Miss Lucy
← All judgments

Delhi Metro Rail Corporation Ltd. vs Delhi Airport Metro Express Pvt. Ltd.

Supreme Court10 April 2024Surya Kant · B R Gavai · Dhananjaya Y Chandrachud

Ratio decidendi

The rule this decision rests on

1. Curative jurisdiction under Article 142 may be invoked to prevent abuse of court process and cure a gross miscarriage of justice, including circumstances where declining to reconsider a final judgment would be oppressive to judicial conscience and cause perpetuation of irremediable injustice, though the enumeration of grounds is not exhaustive. 2. Under Section 34(2-A) of the Arbitration and Conciliation Act 1996, a domestic arbitral award may be set aside if vitiated by patent illegality appearing on its face, including where the arbitrator's interpretation of a contract is such that no fair-minded or reasonable person would adopt it, or the view is not even a possible view to take. 3. A finding based on no evidence, an award ignoring vital evidence in arriving at its decision, or an award without reasons suffers from patent illegality and renders the award perverse and liable to be set aside. 4. Where a termination clause in a concession agreement uses two separate phrases—"cure" and "effective steps for curing"—the arbitrator must give individual import to both phrases; an interpretation that conflates them and requires only complete cure while ignoring whether effective steps toward cure were taken is unreasonable and not a possible view any fair-minded person would adopt. 5. Where the basis of a termination notice concerns safety and the statutory scheme (here, the Metro Railways (Operation and Maintenance) Act 2002) vests authority in the Commissioner to certify safety, evidence of the Commissioner's certificate regarding safety is vital evidence directly relevant to the issue of termination validity and cannot be deemed irrelevant without reasoned explanation. 6. An arbitral tribunal errs in patent illegality by overlooking vital evidence on record—such as a joint application by parties to the statutory authority and the statutory authority's certification—that bears on material elements of the dispute, particularly when the evidence shows steps taken toward compliance with the termination clause's requirements. 7. Where this Court exercises discretionary jurisdiction under Article 136 to review a decision of the High Court under Section 37 of the Arbitration Act, it must limit itself to testing whether the High Court exceeded its jurisdiction by failing to apply correct tests under Section 34; this Court errs when it substitutes its view for the High Court's reasoned application of the patent illegality doctrine without demonstrating jurisdictional error by the High Court.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

2024 INSC 292 Reportable

IN THE SUPREME COURT OF INDIA INHERENT JURISDICTION

Curative Petition (C) Nos.108-109 of 2022 In Review Petition (C) Nos.1158-1159 of 2021 In Civil Appeal Nos 5627-5628 of 2021

Delhi Metro Rail Corporation Ltd. …Petitioner

Versus

Delhi Airport Metro Express Pvt. Ltd. …Respondent

Signature Not Verified

Digitally signed by Sanjay Kumar Date: 2024.04.10 10:53:32 IST Reason:

Page 1 of 39 PART A

JUDGMENT

Dr Dhananjaya Y Chandrachud, CJI

Table of Contents

A. Factual Background ................................................................................................... 3

B. DMRC’s claim and the Tribunal’s findings ............................................................. 7

C. Decisions of the High Court.................................................................................... 10

D. Judgment of this Court in appeal ........................................................................... 11

E. Issues in the Curative Petition. .............................................................................. 12

F. Submissions .............................................................................................................. 12

G. Analysis ..................................................................................................................... 16

I. Curative Jurisdiction may be invoked if there is a miscarriage of justice. .. 16 II. Scope of interference of courts with arbitral awards.................................. 19 III. The award was patently illegal .................................................................. 24 i. Interpretation of the termination clause by the Tribunal was unreasonable ................................................................................................. 26 ii. The award overlooked vital evidence and matters on the record........... 29 H. Conclusion................................................................................................................. 37

Page 2 of 39 PART A

1. The curative jurisdiction of this Court under Article 142 of the Constitution has

been invoked in regard to its decision in Delhi Airport Metro Express

Private Limited vs. Delhi Metro Rail Corporation Ltd. 1. The judgment

remained undisturbed in the exercise of the review jurisdiction of this Court.2

A. Factual Background

2. The petitioner, Delhi Metro Rail Corporation 3 is a state-owned company wholly

owned by the Government of India and the National Capital Territory of Delhi.

The respondent, Delhi Airport Metro Express Private Limited 4 is a special-

purpose vehicle incorporated by a consortium comprising of Reliance

Infrastructure Limited and Construcciones Y Auxiliar de Ferrocarriles SA,

Spain. The consortium bagged the contract for the construction, operation and

maintenance of the Delhi Airport Metro Express Ltd 5 in 2008. The Concession

Agreement 6 envisaged a public-private partnership for providing metro rail

connectivity between New Delhi Railway Station and the Indira Gandhi

International Airport and other points within Delhi.

3. Under the 2008 Agreement, DAMEPL was granted exclusive rights, license

and authority to implement the project and concession in respect of AMEL.

This included the right to manage and operate the Project as a commercial

enterprise. DMRC was to undertake clearances and bear costs relating to

land acquisition, and civil structures, while DAMEPL was to undertake among

1 (2022) 1 SCC 131.

2 Review Petition (C) Nos. 1158-1159/2921.

3 “DMRC” 4 “DAMEPL”/” Concessionaire” 5 “AMEL” 6 “2008 Agreement”

Page 3 of 39 PART A

other things, the design, supply, installation, testing and commissioning of

railway systems. DAMEPL was to complete the work in two years, and

thereafter, to maintain AMEL until August 2038.

4. In April 2012, DAMEPL sought a deferment of the concession fee, citing

delays in providing access to the stations by DMRC. DAMEPL stated that

while AMEL had been running without a glitch since 23 February 2011, the

retail activity had not picked pace. DAMEPL urged DMRC to extend their

support, to this first-of-its-kind public-private partnership by deferring the

concession fee payable by DAMEPL.

5. There was an exchange of correspondence between the parties which

ultimately led the Ministry of Urban Development to convene a meeting of

stakeholders in July 2012. A Joint Inspection Committee was set up to inspect

the defects alleged by DAMEPL.

6. Meanwhile, DAMEPL expressed its intention to halt operations, alleging that

the line was unsafe to operate. Operations were stopped on 08 July 2012. On

09 July 2012, DAMEPL issued a notice to DMRC containing a ‘non-

exhaustive’ list of eight defects which according to them, affected the

performance of their obligations under the 2008 Agreement7. The notice

stated that the defects were attributable to faulty construction and deficient

designs which affected project safety.

7 “Cure Notice”

Page 4 of 39 PART A

7. DAMEPL stated that the defects caused a “material adverse effect” on the

performance of the obligations by it to operate, manage and maintain the

project. DMRC was therefore requested to cure the defects within 90 days

from the date of this notice, failing which it stated that it would be considered

that a “Material Breach” and a “DMRC Event of Default” had occasioned,

entitling DAMEPL to terminate the 2008 agreement.

8. On 8 October 2012, DAMPEL issued a notice terminating the 2008

agreement.8 The termination notice stated that as 90 days had elapsed since

the cure notice in spite of which the defects had not been cured within the

‘cure period’, DAMEPL as Concessionaire was terminating the agreement in

terms of clause 29.5.1 of the 2008 agreement.

9. DMRC initiated conciliation under clause 36.1 of the 2008 Agreement. Since

conciliation did not succeed, DMRC initiated arbitration proceedings on 23

October 2012 under clause 36.2 of the 2008 agreement.

10. On 30 June 2013, DAMEPL halted operations and handed over the line to

DMRC. Before this, on 19 November 2012, both parties made a joint

application to the Commissioner of Metro Railway Safety 9 for re-opening of

AMEL for public carriage of passengers. Enclosed with the application, was

an administrative note jointly signed by representatives of both DAMEPL and

DMRC, which we shall avert to in the course of the judgment.

8 “Termination Notice” 9 “CMRS”/”Commissioner”

Page 5 of 39 PART A

11. Following this application, after inquiry and inspection, the CMRS issued

sanction on 18 January 2013. This sanction was subject to certain conditions

including speed restrictions. Specifically, the metro was to be run at a speed

of 50kmph, and an increase in speed beyond 50kmph up to 80kmph was to

be authorized in steps of 10kmph at a time. For an increase in speed beyond

80kmph, DMRC was to approach the Commissioner for sanction with a

justification as to the improvements carried out by it.

12. Consequently, on 22 January 2013, AMEL operations were commenced by

DAMEPL. On 30 June 2013, the project assets were handed over by

DAMEPL to DMRC. After that, from 01 July 2013, DMRC continued AMEL

operations.

13. In August 2013, the arbitral tribunal comprising Mr AP Mishra, Mr SS Khurana

and Mr HL Bajaj was constituted. 10 On 11 May 2017, the three-member

Tribunal passed a unanimous award in favour of DAMEPL 11.

14. The award held that DAMEPL was entitled first, to the termination payment of

Rs. 2782.33 Crores plus interest in terms of the concession agreement;

second, to expenses incurred in operating AMEL from 07 January 2013 to 30

June 2013 and debt service made by DAMEPL during this period, of Rs

147.52 Crores plus interest at 11% per annum from the date of payment of

stamp duty; third, to the refund of the bank guarantee amounting to Rs 62.07

Crores plus interest at 11% p.a. which had been encashed; fourth, to security

deposits with the service providers, amounting to Rs 56.8 Lakhs plus interest

10 “Tribunal” 11 “Award”

Page 6 of 39 PART B

at 11% p.a.; and that DMRC was entitled to Rs 46.04 Crores as Concession

fee for the period from 23 February 2012 to 7 January 2013.

15. Assailing the award, DMRC instituted an application under Section 34 of the

Arbitration and Conciliation Act 1996 12 before the Delhi High Court. The

Single-Judge of the High Court dismissed the petition 13. This gave rise to an

appeal under Section 37 before a Division Bench of the High Court. The

appeal was partly allowed. 14

16. Against the decision of the Division Bench of the High Court, DAMEPL moved

a Special Leave Petition under Article 136 of the Constitution. A two-judge

bench of this Court allowed the appeal, and restored the award. The review

petition assailing this decision was dismissed. Thus, the curative petition.

B. DMRC’s claim and the Tribunal’s findings

17. Before the Tribunal, DMRC claimed that – (i) it took steps to cure the defects

immediately after it received the cure notice, including approaching SYSTRA -

the original design consultant and convening meetings with the Ministry of

Urban Development and that DAMEPL actively participated in all of these

steps; (ii) that the real reason for the termination notice was that DAMPL had

ceased to find the project financially viable. DMRC sought, inter alia, quashing

of the termination notice; and a direction to the respondent to resume the

performance of its obligations under the 2008 agreement. DAMEPL, on the

other hand, claimed that there were defects attributable to DMRC’s faulty

12 “Arbitration Act”.

13 OMP (COMM) 307/2017 & OMP (I) (COMM) 200/2017 (‘Single Judge’) 14 FAO(OS)(COMM) 58/2018 & CM Nos. 13434/2018 (‘Division Bench’)

Page 7 of 39 PART B

design; that these defects were not cured and no effective steps were taken to

cure them within the 90-day cure period, resulting in material adverse effects

to DAMEPL, entitling it to terminate the concession agreement.

18. The Tribunal was required to adjudicate on the validity of the termination

notice. It framed the following issues:

“Were there any defects in the civil structure of the airport metro line?

If there were defects, did such defects have a material adverse effect on the performance of the obligation of DAMEPL under CA?

If there were defects in the civil structure, which had a material adverse effect on the performance of the obligations under the CA by DAMEPL, have such defects been cured by DMRC and/or have any effective steps been taken within a period of 90 days from the date of notice by DAMEPL to cure the defects by DMRC and thus, were DMRC in breach of the CA as per 29.5.1 (i)?”

19. The Tribunal undertook an analysis of the defects in the structure and whether

they had been cured or effective steps taken during the cure period. It noted

that 72% of the girders were affected by cracks; the cause of the cracks was

uncertain; the depth of the cracks was not reliably determined; and that the

inspection for repairs carried out at the instance of DMRC was ‘non-serious’.

Further, it noted that there were twists in about 80 girders and gaps between

the shear key and the girders which were not cured by DMRC in the cure

period. Taken together, these defects were considered to have compromised

the integrity of the structure. This, the Tribunal held, amounted to a breach of

DMRC’s obligations under the 2008 agreement resulting in a material adverse

effect on the concessionaire.

Page 8 of 39 PART B

20. The Tribunal framed the legal issues that arose for its consideration. The

issue about the validity of the termination agreement was framed in the

following terms:

“D. Was DAMEPL entitled to or justified in termination of the CA, since the cost of repairs of the alleged defects was only approximately Rs.14 crores as compared to the total costs of the project of approximately Rs. 5700 crores?”

21. The issue pertaining to the CMRS certificate was framed as follows:

“H. Did the issuance of certificate by CMRS show that the defects were duly cured?”

22. Both these issues were answered in the negative by the Tribunal. On Issue

‘D’ about the validity of the termination, it was held that since the Tribunal had

found that there were defects in the civil structure, which remained uncured

during the cure period, the amount incurred by DMRC in repairs compared to

the overall cost of the project was irrelevant. 15 On issue ‘H’, about the CMRS

certificate, the tribunal found that the CMRS sanction mandated rigorous

monitoring of operations of the line and imposed a speed restriction. Since the

purpose of the line was to serve as a high-speed line, the tribunal found that

the speed restrictions meant that this purpose was not served and therefore,

the CMRS certificate or the subsequent operation of the line were not relevant

in deciding the issues before it. 16

15 The Award, para 93.

16 ibid, paras 105-108.

Page 9 of 39 PART C

C. Decisions of the High Court

23. The Single Judge of the High Court 17, deciding the Section 34 application,

upheld the award, observing that so long as the award was reasonable and

plausible, considering the material before the Tribunal no interference was

warranted, even if an alternate view was possible. It was held that the

Tribunal, in this case, had analysed material and evidence in great detail, and

arrived at a plausible conclusion.

24. The Division Bench of the High Court 18 partly set aside the award as perverse

and patently illegal, for the following reasons:

24.1. On the validity of the termination, ex-facie, the termination which

was effective immediately from the date of termination was invalid. There

was some ambiguity on the relevant date of termination. The award did

not interpret clause 29.5.1(i) of the concession agreement regarding the

duration of the cure period;

24.2. The speed restrictions were not stated as the reason for termination

in the cure or termination notices and there was no deliberation on this

being a justification for termination before the Tribunal. Thus, the award

was silent and unreasoned on this issue; and

24.3. Underlining the significance of the CMRS sanction under the Act of

2002, the findings of the tribunal on this issue were incorrect because (i)

the award overlooked the legal effect of the CMRS certificate which was

17 “Single Judge”.

18 “Division Bench”.

Page 10 of 39 PART D

binding on the tribunal; and (ii) the award erroneously treated the CMRS

certificate as irrelevant to the issue of the validity of the termination by

wrongly separating the issue of defects and material adverse effects from

the issue of the certificate.

D. Judgment of this Court in appeal

25. This Court set aside the decision of the Division Bench and restored the

arbitral award on the following grounds:

25.1. There was no ambiguity in the date of termination and even if a

different view from that of the tribunal were possible, construction of the

provisions of the contract was within the exclusive domain of the tribunal;

25.2. The award was not perverse. The finding of the tribunal that the

defects were not cured was a finding of fact, not warranting interference;

25.3. DMRC had not contended before the Tribunal that the certificate

was binding and conclusive of the fact that the defects were cured or that

effective steps had been taken; and

25.4. The Division Bench of the High Court was in error in holding that the

issue of the CMRS certificate was wrongly separated from the issue of

defects. It held that dealing with the certificate separately from the validity

of termination did not render the tribunal’s findings on the latter erroneous.

The Tribunal comprised of engineers and the award could not be

scrutinised in the same manner as an award drawn by a legally trained

mind.

Page 11 of 39 PARTs E/F

26. The review petition against the above judgment of this Court was dismissed

on 23 November 2021.

E. Issues in the Curative Petition

27. The issues that arise for our consideration are (i) whether the curative petition

is maintainable; and (ii) whether this Court was justified in restoring the arbitral

award which had been set aside by the Division Bench of the High court on

the ground that it suffered from patently illegality.

F. Submissions

28. We have heard Mr R Venkataramani, Attorney General for India and Mr K K

Venugopal, Mr Parag Tripathi, and Mr Maninder Singh senior counsel on

behalf of the petitioners. They made the following submissions:

28.1. Considering the definition of ‘material adverse effect’ under the

concession agreement, the defects had no material adverse effect on

DAMEPL’s performance of obligations under the agreement, as is

apparent from the running of the metro line. The purpose of the

agreement was fully subserved, as evinced by the continuous running of

the line;

28.2. The purpose of the cure notice was to demand cure compliance

from DMRC. As long as ‘effective steps’ were taken by DMRC,

culminating in cure compliance under the statutory process under the

Page 12 of 39 PART F

Metro Railways (Operation and Maintenance) Act, 2002 19, the termination

notice was invalid;

28.3. Clause 29.5.1 of the agreement shows that the termination ought to

have been effected after 90 days from the cure notice plus 90 days in

addition. Termination was thus effective only on 07 January 2013 and on

this date, none of the defects were pending to be rectified by DMRC;

28.4. The sanction/certificate granted by CMRS was issued on a joint

application by both the parties after thorough inspection of the operations.

The terms of the agreement and the provisions relating to the CMRS

process under the 2002 Act are intrinsically connected;

28.5. The Tribunal should have considered the binding effect of the

CMRS sanction as the issue of speed was neither raised, nor deliberated

before it and was irrelevant to the termination;

28.6. The line has been running since 1 July 2013. The speed of

operations was sanctioned at 50kmph, and has been progressively

increased to 60 kmph in January 2013, 80 kmph in August 2013, 90 kmph

in July 2019, and ultimately 100 kmph and then 110 kmph in 2023. The

metro was running at 80 kmph prior to the termination of the agreement. It

is currently running at 120kmph for which a fresh sanction was obtained

from the CMRS. The smooth operation of the metro line for five and a half

years, until the date of the award was entirely ignored by the Tribunal,

making the award perverse;

19 The 2002 Act

Page 13 of 39 PART F

28.7. The running of the metro line shows that even if there were defects,

they did not render the metro unviable nor did they interfere with

DAMEPL’s obligations under the agreement. Thus, the award is perverse

and patently illegal;

28.8. The tribunal ignored vital evidence, warranting the High Court’s

interference under Section 37 of the Arbitration Act. The miscarriage of

justice principle is informed by the scheme of the Arbitration Act;

28.9. The High Court’s interference with the patent illegality was justified

and this Court under Article 136 ought to have been slow to interfere with

the decision of the Division Bench of the high Court. Miscarriage of justice

in terms of the decision in Rupa Hurra vs. Ashok Hurra20 is linked with

patent illegality. The High Court’s interference under Section 37 was

justified because the exercise of jurisdiction under Section 34 was

erroneous; and

28.10. The issue of the fitness of the line was a matter falling under the

2002 Act under which the Commissioner was the final authority to decide

on the safety of the metro. The certificate could not have been substituted

by the Tribunal’s finding on safety of the line.

29. We have heard Mr Harish Salve, Mr Kapil Sibal, Mr JJ Bhatt and Mr Prateek

Seksaria, learned senior counsel for the respondent. They have made the

following submissions:

20 2002 4 SCC 388.

Page 14 of 39 PART F

29.1. The curative petition is not maintainable as this Court cannot revisit

the conclusions arrived at by the Tribunal;

29.2. DMRC has taken over the project and has been operating it since

01 July 2012 without having paid for its operation between 01 January

2013 till 30 June 2013, except for a small fraction of the total awarded

amount;

29.3. Till early March 2023, the trains were running at 90kmph, as

opposed to the speed of 120kmph at which they ought to have been

running;

29.4. The issue about the relevance of the CMRS certificate has been

squarely addressed by the Single Judge and this Court. The arbitrator is

the sole judge of the quality and the quantity of evidence;

29.5. The award was made after 68 hearings and after consideration of

35,000 pages of documents and oral evidence. It has been two and a half

years since this Court restored the award on 09 September 2021 and the

review against this decision was dismissed on 23 November 2021;

29.6. According to the decision in Rupa Hurra (supra), the court is not

supposed to sit over a judgment like a court of appeal. The scope of the

review jurisdiction is narrow in itself and does not warrant rehearing and

correction of a judgment. Curative proceedings cannot be treated as a

second review; and

Page 15 of 39 PART G

29.7. DAMEPL is not unjustly enriching itself. DAMEPL completed the

project with an investment of Rs 2802 Crores comprising of debt and

equity contributions and it continued to service the debt even after

handing over the line to DMRC. DMRC on the other hand, has paid the

decretal amount of Rs 2599.18 Crores while Rs 5088 Crores under the

decree is outstanding as on 31 January 2024.

G. Analysis

I. Curative Jurisdiction may be invoked if there is a miscarriage of justice

30. Senior Counsel for the respondent set forth preliminary objections challenging

the maintainability of the Curative Petition, in view of the scope of that

jurisdiction delineated inter alia in the decision in Rupa Hurra (supra) We will

first lay down the contours of the jurisdiction of this Court to entertain a

curative petition in exercise of its inherent powers under Article 142.

31. In Rupa Hurra (supra), a Constitution Bench of this Court dwelt on whether

any relief is available against a final judgement of this Court after the

dismissal of a petition seeking review of the judgement. Two opinions were

authored. The main judgment was by Justice Syed Shah Quadri (on behalf of

Chief Justice S P Bharucha, Justice Variava, Justice Shivraj Patil and

himself). A concurring opinion was authored by Justice U C Banerjee.

32. Justice Quadri observed that the concern of the Court for rendering justice in

a cause cannot be considered less important than the principle of finality.

Page 16 of 39 PART G

There are certain situations, the opinion observed, which would require

reconsideration of a final judgement even after the review has been dismissed

to set right a miscarriage of justice. Such circumstances, the court held, are

those where declining to reconsider the judgement would be oppressive to

judicial conscience and cause the perpetuation of irremediable injustice.

Justice Quadri observed:

“42. … the duty to do justice in these rarest of rare cases shall have to prevail over the policy of certainty of judgment as though it is essentially in the public interest that a final judgment of the final court in the country should not be open to challenge, yet there may be circumstances, as mentioned above, wherein declining to reconsider the judgment would be oppressive to judicial conscience and would cause perpetuation of irremediable injustice.”

(emphasis supplied)

33. This Court laid down an overarching principle that the Court may entertain a

curative petition to (i) prevent abuse of its process; and (ii) to cure a gross

miscarriage of justice. 21 The Court provided examples of such circumstances,

such as a violation of the principles of natural justice; or a situation where the

Judge fails to disclose his connection with the subject matter or the parties,

giving scope for an apprehension of bias. However, the Court observed that it

is not possible to exhaustively enumerate the grounds on which a curative

petition may be entertained. The Court noted as follows:

“50. The next step is to specify the requirements to entertain such a curative petition under the inherent power of this Court so that floodgates are

21 Rupa Hurra, para 49.

Page 17 of 39 PART G

not opened for filing a second review petition as a matter of course in the guise of a curative petition under inherent power. It is common ground that except when very strong reasons exist, the Court should not entertain an application seeking reconsideration of an order of this Court which has become final on dismissal of a review petition. It is neither advisable nor possible to enumerate all the grounds on which such a petition may be entertained.

51. Nevertheless, we think that a petitioner is entitled to relief ex debito justitiae if he establishes (1) violation of the principles of natural justice in that he was not a party to the lis but the judgment adversely affected his interests or, if he was a party to the lis, he was not served with notice of the proceedings and the matter proceeded as if he had notice, and (2) where in the proceedings a learned Judge failed to disclose his connection with the subject-matter or the parties giving scope for an apprehension of bias and the judgment adversely affects the petitioner.”

34. The enumeration of the situations in which the curative jurisdiction can be

exercised is thus not intended to be exhaustive. The Court went on to lay

down certain procedural requirements to entertain a curative petition such as

a certificate by a Senior Advocate about fulfilling of the requirements.

35. In his concurring opinion, Justice Banerjee also laid down a similar test of

‘manifest injustice’ to exercise the jurisdiction of this Court under Article 142

while entertaining a curative petition. In essence, the jurisdiction of this Court,

while deciding a curative petition, extends to cases where the Court acts

beyond its jurisdiction, resulting in a grave miscarriage of justice. We now

proceed to lay down the scope of jurisdiction of this Court and the competent

Page 18 of 39 PART G

courts below while dealing with cases arising out of an application to set aside

an arbitral award under Section 34 of the Arbitration Act.

II. Scope of interference of courts with arbitral awards

36. Section 34 of the Arbitration Act delineates the grounds for setting aside an

arbitral award. The provision, as amended by the Arbitration and Conciliation

(Amendment) Act, 2015 reads as follows:

“34. Application for setting aside arbitral award.—

(2) An arbitral award may be set aside by the Court only if—

(b) the Court finds that--

(i) the subject-matter of the dispute is not capable of settlement by arbitration under the law for the time being in force, or

(ii) the arbitral award is in conflict with the public policy of India.

Explanation 1. --For the avoidance of any doubt, it is clarified that an award is in conflict with the public policy of India, only if,--

(i) the making of the award was induced or affected by fraud or corruption or was in violation of section 75 or section 81; or

(ii) it is in contravention with the fundamental policy of Indian law; or

(iii) it is in conflict with the most basic notions of morality or justice.

Explanation 2. --For the avoidance of doubt, the test as to whether there is a contravention with the fundamental policy of Indian law shall not entail a review on the merits of the dispute.

Page 19 of 39 PART G

(2A) An arbitral award arising out of arbitrations other than international commercial arbitrations, may also be set aside by the Court, if the Court finds that the award is vitiated by patent illegality appearing on the face of the award:

Provided that an award shall not be set aside merely on the ground of an erroneous application of the law or by reappreciation of evidence.”

(emphasis supplied)

37. The contours of the power of the competent court to set aside an award under

Section 34 has been explored in several decisions of this Court. In addition to

the grounds on which an arbitral award can be assailed laid down in Section

34(2), there is another ground for challenge against domestic awards, such as

the award in the present case. Under Section 34(2-A) of the Arbitration Act, a

domestic award may be set aside if the Court finds that it is vitiated by ‘patent

illegality’ appearing on the face of the award.

38. In Associate Builders vs. Delhi Development Authority22, a two-judge

Bench of this Court held that although the interpretation of a contract is

exclusively within the domain of the arbitrator, construction of a contract in a

manner that no fair-minded or reasonable person would take, is

impermissible. A patent illegality arises where the arbitrator adopts a view

which is not a possible view. A view can be regarded as not even a possible

view where no reasonable body of persons could possibly have taken it. This

Court held with reference to Sections 28(1)(a) and 28(3), that the arbitrator

must take into account the terms of the contract and the usages of trade

applicable to the transaction. The decision or award should not be perverse or

22 2015 3 SCC 49.

Page 20 of 39 PART G

irrational. An award is rendered perverse or irrational where the findings are (i)

based on no evidence; (ii) based on irrelevant material; or (iii) ignores vital

evidence. Patent illegality may also arise where the award is in breach of the

provisions of the arbitration statute, as when for instance the award contains

no reasons at all, so as to be described as unreasoned. A fundamental breach

of the principles of natural justice will result in a patent illegality, where for

instance the arbitrator has let in evidence behind the back of a party. In the

above decision, this Court observed:

“31. The third juristic principle is that a decision which is perverse or so irrational that no reasonable person would have arrived at the same is important and requires some degree of explanation. It is settled law that where:

(i) a finding is based on no evidence, or

(ii) an Arbitral Tribunal takes into account something irrelevant to the decision which it arrives at; or

(iii) ignores vital evidence in arriving at its decision,

such decision would necessarily be perverse.

42.2. (b) A contravention of the Arbitration Act itself would be regarded as a patent illegality — for example if an arbitrator gives no reasons for an award in contravention of Section 31(3) of the Act, such award will be liable to be set aside.”

(emphasis supplied)

Page 21 of 39 PART G

39. In Ssangyong Engineering & Construction Co. Ltd. vs. NHAI 23, a two-

judge bench of this Court endorsed the position in Associate Builders

(supra), on the scope for interference with domestic awards, even after the

2015 Amendment:

“40. The change made in Section 28(3) by the Amendment Act really follows what is stated in paras 42.3 to 45 in Associate Builders, namely, that the construction of the terms of a contract is primarily for an arbitrator to decide, unless the arbitrator construes the contract in a manner that no fair-minded or reasonable person would; in short, that the arbitrator's view is not even a possible view to take. Also, if the arbitrator wanders outside the contract and deals with matters not allotted to him, he commits an error of jurisdiction. This ground of challenge will now fall within the new ground added under Section 34(2-A).

41. … Thus, a finding based on no evidence at all or an award which ignores vital evidence in arriving at its decision would be perverse and liable to be set aside on the ground of patent illegality. Additionally, a finding based on documents taken behind the back of the parties by the arbitrator would also qualify as a decision based on no evidence inasmuch as such decision is not based on evidence led by the parties, and therefore, would also have to be characterised as perverse.”

(emphasis supplied)

40. In essence, the ground of patent illegality is available for setting aside a

domestic award, if the decision of the arbitrator is found to be perverse, or so

irrational that no reasonable person would have arrived at it; or the

23 2019 15 SCC 131.

Page 22 of 39 PART G

construction of the contract is such that no fair or reasonable person would

take; or, that the view of the arbitrator is not even a possible view. 24 A ‘finding’

based on no evidence at all or an award which ignores vital evidence in

arriving at its decision would be perverse and liable to be set aside under the

head of ‘patent illegality’. An award without reasons would suffer from patent

illegality. The arbitrator commits a patent illegality by deciding a matter not

within his jurisdiction or violating a fundamental principle of natural justice.

41. A judgment setting aside or refusing to set aside an arbitral award under

Section 34 is appealable in the exercise of the jurisdiction of the court under

Section 37 of the Arbitration Act. It has been clarified by this Court, in a line of

precedent, that the jurisdiction under Section 37 of the Arbitration Act is akin

to the jurisdiction of the Court under Section 34 and restricted to the same

grounds of challenge as Section 34. 25

42. In the statutory scheme of the Arbitration Act, a recourse to Section 37 is the

only appellate remedy available against a decision under Section 34. The

Constitution, however, provides the parties with a remedy under Article 136

against a decision rendered in appeal under Section 37. This is the

discretionary and exceptional jurisdiction of this Court to grant Special Leave

to Appeal. In fact, Section 37(3) of the Arbitration Act expressly clarifies that

no second appeal shall lie from an order passed under Section 37, but nothing

in the section takes away the constitutional right under Article 136. Therefore,

in a sense, there is a third stage at which this court tests the exercise of

24 Patel Engineering Limited vs North Eastern Electric Power Corporation Limited (2020) 7 SCC 176. 25 MMTC Ltd. v. Vedanta Ltd, (2019) 4 SCC 163, para 14; Konkan Railways v. Chenab Bridge Project Undertaking, 2023 INSC 742, para 14.

Page 23 of 39 PART G

jurisdiction by the courts acting under Section 34 and Section 37 of the

Arbitration Act.

43. While adjudicating the merits of a Special Leave Petition and exercising its

power under Article 136, this Court must interfere sparingly and only when

exceptional circumstances exist, justifying the exercise of this Court’s

discretion. 26 The Court must apply settled principles of judicial review such as

whether the findings of the High Court are borne out from the record or are

based on a misappreciation of law and fact. In particular, this Court must be

slow in interfering with a judgement delivered in exercise of powers under

Section 37 unless there is an error in exercising of the jurisdiction by the Court

under Section 37 as delineated above. Unlike the exercise of power under

Section 37, which is akin to Section 34, this Court (under Article 136) must

limit itself to testing whether the court acting under Section 37 exceeded its

jurisdiction by failing to apply the correct tests to assail the award.

III. The award was patently illegal

44. In the case at hand, the Division Bench found the award to be perverse,

irrational and patently illegal since it ignored the vital evidence of CMRS

certification in deciding the validity of termination. This, the Division Bench

held, overlooked the statutory certification deeming it irrelevant without

reasons and thus the award was patently illegal according to the test in

Associate Builders (supra).27

26 Chandi Prasad Chokhani v. State of Bihar, AIR 1961 SC 1708; Pritam Singh v. State, 1950 SCC 189. 27 Division Bench, paras 98-99.

Page 24 of 39 PART G

45. This Court in appeal against the judgment of the Division Bench of the High

Court held that the award was not perverse. Factual findings such as the

finding that the cure period was 90 days and that DAMEPL was entitled to

terminate the contract, could not, it was held, be interfered with. 28 On the

CMRS Certificate, this Court held that the arbitral tribunal was deciding

whether there was a breach of the agreement and whether the defects were

cured within the cure period; hence the safety of the line was not an issue

before the tribunal. This Court held that the Commissioner may be the

competent authority to determine the safety of the project but the certificate

itself did not show that the defects were cured within 90 days. This Court

disagreed with the Division Bench and held that the CMRS certificate had no

bearing on the validity of the termination.

46. There is a fundamental error in the manner in which this Court dealt with the

challenge to the decision of the High Court. This jurisdiction of this Court was

invoked under Article 136 of the Constitution. The Court was exercising its

jurisdiction over a decision rendered by the Division Bench of the High Court

in appeal under Section 37. The Division Bench had held that the award

overlooked crucial facts and evidence on record that were crucial to the

determination of the issues before the arbitral tribunal. This led to the award

being perverse and patently illegal within the parameters of Section 34 as

explained in the judgments of this Court in Associate Builders (supra) and

Ssangyong (supra). The award overlooked the express terms of clause

29.5.1(i) which stipulated that if “effective steps” were taken during the cure

28 Civil Appeal, para 31.

Page 25 of 39 PART G

period by DMRC, the contractual power to terminate could not be exercised.

This Court incorrectly considered the CMRS certificate to be irrelevant to the

validity of the termination.

i. Interpretation of the termination clause by the Tribunal was

unreasonable

47. Interference with an arbitral award cannot frustrate the ‘commercial wisdom

behind opting for alternate dispute resolution’, merely because an alternate

view exists. 29 However, the interpretation of a contract cannot be

unreasonable, such that no person of ordinary prudence would take it. The

contract, which is a culmination of the parties’ agency, should be given full

effect. If the interpretation of the terms of the contract as adopted by the

tribunal was not even a possible view, the award is perverse.30

48. Clause 29.5.1(i) entitles the concessionaire to terminate the agreement if

DMRC “failed to cure such breach or take effective steps for curing such

breach” within the cure period. Pertinently, the clause uses two separate

phrases, “cure” and “effective steps to cure”. The clause reads as follows:

“29.5.1 The Concessionaire may after giving 90 (ninety) days’ notice in writing to DMRC terminate this Agreement upon the occurrence and continuation of any of the following events (each a “DMRC Event of Default”), unless any such DMRC Event of Default has occurred as a result of Concessionaire Event of Default or due to a Force Majeure Event.

(i) DMRC is in breach of this Agreement and such breach has a Material Adverse Effect on the

29 Dyna Technologies Private Limited v. Crompton Greaves Limited, (2019) 20 SCC 1, paras 24, 25. 30 Konkan Railway Corporation Limited v. Chenab Bridge Project Undertaking, 2023 9 SCC 85. Page 26 of 39

PART G

Concessionaire and DMRC has failed to cure such breach or take effective steps for curing such breach within 90 (ninety) days of receipt of notice in this behalf from the Concessionaire;”

(emphasis supplied)

49. The Tribunal found that since certain defects remained after the cure period,

this was indicative of the fact that the defects were not cured and that no

effective steps were taken. However, logically, the fact that defects existed at

the end of the cure period relates to one aspect of the termination clause –

that the defects were not completely cured. It does not explain whether

effective steps were taken within the cure period. Effectively, the Tribunal

considered that in-progress steps that had not yet culminated into completely

cured defects were not “effective steps” to offset termination. This places the

two components i.e. ‘curing of defects’ and ‘taking effective steps to cure

defects’ at par, to mean that only the completed curing of defects is relevant.

The Tribunal fails to explain what amounts to an ‘effective step’ and how the

steps taken by DMRC were not effective, within the meaning of the phrase.

50. Evidently, this could not have been the intention of the parties, because they

have clearly agreed to include the phrase “effective steps”. They clearly

intended that once a cure notice was served on a party, it would be open to

them to either cure defects or to initiate effective steps, even if they could not

culminate into the complete curing of defects within the cure period.

Incremental progress, even if it does not lead to complete cure, is an

acceptable course of action to prevent termination according to the 2008

Agreement.

Page 27 of 39 PART G

51. The Tribunal did not appreciate the individual import of the two phrases

separately from each other. This was not a matter of mere “alternate

interpretation” of the clause, but an unreasonable and uncalled for

interpretation of the clause, which frustrated the very provision, and which no

reasonable person would have accepted considering the terms of the clause.

We must clarify that Tribunal could have still arrived at the conclusion that the

steps taken during the cure period were not effective within the meaning of the

clause for certain reasons. However, such discussion and reasoning is

conspicuously absent.

52. Issue H framed by the Tribunal- “Did the issuance of certificate by CMRS

show that the defects were duly cured” similarly glosses over the effective

steps aspect of the clause. Given this framing, the issue was bound to be

answered in the negative since the CMRS certificate does not conclude that

the defects were completely cured.

53. The decisions of the Single Judge and this Court are similarly silent on the

aspect of “effective steps”. In paragraphs 31 to 34 of its judgment, this Court

noted that since the defects were not cured in 90 days, the termination was

valid. Impliedly, this Court found that the defects ought to have been fully

cured within the cure period in order to avoid termination.

54. The judgment of this Court also never tested the relevance of the CMRS

certificate vis-à-vis “effective steps”. This Court accepted a reading of the

termination clause by the Arbitral tribunal and the Single Judge that was not

even a possible view and could not have been arrived at on any objective

Page 28 of 39 PART G

assessment. This Court not only overlooked the plain words of the clause but

also rendered the phrase “effective steps” otiose.

ii. The award overlooked vital evidence and matters on the record

55. The erroneous and misleading framing of the issue as noted above led to the

ignoring of vital evidence relevant to the issue of termination. The arbitral

tribunal held that since the Commissioner imposed conditions of inspection

and speed restrictions, this meant that the defects were not fully cured.

56. Certainly, the imposition of conditions shows that the defects were not cured

completely, to warrant an unconditional sanction for full speed operations.

However, as the Division Bench of the High Court correctly observed, the

separation of the validity of termination and relevance of the CMRS certificate

was the reason for this erroneous finding. Since the ‘effective steps’ aspect

was overlooked, the CMRS certificate was erroneously deemed to be

irrelevant.

57. On 19 November 2012, a joint application was made by the parties to the

Commissioner under the 2002 Act. Significantly, the annexure to the

application which was jointly signed by the parties states as set out below:

“f) The repairs have been Inspected by an Independent Engineer M/s TUV, engaged by

Page 29 of 39 PART G

DMRC to conduct the technical check on the quality of work and to ensure that the repairs are carried out as per the approved repair methodology. The copies of the certificates obtained from TUV are enclosed as Annexures xvii.

g) Cracks in soffit of some ‘U’ girders were also observed and, therefore, inspection of all the girders have been done and mapping of the cracks have been undertaken accordingly (Annexure- xviii). Cracks have beery noticed in 367 girders.

These cracks were analysed by M/s SYSTRA and their report is, enclosed as Annexure xix. They have concluded that there is no effect on the integrity of the girders and that there is no reason to-be further worried. M/s SYSTRA have also given the repair methodology for these cracks from the point of view of durability and to avoid permeation of water during the service life of girders, (Included in Annexure-xvi). Accordingly, the cracks wider than 0.2 mm have been Injected with epoxy resin and cracks less than 0.2 mm have been sealed with epoxy sealant.

h) Train trials after repairs by DMRC have been completed successfully and all systems have been checked for correct functioning at various speeds Including at speed of 120 kmph. Track recording was done with OMS-2000 during these trials and no peak of value ≥ 0.15g was recorded upto 120 Kmph (results of OMS 2000 are enclosed in Annexure XIV)”

(emphasis supplied)

58. Admittedly, some of the defects were cured in their entirety and steps were

taken by DMRC to cure the remainders, based on which the parties had jointly

sought permission under the 2002 Act. The parties stated that the repairs had

been inspected by an independent engineer; an analysis of the cracks

revealed that the integrity of the girders was intact and there was no cause of

concern. Further, the parties stated that the train trials “after repairs by DMRC

have been completed successfully and all systems have been checked for

Page 30 of 39 PART G

correct functioning at various speeds including the speed of 120kmph”. It is

apparent on the face of the record that certain repairs were completed by

DMRC and the trials had been completed at full speed as on the date of

application, 19 November 2012.

59. On 9 July 2012, about four months before the date of the joint application,

DAMEPL had averred in the cure notice that the project was not ‘safe for

operations’ and that it posed a threat to life and property. The arbitral tribunal

was correct in concluding that the joint application does not constitute a

waiver of the termination, but this evidence was vital considering the change

in DAMEPL’s position on the safety of the line from the date of the cure notice

to the date of the joint application. DMRC did take certain steps to alleviate

DAMEPL’s concerns so as to warrant this change of position. There is no

explanation forthcoming in the award about why none of these steps initiated

during the cure period were ‘effective steps’. This gap in reasoning stems from

the arbitral tribunal wrongly separating the issue of termination and the CMRS

certificate.

60. Besides the effective steps aspect, there is another reason why the CMRS

certificate ought to have been treated as relevant. The Tribunal treats the cure

notice as a crucial document. At paragraph 26 of the award, it noted that

“since the cure notice dated 9th July 2012 is a crucial document in this case, it

is useful to quote certain paragraphs of the said letter”. The cure notice, in

turn, was heavily premised on the safety of operations.31 Interestingly, at

paragraph 27 of the cure notice, DAMEPL avers that the trains can only be 31 Cure Notice paras 18,21,26, and 27.

Page 31 of 39 PART G

operated once the defects are cured to the satisfaction of the stakeholders

about the safety of operations.

61. Reference may be made to the 2002 Act under which the CMRS is the

relevant statutory stakeholder whose satisfaction about the safety of

operations is necessary for running of the metro. The relevant provisions of

the Act may be adverted to here:

“14. Sanction of Central Government to the opening of metro railway.—The metro railway in the the National Capital Region, metropolitan city and metropolitan area shall not be opened for the public carriage of passengers except with the previous sanction of the Central Government.

15. Formalities to be complied with before giving sanction to the opening of metro railway.—(1) The Central Government shall, before giving its sanction to the opening of the metro railway under Section 14, obtain a report from the Commissioner that—

(a) he has made a careful inspection of the metro railway and the rolling stock that may be used thereon;

(b) the moving and fixed dimensions as laid down by the Central Government have not been infringed;

(c) the track structure, strength of bridges, standards of signalling system, traction system, general structural character of civil works and the size of, and maximum gross load upon, the axles of any rolling stock, comply with the requirements laid down by the Central Government; and

(d) in his opinion, metro railway can be opened for the public carriage of passengers without any danger to the public using it.

(2) If the Commissioner is of the opinion that the metro railway cannot be opened without any danger to the public using it, he shall, in his report, state the grounds therefor, as also the

Page 32 of 39 PART G

requirements which, in his opinion, are to be complied with before sanction is given by the Central Government.

(3) The Central Government, after considering the report of the Commissioner, may sanction the opening of the metro railway under Section 14 as such or subject to such conditions as may be considered necessary by it for the safety of the public.

18. Power to close metro railway opened for public carriage of passengers.—Where, after the inspection of the metro railway opened and used for the public carriage of passengers or any rolling stock used thereon, the Commissioner is of the opinion that the use of the metro railway or of any rolling stock will be attended with danger to the public using it, the Commissioner shall send a report to the Central Government who may thereupon direct that—

(i) the metro railway be closed for the public carriage of passengers; or

(ii) the use of the rolling stock be discontinued; or

(iii) the metro railway or the rolling stock may be used for the public carriage of passengers subject to such conditions as it may consider necessary for the safety of the public.

21. Delegation of powers.—The Central Government may, by notification, direct that any of its powers or functions under this chapter, except power to make rule under Section 22, shall, in relation to such matters and subject to such conditions, if any, as may be specified in the notification, be exercised or discharged also by the Commissioner.”

Page 33 of 39 PART G

62. In essence, the scheme of the 2002 Act, provides that no metro line will

operate except with the previous sanction of the Central Government.32

Before granting the sanction, the Central Government has to obtain a report

from the Commissioner that (inter alia) the latter has carefully inspected the

metro railway, the general structure of civil works and that in their opinion, the

metro railway can be opened for passengers without any danger to the

public. 33 The Central Government may sanction the opening of the line as

such or subject to conditions it considers necessary for public safety. 34 If the

Commissioner is of the opinion that the use of the metro will “attend danger to

the public using it”, they may send a report to the Central Government, which

may in turn direct that the metro be closed or may be open for public carriage

only subject to certain conditions. 35 The powers of the Central Government

may be delegated to the Commissioner. 36

63. The structure and safety of the project, as certified by the CMRS, were thus

relevant before the Tribunal, making the CMRS certificate a vital piece of

evidence in deciding the issue. The CMRS certificate was relevant evidence

about the safety of the structure. Considering the statutory scheme of the

2002 Act, especially Section 15, the Tribunal erred in deeming the sanction

irrelevant to its central issue – which was the validity of the termination, which,

according to the cure notice, was premised on safety.

32 Section 14, Metro Railways (Operations and Maintenance) Act 2002. 33 Section 15, ibid.

34 Section 15(3), ibid.

35 Section 18, ibid.

36 Section 21, ibid.

Page 34 of 39 PART G

64. Overall, the cure notice places great emphasis on the safety of the

passengers, which, they claimed stood compromised by defects, justifying

discontinuation of operations. This issue falls directly within the domain of the

Commissioner under the scheme of the 2002 Act.

65. Rather than considering the vital evidence of the CMRS certificate towards

safety and effective steps, the arbitral tribunal focussed on the conditions

imposed by the Commissioner on speed and regarding inspections. While the

Division Bench correctly noted that the certificate was relevant for the issue of

the validity of termination, this Court held that safety was not in issue, even

though DAMEPL insisted on discontinuing operations citing safety concerns.

We respectfully disagree with this Court’s re-assessment of the Division

Bench’s interpretation. The cure notice was relevant for the reasons stated

above. Moreover, the fact that DAMEPL premised it on safety could not have

been overlooked by the Tribunal. In doing so, it overlooked vital evidence

pertaining to an issue that goes to the root of the matter. The cure notice was

obviously on the record and merited consideration for its contents bearing on

vital elements of safety.

66. The cure notice, which contains statements bearing on the safety of the line

and other material indicating that the line was running uninterrupted are

matters of record. While the cure notice contains allegations about the line not

being operational, there is evidence on the record indicating that the line was

in fact running. Even if we were to accept that the finding of the arbitral

tribunal that the defects were not completely cured during the cure period is a

Page 35 of 39 PART G

factual finding incapable of interference, it is clear from the record that DMRC

took steps towards curing defects which led to the eventual resumption of

operations. The award contains no explanation as to why the steps which

were taken by DMRC were not ‘effective steps’ within the meaning of the

termination clause.

67. In essence, therefore the award is unreasoned on the above important

aspects. It overlooks vital evidence in the form of the joint application of the

contesting parties to CMRS and the CMRS certificate. The arbitral tribunal

ignored the specific terms of the termination clause. It reached a conclusion

which is not possible for any reasonable body of persons to arrive at. The

arbitral tribunal erroneously rejected the CMRS sanction as irrelevant. The

award bypassed the material on record and failed to reconcile inconsistencies

between the factual averments made in the cure notice, which formed the

basis of termination on the one hand and the evidence of the successful

running of the line on the other. The Division Bench correctly held that the

arbitral tribunal ignored vital evidence on the record, resulting in perversity

and patent illegality, warranting interference. The conclusions of the Division

Bench are, thus, in line with the settled precedent including the decisions in

Associate Builders (supra) and Ssangyong (supra).

Page 36 of 39 PART H

H. Conclusion

68. The judgment of the two-judge Bench of this Court, which interfered with the

judgment of the Division Bench of the High Court, has resulted in a

miscarriage of justice. The Division Bench applied the correct test in holding

that the arbitral award suffered from the vice of perversity and patent illegality.

The findings of the Division Bench were borne out from the record and were

not based on a misappreciation of law or fact. This Court failed, while

entertaining the Special Leave Petition under Article 136, to justify its

interference with the well-considered decision of the Division Bench of the

High Court. The decision of this Court fails to adduce any justification bearing

on any flaws in the manner of exercise of jurisdiction by the Division Bench

under Section 37 of the Arbitration Act. By setting aside the judgement of the

Division Bench, this Court restored a patently illegal award which saddled a

public utility with an exorbitant liability. This has caused a grave miscarriage of

justice, which warrants the exercise of the power under Article 142 in a

Curative petition, in terms of Rupa Hurra (supra).

69. The Curative petitions must be and are accordingly allowed. The parties are

restored to the position in which they were on the pronouncement of the

judgement of the Division Bench. The execution proceedings before the High

Court for enforcing the arbitral award must be discontinued and the amounts

deposited by the petitioner pursuant to the judgment of this Court shall be

refunded. The part of the awarded amount, if any, paid by the petitioner as a

result of coercive action is liable to be restored in favour of the petitioner. The

Page 37 of 39 PART H

orders passed by the High Court in the course of the execution proceedings

for enforcing the arbitral award are set aside.

70. Before concluding, we clarify that the exercise of the curative jurisdiction of

this Court should not be adopted as a matter of ordinary course. The curative

jurisdiction should not be used to open the floodgates and create a fourth or

fifth stage of court intervention in an arbitral award, under this Court’s review

jurisdiction or curative jurisdiction, respectively.

71. In the specific facts and circumstances of this case to which we have

adverted in the course of the discussion, we have come to the conclusion that

this Court erred in interfering with the decision of the Division Bench of the

High Court. The judgment of the Division Bench in the appeal under Section

37 of the Arbitration and Conciliation Act 1996 was based on a correct

application of the test under Section 34 of the Act. The judgment of the

Division Bench provided more than adequate reasons to come to the

conclusion that the arbitral award suffered from perversity and patent illegality.

There was no valid basis for this Court to interfere under Article 136 of the

Constitution. The interference by this Court has resulted in restoring a patently

illegal award. This has caused a grave miscarriage of justice. We have

applied the standard of a ‘grave miscarriage of justice’ in the exceptional

circumstances of this case where the process of arbitration has been

perverted by the arbitral tribunal to provide an undeserved windfall to

DAMEPL.

Page 38 of 39 PART H

72. The curative petitions are allowed in the above terms.

73. Pending applications, if any, stand disposed of.

…...…...….......………………....…CJI.

[Dr Dhananjaya Y Chandrachud]

..…...…...….......………………....…..J. [B R Gavai]

…....…...….......………………....…..J. [Surya Kant]

New Delhi April 10, 2024

Page 39 of 39

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free