Delhi ERC vs Tata Power Delhi Distribution Ltd.
- Neutral2026 INSC 461
Ratio decidendi
The rule this decision rests on
Where a generating utility's operational and tariff recovery period is fixed by regulatory approval to a specific duration shorter than the technical useful life of the asset, depreciation recovery in tariff determination is limited to the approved operational period and cannot extend beyond it, notwithstanding that the asset's technical useful life may be longer. Tariff regulations prescribing depreciation methodology over an asset's useful life must be construed harmoniously with provisions limiting tariff entitlement to the period specified in the Power Purchase Agreement or regulatory approval, and cannot be read to confer an absolute right to recover depreciation beyond the approved operational period. Section 61(d) of the Electricity Act, 2003, which mandates safeguarding of consumer interest in tariff determination, is a central guiding principle that must be weighed against cost recovery entitlements; consumers cannot be required to bear tariff charges for supply of electricity beyond the period during which electricity was actually supplied to them. Where a generating utility is permitted to operate an asset as a merchant generator or to sell the asset without legal impediment after the conclusion of its approved operational period, the utility cannot recover unrecovered capital costs from distribution consumers or retail consumers beyond that approved period through tariff charges. True-up proceedings under tariff regulations are intended to give effect to the approved tariff framework and not to reopen, reconfigure, or alter the conditions and duration of that framework.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
2026 INSC 461 REPORTABLE
IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 6388 OF 2025
DELHI ELECTRICITY REGULATORY COMMISSION ... APPELLANT
VERSUS TATA POWER DELHI DISTRIBUTION LIMITED … RESPONDENT
JUDGMENT
ALOK ARADHE, J.
1. This appeal under Section 125 of the Electricity Act, 2003,
(2003 Act) preferred by Delhi Electricity Regulatory Commission
(Commission) challenges the correctness and legality of the
judgment and order dated 10.02.2025 passed by the Appellate
Tribunal for Electricity (APTEL). By the impugned judgment,
APTEL has set aside the order dated 11.11.2019 passed by the
Commission and issued the direction that entire capital cost of
Rithala Combined Cycle Power Plant at Rithala, Delhi (the
Plant) be permitted to be recovered through depreciation over a Signature Not Verified Digitally signed by Jayant Kumar Arora
period of fifteen years notwithstanding the admitted fact that Date: 2026.05.07 17:04:49 IST Reason:
1
the Plant ceased to supply electricity to the consumers from
and after March-2018.
2. The facts giving rise to this litigation though substantially not
in dispute, are required to be set out, in order to appreciate the
competing legal submissions advanced before us.
FACTUAL MATRIX
3. The respondent, Tata Power Delhi Distribution Limited (TPDDL)
is a joint venture entity between the Tata Power Company
Limited and Delhi Power Company Limited. On 11.06.2017,
TPDDL moved a proposal for allotment of land at Rithala for
setting up a temporary 108-megawatts Gas-based Power Plant
with operational tenure expressly limited to 5 to 6 years,
following which the land would revert to the Delhi Development
Authority (DDA). The genesis of the project lay in the pressing
and urgent need to augment power supply in the National
Capital Territory of Delhi in the lead-up to the Commonwealth
Games 2010. The Plant was conceived as a short-term measure
to address peak demand and accordingly, approval was
structured within a limited operational horizon. On
24.07.2007, TPDDL addressed the letter to the DDA seeking
2 change of land use specifically for a short-term 5 to 6 years
operational span of the Plant.
4. On 17.05.2008, TPDDL intimated Commission of its intention
to establish and operate the Plant. The Commission sometime
in April-2009 granted in principle approval for the scheme
based on TPDDL’s proposal submitted in the year 2008. On
27.07.2009, Generation and Distribution divisions of TPDDL
executed an intra company “Terms and conditions for sale and
purchase of power for the Plant”. The TPDDL on 21.08.2009
filed a petition namely, petition no. 11 of 2009, before the
Commission under Section 62 read with Section 86 (1)(b) of the
2003 Act, seeking approval of the said terms and conditions. A
second petition namely, petition no. 7 of 2010, was filed on
26.02.2010, seeking approval for the use of 6 acres land for
setting up 108-megawatts Power Generation Plant at Rithala,
New Delhi. A third petition namely, petition no. 6 of 2013, was
filed by TPDDL on 23.11.2012, seeking determination of the
final generation tariff from the Plant.
5. The Plant achieved commercial operation in open cycle mode on
04.02.2011 and in combined cycle mode on 04.09.2011. The
3 Commission disposed of all the three petitions filed by TPDDL
by a common order dated 31.08.2017, the details of which are
as follows:
(i) The Commission allowed petition no. 11 of 2009 to
the extent of permission granted by Government of
National Capital Territory of Delhi (GNCTD) for a
period of six years from the year of commissioning of
the Plant in combined cycle mode, thereby fixing the
operation and supply period up to March-2018.
(ii) The Commission allowed petition no. 7 of 2010
subject to the condition that any profits from the
Plant would be governed by provisions of DERC
(Treatment of Income from Other Business of
Transmission Licensee and Distribution Licensee)
Regulations, 2005.
(iii) The Commission allowed petition no. 6 of 2013 and
approved the fixed charges and operational
parameters required for computation of energy
charges and directed the TPDDL to file true-up
petitions for finalisation of generation tariff for the
respective years.
4
6. The Commission by its order dated 31.08.2017, determined the
capital cost of the Plant at ₹197.70 crores after applying
appropriate benchmarking and prudence checks as against the
TPDDL’s claimed capital cost of ₹320.17 crores. It is noteworthy
that the said capital cost determination was made in the
backdrop of six years operational framework. The Commission
accepted a technical useful life of the Plant of fifteen years
based on experts certification, and it restricted the operational
and tariff recovery framework to a period of six years. The Plant
was thus allowed to operate for supply purposes only till
March-2018. The TPDDL did not challenge the aforesaid order
by way of an appeal and therefore the order dated 31.08.2017
has become final and binding inter-parties.
7. Subsequently, TPDDL filed a petition namely, petition no. 51 of
2017, seeking true-up of expenditure for Financial Years 2010-
2011 to 2016-2017 and the annual requirements for Financial
Year 2017-2018. The Commission, by an order dated
11.11.2019, allowed depreciation at the rate of 6% per annum
in respect of the Plant only up to Financial Year 2017-2018
resulting in cumulative depreciation of ₹83.34 crores. The
remaining capital cost of approximately ₹94.59 crores together
5 with carrying cost, was not allowed to be passed through in
tariff, on the ground that Plant has ceased to supply electricity
to the consumers after March-2018.
8. The aforesaid order of the Commission was challenged by
TPDDL in an appeal. The APTEL by an order dated 10.02.2025
inter alia held that the Commission itself had fixed the useful
life of the Plant at fifteen years and had computed the capital
cost on that basis. Therefore, the depreciation cost cannot be
restricted only to six years. The APTEL further held that
Regulation 6.32 of the DERC (Terms and Conditions for
Determination of Generation Tariff) Regulations, 2011 (2011
Regulations) mandated depreciation over the useful life and did
not admit of any exception. The APTEL, therefore, set aside the
order of the Commission and remanded the matter to it with a
direction to allow recovery of entire capital cost of the Plant by
way of depreciation over the useful life of the Plant for fifteen
years.
9. Aggrieved by the said judgment the Commission has preferred
the present appeal.
SUBMISSIONS
10. Learned senior counsel for the Commission submitted that
APTEL erred in not appreciating that TPDDL cannot recover the
capital cost of the Plant either from the distribution licensee or
6 from the retail consumers of Delhi, in respect of electricity not
supplied and to fasten the liability on the consumers for a
period beyond March-2018 is contrary to Section 61 (d) of the
2003 Act. It is contended that APTEL misapplied Regulation
6.32 of 2011 Regulations and ought to have appreciated that
TPDDL was free to exploit the Plant beyond six years to recover
its capital cost. It is, therefore, submitted that the impugned
order be set aside and the appeal be allowed.
11. Learned senior counsel for the TPDDL, on the other hand,
submitted that TPDDL is entitled to recover depreciation in
terms of Regulation 6.32 of 2011 Regulations, as the same does
not restrict depreciation only to the operational life or the
duration of the Power Purchase Agreement (PPA). It is
contended that TPDDL is only seeking to recover balance
recovery of depreciable capital cost of the Plant. It is urged that
Commission must abide by and implement the directions of
APTEL to secure accountability and disproportionate increase
and long pending regulatory asset depict a regulatory failure
which has serious consequences on all stakeholders and the
ultimate burden is only on the consumer 1. It is urged that the
1 BSES Rajdhani Power Ltd. & Anr. v. Union of India & Ors., 2025 SCC OnLine SC 1637 7 order of the APTEL does not call for any interference in this
appeal.
ISSUES
12. We have considered the rival submissions on both sides and
have perused the record. Section 125 of the 2003 Act provides
for a remedy of appeal to an aggrieved person from the decision
or order of APTEL to this Court, on any one or more of the
grounds specified in Section 100 of the Code of Civil Procedure,
1908.
13. Upon consideration of the pleadings, the record of the
proceedings before the Commission and APTEL, and the
submissions of learned counsel for the parties, following
substantial questions of law arise for determination in this
appeal:
(i) Whether the depreciation under the applicable tariff
regulations must necessarily be allowed over the entire
technical useful life of an asset irrespective of the period
during which the asset is actually utilised for supply of
electricity?
(ii) Whether Regulation 6.32 of 2011 Regulations confers an
absolute right upon the generating utility to recover
entire capital cost over the useful life of the asset, even
8 where the asset ceases to supply electricity to the
consumer?
(iii) Whether the APTEL erred in law in disregarding the
regulatory framework and approval conditions which
limited the operational and recovery period of the Plant
to six years?
STATUTORY FRAMEWORK
14. Before proceeding further, it is useful to set out the statutory
and regulatory provisions that have bearing on the questions
which arise for consideration in this appeal.
15. Section 61 of the 2003 Act governs the determination of tariff.
Section 61(d) specifically provides that in specifying the terms
and conditions for the determination of tariff, the Appropriate
Commission shall be guided, inter alia, by the object of
safeguarding consumers’ interests and at the same time,
recovery of the cost of electricity in a reasonable manner. This
provision establishes consumer welfare not as a peripheral
consideration but as a central and guiding statutory principle in
tariff determination.
16. Section 62 of the 2003 Act empowers the Commission to
determine tariff for supply of electricity by a generating company
9 to a distribution licensee, in accordance with the provisions of the
2003 Act and the Regulations made thereunder.
17. Regulations 6.30 to 6.32 of the DERC (Terms and Conditions
for Determination of Generation Tariff) Regulations, 2011 provides
as follows:
“6.30 Depreciation shall be calculated for each year of the Control Period, on the amount of Capital Cost of the Fixed Assets as admitted by the Commission; Provided that depreciation shall not be allowed on assets funded by any capital subsidy/grant.
6.31 Depreciation for each year of the Contral Period shall be determined based on the methodology as specified in these Regulations along with the rates and other terms specified in Appexdix-1 of these Regulations.
6.32 Depreciation shall be calculated annually, based on the straight line method, over the useful life of the asset. The base value for the purpose of depreciation shall be capital cost of the asset as admitted by the Commission. Provided that, the remaining depreciable value as on 31st March of the year closing after a period of 12 years from the date of commercial operation shall be spread over the balance useful life of the assets.”
18. Regulation 4.1 of the 2011 Regulations mandates that the tariff
for supply of electricity by the generating company to the
distribution licensee shall be in accordance with the PPA or any
other arrangement for such period as may be approved or
10 adopted by the Commission, to the extent of the existing
installed capacity as contained in the PPA.
ANALYSIS AND FINDINGS
Question No. (i)
19. The Commission while computing the capital cost of the Plant
for determination of final generation tariff, by an order dated
31.08.2017, found that useful life of the Plant is fifteen years.
However, the Commission vide order dated 31.08.2017, approved
the PPA which restricted the period of operation and supply up
to March-2018, i.e., for a period of six years. Admittedly, a sum
₹83.34 crores has been approved as depreciation for the
aforesaid period of six years.
20. The tariff determination is not merely a mathematical exercise
but a regulatory balancing act. The object of enabling reasonable
cost recovery for utilities must be weighed against and calibrated
with, paramount obligation to safeguard consumer interest. In
the instant case, admittedly, electricity has not been supplied to
the consumers beyond March-2018. The consumers cannot be
required to pay for a service which they no longer received.
Under the PPA, TPDDL had to supply electricity only for a period
of six years. It is also pertinent to note that the Commission on
04.09.2012, had clarified to the Managing Director of TPDDL
11 that the plant could be treated as a merchant generator which is
free to sell the power anywhere other than to the distribution
utilities in Delhi or outside the State or to captive consumers
within the State. There was no legal impediment to either sale of
the Plant or sale of electricity as a merchant generator.
Therefore, TPDDL cannot be permitted to burden the consumers
with tariff charges beyond March-2018. Therefore, the first
substantial question of law is answered in the negative. Question No. (ii)
21. Regulation 6.32 of 2011 Regulations prescribes the
methodology of calculating depreciation over the useful life of the
asset. It is a settled canon of statutory interpretation that no
provision has to be read in isolation. Regulation 6.32 of 2011
Regulations must be construed harmoniously with Regulation
4.1 of 2011 Regulations, which mandates that the tariff for
supply of electricity by a generating company to a distribution
licensee is to be determined in accordance with PPA or any other
arrangement for such period as may be approved or adopted by
the Commission, to the extent of existing installed capacity
contained in the PPA. Regulation 4.1 of 2011 Regulations
confines tariff entitlement to the period approved in the PPA. The
order dated 31.08.2017 fixed the operational and recovery
12 framework of the plant up to March-2018. The 2011 Regulations
have to be read in conjunction with Section 61(d) of the 2003 Act
which places the consumer interest at the centre of tariff
Regulation. Thus, Regulation 6.32 of the 2011 Regulations does
not, and cannot, override the broader statutory and regulatory
framework and the same does not confer an absolute and
unconditional right upon the generating utility to recover
depreciation from the consumers even for a period when the
asset is free to supply electricity. For the aforementioned
reasons, the substantial question of law no. (ii) is also answered
in the negative.
Question No. (iii)
22. The GNCTD granted permission on a temporary basis for a
period 5 to 6 years. The TPDDL was directed to obtain all
necessary regulatory approvals before commencing generation.
The Commission in its order dated 31.08.2017, which was not
challenged by TPDDL, approved the PPA only for a period of six
years from the date of commercial operation till March-2018. The
APTEL ought to have appreciated that distinction between 15
years technical useful life and 6 years regulatory recovery period
is not merely semantic but the tariff framework drew the
distinction clearly. The APTEL’s approach is inconsistent with the
13 order dated 31.08.2017, which was accepted by TPDDL and had
attained finality. The True-up proceedings are intended to give
effect to tariff framework and not to reopen or reconfigure it. The
APTEL erred, therefore, in disregarding the regulatory framework
and conditions of approval. Therefore, the third substantial
question of law, is answered in the affirmative.
23. For the foregoing reasons, the substantial questions of law
which arise for consideration in this appeal, are answered in
favour of the Commission and against the TPDDL. The impugned
judgment dated 10.02.2025 passed by the APTEL is set aside and
order dated 11.11.2019 passed by the Commission is restored.
24. In the result, appeal is allowed. There shall be no order as to
costs.
.…..………………….………….……….J. [PAMIDIGHANTAM SRI NARASIMHA]
…..…….……………….………….……….J. [ALOK ARADHE]
NEW DELHI;
MAY 7, 2026.
14
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free