Miss Lucy
← All judgments

Cci Projects (P) Ltd. vs Vrajendra Jogjivandas Thakkar

Supreme Court27 November 2018R. Subhash Reddy · Uday Umesh Lalit

Ratio decidendi

The rule this decision rests on

1. Where there is a transfer of immovable property within a family and the transferees have been living together with the transferors, a complaint for compensation for delayed delivery of possession filed by the subsequent transferee is maintainable, notwithstanding that the original allottees had transferred their interest; the principle in *Haryana Urban Development Authority v. Raje Ram* that a complaint is not maintainable by a subsequent transferee does not apply where the transfer is within the family rather than to a stranger. 2. Where a builder is required by law to re-submit plans and obtain fresh statutory clearances (such as fire safety permission) after the original agreement is executed, the time taken to comply with these mandatory legal requirements constitutes a valid ground for extension of the delivery date under a force majeure or extension clause, and the builder is entitled to have that period excluded from any calculation of unexplained delay. 3. Where there is a reduction in the availability of a key construction material in the market (such as sand) due to regulatory restrictions, even if not a complete ban, the builder is entitled to some consideration in the form of reduced compensation for delayed delivery, as this constitutes a circumstance affecting the supply chain beyond the builder's control. 4. In consumer disputes regarding delayed delivery of immovable property, where a builder is found to be responsible for delay but only for a portion of the total delay period, the consumer is entitled to compensation by way of interest on the amounts paid, calculated at a reasonable rate for the period of unexplained delay; where the exact calculation of such interest would be complex, a court may award a lump sum compensation in substitution of interest directions to meet the ends of justice.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

1

Reportable

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL Nos. 6784-6785 OF 2018

CCI Projects (P) Ltd. ……Appellant

VERSUS

Vrajendra Jogjivandas Thakkar ..…. Respondent

WITH

CIVIL APPEAL Nos. 6786-6787 OF 2018 (CCI Projects (P) Ltd. vs. Vrajendra Jogjivandas Thakkar)

JUDGMENT

Uday Umesh Lalit, J.

1. These appeals under Section 23 of the Consumer Protection Act, 1986

are directed against the common order dated 23.01.2018 passed by the

National Consumer Disputes Redressal Commission, New Delhi

(“Commission” for short) in Consumer Case Nos.975 and 976 of 2016. Signature Not Verified Digitally signed by MUKESH KUMAR Date: 2018.11.27 17:50:17 IST Reason:

2. In Consumer Case No.976 of 2016, Vrajendra J. Thakkar, HUF had

booked a residential flat with the appellant in a project named “White Spring 2

Building”, which the appellant was to construct at Village Magathane

Dattapada Road, Borivali (East), Mumbai, for a consideration of

Rs.90,38,850/- and flat No.6A in the building was allotted to said Vrajendra J.

Thakkar, HUF. The parties entered into an agreement dated 30.10.2012 and

in terms of Clause 17 of said Agreement, the possession was to be delivered

by August, 2014. However, in terms of the Agreement, the date of delivery of

possession would stand automatically extended in the event of any of the

contingencies specified in the said clause which was to the following effect:

“Possession of the said Premises in the said Building shall be given by The Promotor to the Purchaser on or before August, 2014 on a “best effort” basis. Provided that in the even of occurrence of any of the following events, the aforesaid date of possession shall automatically stand extended by a period by which the possession is delayed on account of such event(s) –

(a) Non-availability of steel, cement, other building of construction materials, water or electricity supply;

(b) War, civil commotion, strike, lockout, riots, acts of terrorism, epidemics, earthquake, flood, other act of God, any prohibitory order of any court, tribunal or authority against the development of the said Properties:

(c) Any notice, order, rule, notification, circular of the Government and/or other public or competent authority, court, tribunal or Quasi-judicial body or authority;

(d) Delay in getting NOC, permissions licenses, approvals, consents, connections, plans, occupancy, 3

certificate, completion certificate and permissions from MCGM and other authorities/bodies.

(e) Change in any law, rules, regulations, bye-laws of any Government, authorities, public/local bodies affecting the development of the said Properties.

(f) Any notice/direction notification, order from the forest department, Ministry of environmental department, pollution control department, MCGM, any Government Department or public body/local Authority, in respect to the said Properties;

(g) Delay or default in payment of the balance purchase price and/or other amounts payable hereunder by the Purchaser to the Promoter (without prejudice to the right of the Promoter to terminate this Agreement in terms of clause 12 above.”

3. Said Vrajendra Thakkar, HUF thereafter transferred the allotment in

favour of mother of the present respondent namely Kumudben Jagjivandas

Thakkar. Said Kumudben Thakkar thereafter gifted the very same Apartment

to the present respondent.

4. In Consumer Case No.976 of 2016, Smt. Hemali Vrajendra Thakkar

had booked a residential flat with the appellant in the same project and Flat

No.6B was allotted to her for the same consideration of Rs.90,38,850/-. She

also entered into similar agreement dated 30.10.2012 having identical clauses

including the aforesaid Clause No.17 to deliver the possession by August,

2014. Later, the aforesaid allotment was transferred by Hemali Vrajendra 4

Thakkar in favour of her mother-in-law namely Kumudben Thakkar who in

turn gifted the same to the respondent herein. The gift deed dated 19.08.2015

contained one of the recitals as under:

“And Whereas, although the Donee has other siblings too but right from beginning the Donor and her late husband had been staying with the Donee and his family at the aforementioned address and it is only the Donee who had been taking care of each and every thing of the Donor and her husband from the smallest to the biggest of their requirements. … … …”

5. On or about 02.06.2016, the aforesaid Consumer Case Nos.975 and

976 of 2016 were filed contending inter alia that though sum of

Rs.85,86,911/- had been deposited in respect of each of the flats, no

possession was delivered by the appellant. In the circumstances following

reliefs were prayed for:

“a. OP be directed to handover the legal possession of flat to complainant within one month AND b. OP be directed to pay to Complainant 18% interest per annum on Rs.85,86,911/- from September 2014 on the consideration amount already paid to OP till OP handover the possession of the flat to Complainant. Or c. if granting prayer a) & b) is legally not possible then in alternative OP be directed to hand over any other newly constructed flat to complainant consisting same area, at the same rate in same locality in tower with same facility. OR 5

d. OP be directed to refund the Complainant Rs.2,00,00,000/- (Rupees Two Crore) the current market value of the said flat. AND e. AND OP be directed to pay the complainant 18% interest per annum on Rs.85,86,911/- from September, 2014 on the consideration amount already paid to OP till OP refund complainant Rs.2,00,00,000/- the current market value of the said flat. AND f. OP be directed to pay complainant Rs.5,00,000/- as compensation for causing mental stress, harassment and agony. AND g. OP be directed to pay to Complainant Rs.1,00,000/- as litigation cost.

h. Any other relief as Hon’ble Commission deem fit and proper.”

6. The appellant resisted the complaints and submitted that the

construction activity had begun after obtaining requisite permissions.

However, New Development Control Rules stood notified in 2012 which

obliged the builder/developer to prefer fresh application after seeking

mandatory permission from the Fire Department. An application in that behalf

was made on 21.12.2012 after complying with the mandatory provisions but

the amended No Objection Certificate came to be granted only on 07.05.2013.

Additionally, between August, 2013 till September, 2015 i.e. for more than 24

months there was restriction on sand mining activity as a result of which, one

of the basic raw material for construction had become scarce in the market. It 6

was further stated that the complainants themselves were in default and as

such demand for payment of Rs.1,04,207/- in respect of each of the flats

towards interest on outstanding amounts was raised and appropriate debit

notes were issued by the appellant.

7. During the pendency of the matters before the Commission, the

possession of the aforesaid flats 6A and 6B was offered by the appellant vide

letter dated 16.11.2016. On 10.07.2017 the Commission directed the

complainants to pay admitted sums to the appellant and to deposit the

disputed sums with the Commission, whereafter the possession of the flats

was taken on 04.08.2017. The matters before the Commission thus stood

confined to the issue whether the complainants in both the cases were entitled

to any compensation in respect of delayed payment or whether the appellant

was entitled to have the period extended in terms of aforesaid clause No.17.

8. The Commission rejected the submission in respect of amended NOC

granted on 07.05.2013. It further rejected the submission regarding non-

availability of sand by observing that no document had been placed on record

to substantiate such claim. The Commission observed that except the sum of

Rs.104,207/- which the appellant sought to recover towards interest for

delayed payment, rest of the sums were not disputed by the complainants and 7

stood paid to the appellant. After considering the rival claims the

Commission disposed of the complaints with following directions:

“1. The balance, if any, out of the amount deposited by the complainant with this Commission before taking possession of the flat and proportionate interest which may have accrued on that amount deducting (i) the interest amount of Rs.10427/- (in both the complaints) and (ii) an amount equivalent to compensation payable to the complainant in terms of direction (3) below, shall be released to the opposite party.

2. The amount of Rs.104207/- shall (in both the cases) be released to the complainant along with proportionate interest which may have accrued on that amount.

3. The opposite party shall pay compensation in the form of simple interest @ 8% per annum on the amount which had been paid by that date, to the complainant, w.e.f. 01.09.2014 till the date on which the possession was actually delivered to him. The compensation to the extent available shall be adjusted out of the amount payable to the complainant in terms of direction (1) above.

4. The opposite party shall also pay Rs.25,000/- as the cost of litigation in each complainant to the complainant.

5. The payment by the OP in terms of the order shall be made within three months from today.” 8

9. In these appeals challenging the correctness of the decision of the

Commission, we heard Mr. Sanjiv Sen, learned Senior Advocate and Dr.

Vinod Kumar Tewari, learned Advocate for the parties.

10. It was submitted by Mr. Sanjiv Sen, learned Senior Advocate:

(a) The complaints were not maintainable in as much as the original

allottees had transferred their interest. Reliance was placed on the

decision of this Court in Haryana Urban Development Authority

v. Raje Ram1.

(b) The time lost between 21.12.2012 till 07.05.2013 on account of

mandatory requirement for re-submission of plans, the appellant

was entitled to have that period extended.

(c) The National Green Tribunal had banned sand mining activities

across the country on 05.08.2013 which came to be relaxed only

when new policy was formulated by Union of India in September,

2015. It was submitted that the availability of sand during this

period had come down to 20% of what it was before.

It was therefore submitted that the appellant was not at fault. In any

case the possession was offered on 16.11.2016 and thus it was only a short

1 (2008) 17 SCC 407 9

period of more than 2 years between August, 2014 and 16.11.2016 which was

the period in question. In his submission, the period stood completely

explained and as such the Commission was not justified in imposing liability

on the appellant.

11. The learned Advocate for the respondent on the other hand submitted

that the transfers effected by the parties were within the family. He submitted

that the appellant was not entitled to any extension of period. He further

submitted that the order passed by the National Green Tribunal had banned

illegal sand mining activity and not sand mining activity itself. The sand was

thus available in market.

12. We have gone through the record and considered the rival

submissions. The decision of this Court in the case of Haryana Development

Authority (supra) turned on individual facts of the case where the very

entitlement of the subsequent allottees to claim damages or compensation for

delayed delivery of possession was found to be unsustainable. Said decision

of this Court related to cases where the original allottees had transferred the

allotment in favour of total strangers with the permission of the authority and

as found by this Court, the subsequent allottees were aware that there was 10

delay in delivering the allotted plots on account of time taken in forming the

layout or on account of encroachment and yet had purchased the interest of

the original allottees. In the present case the transfers were effected within the

family where the members had been living together. The decision of this

Court in Haryana Urban Development Authority (supra) cannot be stretched

to say that in every case where there is a transfer, the complaint by the

subsequent transferee would not be maintainable at all.

13. At the same time, the appellant is justified in saying that as a result of

mandatory requirements to resubmit the plans and get the fresh NOC in

respect of fire safety permission, the period between 21.12.2012 to

07.05.2013 stood completely explained. Thus, out of the period between

August, 2014 till 16.11.2016, the appellant would be entitled to have a period

of 6 months of extension. That still leaves us with a period of a year and 8

months. The Commission has awarded 8% interest on the deposited sum.

The deposited sum in either case being Rs.85.86 lakhs, going by the direction

issued by the Commission, the interest element in respect of the period of one

year and 8 months would be in the region of Rs.11.4 lakhs. We now consider

the second part of the submission. It is true that there was no complete ban on

sand mining. But as a result of reduced availability of sand in the market, the 11

demand and supply ratio must have been upset. The appellant would therefore

be entitled to some benefit on that count.

14. Considering the entirety of the matter, in our view, instead of direction

No.3 issued by the Commission, a lumpsum payment of Rs.5 lakhs in

substitution of said direction, would meet the ends of justice. We, therefore,

modify the directions issued by the Commission. Retaining directions 1, 2 &

4, the direction No.3 is substituted and in its place the appellant would be

required to pay a lumpsum compensation of Rs.5 lakhs to the respondent in

respect of each case. We direct that all the sums covered by the directions

shall be made over within 2 months from today failing which the respondent

complainant shall be entitled to 8% interest on the amounts in question.

15. With these directions civil appeals stand disposed of. No costs.

......………..……..……J. (Uday Umesh Lalit)

..……..…..……………J. (R. Subhash Reddy) New Delhi, November 27, 2018

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free