impugned

Notification dated 03.7.2006 under Section 4 and Notification

dated 18.12.2006 under Section 6 of the LA Act are hereby

quashed. Costs are made easy.

...............

............J.

[G.S. SINGHVI ]

...........................J.

[H.L. DATTU ]

New Delhi,

August 23, 2011.

34

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free