Miss Lucy
← All judgments

Birla Corporation Limited vs Bhanwar Singh And Ors.

Supreme Court12 January 2024

Ratio decidendi

The rule this decision rests on

Where a protected monument of national importance and UNESCO World Heritage Site status is exposed to potential structural damage from mining and blasting operations in proximity, a complete prohibition of mining and blasting activities is not warranted solely on the basis of reasonable precaution or generalized apprehension; instead, the court must examine scientific and expert evidence on the actual impact of such operations at specified distances before imposing restrictions. The safe minimum distance from a protected monument below which mining operations involving explosives must be prohibited should be determined by expert investigation that considers the cumulative peak particle velocity induced by blasting operations at various distances, the nature and resilience of the monument's structures, and the findings of credentialed research institutions, rather than by accepted liberal recommendations alone if those recommendations remain unverified through detailed empirical study. Environmental damage to a protected monument from mining and blasting activities, even if established, does not necessarily justify a blanket ban on all mineral extraction in the surrounding area; instead, a proportionate response that permits mechanical mining while restricting only those extraction methods scientifically demonstrated to cause harm is appropriate where the evidence supports differentiation. Where expert reports on the impact of blasting on a heritage monument differ in their conclusions regarding safe distances, and the evidence suggests that technological advancements may alter the risk profile, the court should not definitively resolve the matter through existing studies but must commission further investigation by independent multi-disciplinary experts before issuing final prohibitory orders. The preservation of a protected monument is a multi-dimensional undertaking that cannot be addressed by restrictions on a single activity (such as blasting) alone; it must simultaneously address all identified causes of structural deterioration, including tourist footfall, maintenance deficiencies, animal interference, and vegetation growth, with coordinated action by the relevant authorities.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

2024 INSC 35 NON-REPORTABLE

IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION

S.L.P.(C) No. 21211 of 2012

BIRLA CORPORATION LIMITED THROUGH ITS MANAGING DIRECTOR … PETITIONER

VERSUS

BHANWAR SINGH AND OTHERS … RESPONDENT(S)

WITH

SLP (C) No. 22377 of 2012

WITH

SLP (C) NO. 23551 OF 2012

WITH

SLP (C) NO. 29698 OF 2012

WITH

SLP (C) NO. 25186 OF 2012

WITH

SLP (C) NO. 31905 OF 2013 Signature Not Verified Digitally signed by SWETA BALODI Date: 2024.01.12 WITH 17:11:05 IST Reason:

SLP (C) NO. 31724 OF 2012

1 ORDER

1. The Chittorgarh Fort represents the quintessence of a tribute to

nationalism, courage, medieval chivalry, and sacrifice exhibited between

the seventh and the sixteenth centuries by several rulers, like the Mewar

rulers of Sisodia, their kinsmen, women, and children. The Chittorgarh Fort

has weathered and withstood many battles and has been a witness to the

power and pride of the kings who occupied the Fort. The history is replete

with brave, extraordinary and indomitable courage exhibited by the rulers

and occupants of the Fort.

1.1 The Chittorgarh Fort is a notified monument under the Ancient and

Historical Monuments and Archaeological Sites and Remains (Declaration

of National Importance) Act, 1951 and the Ancient Monuments

Archaeological Sites and Remains Act, 1958, and also a notified UNESCO

World Heritage Site. The Fort attracts tourists from far and near for

sightseeing and to look at the tall and strong structures on the hilltop of

Chittorgarh, evidencing the grit and ability to withstand all adversities.

Despite the passage of centuries, from the time of construction, the

2 Chittorgarh Fort retains some significant, world-class structures, including

the Vijay Stambh, Kirti Stambh, Padmini Palace, Kumbha Palace and

Meera Mandir.

2. The Fort’s history and legacy make it a preferred destination for

tourists. The serene hillock, which had less populated surroundings at one

point, is subject to contemporaneous development, urbanisation, etc. The

principal issue considered by the High Court of Rajasthan in the judgement

impugned before us does not deal with the peripheral inconveniences that

the Fort has experienced with the onset of urbanisation and tourism in the

immediate past. But a distinct problem of considerable importance.

3. The immutable geology of the area has limestone formation of the

Vindhyan age, and as per geological study and assessment, the limestone

is located in Nimbahera city. The mineral reserve of this stone occurs

between Nimbahera shales and Suket shales.

4. The limestone is a valuable mineral resource from the perspective

of the State exchequer and is a material or a raw material used in more

than one sense. The State Government granted prospective mining leases

of small, medium and large areas in and around the hillock and the

surrounding areas of the Chittorgarh Fort to individuals/industrial houses.

The exploitation of minerals available in the surrounding area by the

lessees to the State Government, particularly in an unscientific manner or

3 disproportionate exploitation of minerals in hard and rude mining activities,

was seen as a threat to the existential utility of the Chittorgarh Fort and the

structures referred to in paragraph no. 1.1 (supra) of this Order.

5. One Shri Thakur Umed Singh Rathore filed W.P. (PIL) No.

1316/1999 before the High Court of Rajasthan, questioning the blasting

operations undertaken for limestone extraction resulting in possible

damage to the existing structures of the Chittorgarh Fort. The gist of the

complaint is that continuous/frequent exposure of the ancient structures in

the Chittorgarh Fort to the peak particle velocity (PPV) generated by the

explosives used in mineral extraction would damage the heritage

monument, and this negligence of the present generation will leave only

the remnants of the Chittorgarh Fort to the succeeding generations.

6. The issue is undoubtedly of grave concern, and the conflict between

the exploitation of mineral wealth and sustaining the neighbourhood,

stated pithily, adheres to the principle of sustainable exploitation of mineral

resources without adversely affecting the community interest in any

manner.

7. On 06.08.2002, W.P. (PIL) No. 1316/1999 was disposed of. For the

present purpose, we are not referring to the material and the larger

question considered by the Rajasthan High Court in the order dated

06.08.2002, in W.P. No. 1316/1999.

4

8. Respondents Nos. 1 to 6 herein filed W.P. (PIL) No. 6591/2011

before the High Court of Rajasthan against the Union of India through

Archaeological Survey of India (ASI)/Respondent No. 7 herein and others.

The gist of the writ prayer is stated thus:-

i. To protect the Chittorgarh Fort.

ii. To stop blasting within a radius of ten kilometres from the Fort.

iii. To refrain the Mining Department from granting mining leases

within ten kilometres of the radius of the Fort.

iv. To prohibit open blasting within a radius of ten kilometres from

the Fort.

Birla Corporation Limited Chanderiya, Chittorgarh/Petitioner herein is

arrayed as Respondent No. 20 in W.P. (PIL) No. 6591/2011.

9. During the pendency of W.P. No. 6591/2011, the High Court had the

advantage of the replies from the contesting respondents; the affidavits of

government departments setting out their view on all the issues

considered by the High Court in W.P. (PIL) No. 6591/2011 and on the

impact of blasting on the Chittorgarh Fort on 25.05.2012 W.P. (PIL) No.

6591/2011 was disposed of.

10. To conclude this part of the narrative, we refer to the following

paragraphs of the impugned judgement:-

5

“For causing severe damage to the fort structures including Vijay Stambha, Kirti Stambha and Kumbha Mahal and houses and affecting ecology and environment, considering the polluter-pays principle, it is just and proper to direct Birla Cement and other mine holders to pay compensation for restoring back glory of ancient monument to the extent it is possible after damage. A lot of damage has also been caused in the area in question, let restoration and its reclamation be done as expeditiously as possible.

Accordingly, we make the interim order absolute and direct that no mining activities and blasting shall take place within 10 kms from the fort wall. The mining leases granted within 10 kms from fort wall are cancelled. The Birla Cement as well as mine holders are directed to make payment of compensation to the tune of Rs. 5 crores (Five Crores only), out of which, 90% shall be paid by Birla Cement and the remaining amount shall be paid by other mine holders involved in blasting. The amount of compensation shall be kept at the disposal of Archaeological Survey of India (ASI) and be utilized for repair and upkeep of the fort in question. The plan to repair damages and improve facilities be submitted to this Court within four months.”

11. Hence, SLP (C) No. 21211 of 2012 at the instance of Birla

Corporation Limited Chanderiya, Chittorgarh/Respondent No. 20 in W.P.

(PIL) No. 6591/2011.

12. On 20.07.2012, a notice on the SLP was issued. The order dated

18.01.2013 of this Court reads thus:-

“It is evident from the impugned order that the main issue before the High Court pertained to the impact of blasting operations in the periphery of Chittorgarh fort. Hence, the question of a complete ban on mining operations around the fort, even without involving blasting, has not been examined. The parties are ad idem that before making final orders on the prayer for stay of the impugned directions, a report from an expert on the subject matter be called for. It is suggested that in the first instance, the Central Building Research Institute, Roorke, may be asked to conduct a study of impact of mining on the said fort even without blasting operations and submit its interim report. In other words, an expert should evaluate the effect of mining in the fort area, with any kind of manual or electric gadgets, like surface scrappers, rock breakers, etc.

We accede to the prayer and accordingly request the Director of the Said Institute to nominate an expert to undertake the said exercise and submit his report as expeditiously as possible. In any case, interim report shall

6 be submitted within three weeks from today. It will be open to the said expert to consult or seek assistance of any other agency, as he may deem necessary. It is agreed that all the expenses in this regard shall be borne by M/s Birla Corporation Ltd. The Secretarial assistance shall, however, be provided by the State. In the meanwhile, the petitioners are permitted to carry out mining operations manually, without the use of any kind of heavy equipment like the JCBs, Earth movers etc. As the said fort is a protected monument, the ASI shall closely monitor the mining operations. [D.K Jain, Madan B. Lokur, JJ].”

13. On 08.03.2013, as part of monitoring the effect of the mining

activities in the neighbourhood of the Chittorgarh Fort, the consensus

emerged from the submissions made by the parties appearing in this lis,

this Court directed the study of a cumulative impact of peak particle

velocity (PPV) on the structures in the Fort from the blasting operations

undertaken by the lessees of the mining leases. The Petitioner before this

Court possesses a mining lease for 598.98 hectares at a distance of about

4.5 kilometres from the boundary of the Chittorgarh Fort and the Petitioner

challenges the directions issued by the High Court in paragraph no. 10

(supra). A few other SLPs are tagged with the main case. We are not

referring to the challenge in these SLPs, for the directions we are

considering through this order.

14. This Court, permitted the study of cumulative impacts of vibrations

and peak particle velocity (PPV) on the structures in the Fort from the

blasting operations and simultaneously prohibited blasting for any

purpose, including the proposed study, within the radius of one kilometre

from the boundary of the Chittorgarh Fort. This Court directed the Central

7 Building Research Institute, Roorkee (CBRI, Roorkee), to undertake a

comprehensive study of the environmental impact on the subject

monument from the mining and blasting activities by the lessees of the

mining lease within a radius of ten kilometres.

15. CSIR-CBRI, Roorkee, constituted a team of experts and officers to

undertake a comprehensive study to assess the impact of mining by using

explosives on the structural integrity of the Chittorgarh Fort based on the

following terms of reference:-

i. Whether blasting including the cumulative effect of blasting beyond a specified distance has any impact whatsoever upon the structure of the Fort?

ii. What appeared to be the causes that have led to cracks and other damage caused to the Fort, other than ageing simplicitor? iii. Whether the uncontrolled access to tourist has any adverse impact upon the structure and if so, any suggested steps to regulate this activity.

iv. Whether the activities within the colony situated in the Fort as well as the flow of traffic including heavy traffic in the vicinity of the Fort have any adverse consequences upon the structural integrity of the Fort, and if so the suggested measures to deal with the problems.

v. General recommendations on the steps to be taken to restore the structural integrity to repair the cracks and generally ensure that no damage in future is caused to the structural integrity. vi. A comprehensive Environmental Impact Assessment (EIA) covering all kind of pollution-air, ground water, noise etc. by the complete cycle of mining activities including its transportation.

16. CSIR-CBRI, Roorkee, between November 2013 and September

2014, undertook the study of the environmental impact from the mining

activities and generated data from the site during the full-scale blasting

operations both individually and in combinations from the mines. CSIR-

8 CBRI, Roorkee associated the Central Institute of Mining and Fuel

Research (CIMFR) in the study and submitted the Report dated

30.09.2014. It is apposite to excerpt a few of the conclusions in the report

dated 30.09.2014:-

“1.10: General recommendations for all the mines i. Although the vibration induced by blasting was found to be within the permissible limits, it is recommended that continuous vibration monitoring using suitable instruments in each group of mines shall be carried out by the mining personnel. Periodic review, say half yearly of the vibration recoded by each mine operator shall be done by expert agency. This will not only provide control on the unguarded blasting practices but over a period of time, blasting practices will be improved by educating the mine operators, particularly in case of Manpura and Bhairon Singhji ka Khera quarries.

ii. In BSK and Manpura quarries, advanced blasting techniques using delay detonator both electric as well as non-electric initiation systems should be implemented in phased manner by imparting training to the mine operators. This will enhance safety as well as productivity of all the stake holders.

iii. Structural health monitoring of Chittorgarh Fort structures should be carried out for at least another two years by installing number of sensors at critical structures to measure response of the Fort structures during actual mining operations.

iv. DMG shall be given greater responsibility towards the supervision of routine blasting practices in compliance with safety guidelines and MMR 1962 in case of mining of minor minerals.

v. There should be at least one licensed blaster for each group of five small quarries for both BSK and Manpura quarries separately. Only a licensed blaster shall be allowed to conduct blast after following proper safety precautions and evacuation of men and machinery from the danger zone.

vi. In all the basting practices, safety guidelines and approval as suggested by Directorate General of Mines Safety, Dhanbad and other regulatory bodies shall be strictly followed.

1.11 Conclusion:

9 Monitoring of blast-induced vibration and air overpressure were done at more than 500 locations by conducting approximately 100 blasts and mines between 1.0 and 10.0 km. Based on that, the following conclusions are drawn-

1. Review of various National and International standards for safe limit of ground vibration induced by traffic, machinery and blasting reveal that the ground vibration and air overpressure below 2.0 mm/s and 134 dB (L) respectively will not cause any damage to the historic building irrespective of the source of vibration and air overpressure.

2. In BCW mines, values of ground vibration and air overpressure are reduced to less than 2.0 m/s and 110 dB (L) at distance of 500 m and 800 m respectively whereas the minimum distance of the Fort from the mine boundary is about 4.5 km.

3. In Bhairon Singhji ka Khera (BSK) and Manpura quarries, values of vibration and air overpressure were less than the recommended values of 2.0 mm/s and 134 dB (L) respectively at 200 m distance from the blasting source.

4. It can therefore be concluded that the vibration and air overpressure induced by blasting in mines of Birla Cement Works, Chittorgarh, Bhairon Singhji ka Khera and Manpura Quarries may be concluded to absolutely safe as per various National and International Standards.

5. Blast design parameters as discussed in “Section 10.0 Recommended Blasting Practices” of this report shall be used for routine blasting practices in each mine.

6. It is suggested that continuous supervision of blasting operations, monitoring of blast induced ground vibrations in Jai-Surjana Mine of Birla Cements Works (BCW), Bhairon Singhji Ka Khera and Manpura quarries shall be carried out by the mining personnel themselves and recorded data of vibration should be checked and ratified by an expert agency at least once in a year.”

17. We have heard the Learned Counsel appearing for the parties and

have perused the Report dated 30.09.2014 filed by CSIR-CBRI, Roorkee.

The Learned Counsel appearing for the State of Rajasthan has placed

before us an abstract of the Report by the Indian Bureau of Mines, Mining

Research Cell, TMP Division on the impact of blast-induced ground

vibration on the Chittorgarh Fort, due to working of limestone, china clay

and red ochre mines in the radius of ten kilometres of Chittorgarh Fort.

10

18. The report filed on behalf of the State of Rajasthan records

independent conclusions for Jai-Surjana and Block-B (Bherda), Manpura

stone quarries and Bheiron Singh Ji Ka Khera which read thus:-

“Jai-Surjana and Block-B (Bherda)- The minimum distance from the lease hold area to Chittorgarh fort is 4 kms and therefore, it is concluded that there is no impact on Chittorgarh fort due to induced ground vibration using 160-300 kg/delay with present existing practice. However, the maximum charge 500 kg per delay will also dissipate at a distance of 2191 m and will have no significant impact on Chittorgarh fort. Thus, it is evident that the maximum charge per delay should be restricted to 500 kg during rainy season and not increase beyond this limit in any circumstances for safe protection of Chittorgarh fort due to mine blasting. Thus, it is concluded from the regression analysis and the field observations considering the importance of the Historical /Archaeological monuments - Chittorgarh Fort maximum charge of explosive /delay as per existing practice may be restricted upto 300 kg in dry season and 500 Kg in rainy season for safe protection of Chittorgarh fort. There is no adverse effect on Chittorgarh Fort and other monuments situated on the hill due to present existing blasting practices/mining operations in the mines of Birla Cement (Block-C Jai-Surjana) limestone mines.

Manpura stone quarries- It is concluded from the regression analysis and the field observations, that there is no adverse impact on Chittorgarh fort due to blasting using the maximum charge per delay 0.125 kg as per existing practice. The low frequency range data less than 25 Hz not recorded during the monitoring and therefore explosive charge/delay as per existing practice may be continued upto 0.125 kg for the safety of Chittorgarh Fort.

Bheiron Singh Ji Ka Khera- It can be concluded from the regression analysis and the field observations, that there is no adverse impact on Chittorgarh fort due to blasting using the maximum charge per delay 0.125-0.25 kg as per existing practice. The low frequency range data less than 25 Hz not recorded during the monitoring and therefore explosive charge/delay as per existing practice may be continued upto 0.125 - 0.250 kg for the safety of Chittorgarh Fort.

Segwa Area- China clay/Red ochre mines (15 nos.) falling within 10 km distance of Chittorgarh are situated at Segwa Area and are not covered in this study as they have not approached to IBM for study.”

11

19. Dr. Abhishek Manu Singhvi, Learned Senior Counsel appearing for

the Petitioner/Birla Corporation Limited invited our attention to the

chronology of dates and events concerning the Petitioner, which operates

a mining lease of 598.98 hectares at a distance of about 4.5 kilometres

from the Chittorgarh Fort. The mining operations undertaken by the

Petitioner from any viewpoint to wit scientific, technical and legal principles

are safe and do not cause a debilitating effect on the structures in the

Chittorgarh Fort. Therefore, the directives issued by the High Court in the

impugned judgement are unreasonable directions, based on mere

apprehensions, conjectures and contrary to the record before the High

Court. The State government, after appreciating the distance at which the

limestone mines of the Petitioner are located and being satisfied with the

safety, granted mining leases to the Petitioner. The manual prospecting or

mining of limestone is onerous, economically disadvantageous, and

without there being direct or indirect injury from the activities of the

Petitioner, the impugned judgement imposed a ban on safe and technical

ways of mineral extraction from the mines situated at Jai-Surjana and

Block-B (Bherda). Therefore, he prays for setting aside the judgement.

19.1 Dr. Singhvi contends by relying on the report dated 30.09.2014 of

CSIR-CBRI, that the study of impact from blasting at the Petitioner’s mine,

has not travelled beyond a maximum distance of 1 ½ kilometres, and the

12 blasts carried out at subject mines did not record any vibrations/ peak

particle velocity (PPV) at the Fort. Therefore, he contends that the

impugned judgment is liable to be set aside, and the Petitioner is allowed

to operate the mines in accordance with the grant conditions.

19.2 The Senior Counsel alternatively placed on record the view of the

Petitioner/ Birla Corporation Limited on preserving the existing grandeur

of the Chittorgarh Fort for posterity. As a responsible corporate entity, the

Petitioner is prepared to establish its bonafides in any further study

intended to correlate between the alleged debilitating effect on structures

and the causes for such findings on the monuments in the Chittorgarh Fort.

He argues that the Petitioner proposes to adopt electronic blasting

systems, which have far lesser impacts of vibrations than the blasting

verified in the previous study. According to the Petitioner, electronic

blasting systems for fragmentation improvement are the latest technology.

This technology is used worldwide as a safe and scientifically proven

blasting method employed in mineral ore extraction by the lessees. The

Learned Counsel suggests that this Court can direct a fresh study on the

impact of blasting of the mines on the structures in the Chittorgarh Fort;

measures for ensuring the safety and structural soundness of the Fort,

and the Court monitors the working of mines before a final verdict on the

minimum distance to be maintained for blasting operations is rendered.

13 However, it is argued that if the ipse dixit allegations resulting in the

impugned directions are allowed to operate, the stakeholders would suffer

irreparable injuries.

20. The Learned Senior Counsel, Dr. Manish Singhvi, appearing for the

State, placing reliance on the Report of the Ministry of Coal and Mines,

Indian Bureau of Mines, Mining Research Cell, argues that though the

Report stipulates the operation beyond 1½ kilometres as a safe radius,

still he advises strict care and caution, and prefers to err on the side of

caution than cure in stipulating the prohibited radius. He contends that the

blasting should be restricted within a radius of five kilometres. We

appreciate the contention and, even a study of the impact from blasting

operations is directed by us. The study shall be undertaken beyond a five-

kilometre radius from the Chittorgarh Fort. During the proposed study, the

Expert Committee ensures that the maximum permissible explosives

recommended in the Report of the Indian Bureau of Mines, Mining

Research Cell is taken note of and acted accordingly. The study on the

impact from electronic blasting systems with the latest technology is

undertaken. He prays that until a framework on the working of mines in

the neighbourhood of the Chittorgarh Fort is finalised, this Court continues

to monitor the mining activities, particularly those carried out by blasting

to protect the monuments located in the Fort.

14

21. Mr. Jayant Kumar Mehta, Learned Senior Counsel appearing for

Respondent Nos. 1 to 6 contends that the impugned judgement has not

prohibited mining within the radius of ten kilometres but has restricted the

operation of the mining lease to manual mining alone. The Report

submitted by CSIR-CBRI, Roorkee, cannot be treated as a report of the

experts in the field of explosives/mine blasting operations. Firstly, it is

argued that the directions in the impugned judgement are tenable and,

secondly, essential in the circumstances established in the instant case.

21.1 Advocate Ajay Kumar Singh stated that any study of the impact

from blasting on the monument is by the experts in mining engineering,

civil engineering and geologists. According to the Counsel, the scope of

study must include baseline data collection, advanced remote sensing

techniques, advanced survey techniques, seismic monitoring and

vibration analysis, geological and geotechnical investigations and

structural analysis to implement the precautionary principle applied as a

stepping aid to sustainable development.

22. The Chittorgarh Fort was constructed in the Mauryan period, and

from time to time, the rulers of the kingdom rebuilt, expanded and

continued the legacy inherited. The Report of CSIR-CBRI, Roorkee, deals

with the impact on the Chittorgarh Fort from the explosives used in mining

and the peak particle velocity (PPV) on the structures existing in and

15 around the Fort. The Report also deals with the ancillary causes for the

present state of affairs, i.e., footfall of tourists, the presence of monkeys

and haphazard maintenance by the ASI and local authorities. We are of

the view that the approach to preserving the monument must be multi-

dimensional. With the passage of every year, the need to preserve

monuments increases. The prohibition and regulation of blasting would

address only one front of the problems identified in the Report. Therefore,

this Court is of the firm view that the Chittorgarh Fort, a heritage

monument, must be maintained and preserved under all the

circumstances. The common thread running through the argument of all

the Counsel in the steps needed to preserve the Fort are implemented

and if need be, this Court issues continuous mandamus from time to time

to the authorities.

23. We take note of the assertions of the Petitioner and the opposition

voiced by Respondent Nos. 1 to 6 and other impleaded respondents. At

this juncture, we place on record our appreciation for the work undertaken

by CSIR-CBRI, Roorkee in filing the Report dated 30.09.2014. However,

we are also of the view that the safe minimum distance for blasting

operations from the Chittorgarh Fort suggested in the Report of the CSIR-

CBRI, Roorkee in all material particulars is not in line with the Report of

the Ministry of Coal and Mines, Indian Bureau of Mines, Mining Research

16 Cell. At the same time, despite reports suggesting that blasting operations

can be undertaken beyond the safe distance as suggested by the experts

would ought not to be given effect unless examined in a detailed study

undertaken by exploring the latest techniques and technologies. The

scientific/technological advancements can only be ignored if their efficacy

as wanting is established in a study undertaken by a committee

constituted by this Court. This Court at this stage of consideration ought

not to accept the electronic blasting system technique suggested by the

Petitioner can be a safe solution to allow mining operations by blasting

without a prohibitory radius. By choice, we prefer a third-party institution

and experts in this branch of engineering/science to undertake the study

independently and file a report before this Court on the aspects discussed

above.

24. In the preceding paragraphs, we have noticed other contributory

circumstances viz. negligence causing deterioration to the structures in

Chittorgarh Fort. Monkey menace, human/tourist footfall, unwanted

vegetation growth, and the defacing of statues are a few factors recorded

in the report dated 30.09.2014 that are contributing to the deterioration of

the Fort. The extent of damage to the monument is a serious question.

So, the prevention of damage from any such collateral activities must be

simultaneously addressed by the State Government of Rajasthan and the

17 ASI. Therefore, through this order, a three-pronged study and action plan

are implemented. Hence, the following directions:-

24.1 The recommendations in the Report dated

30.09.2014 which are directed against ASI and the State of

Rajasthan are implemented within two months from the

receipt of this Order. For the said purpose, we direct the

Union of India, through the Director General, ASI, to file a

compliance report on the deficiencies noted in the

monument’s maintenance, steps initiated and progress

made by the next date of hearing.

24.2 Respondent No. 8 is directed to ensure strict

implementation of the Solid Waste Management Rules,

2016 and to take all steps necessary to control the monkey

menace and the sources of unauthorised littering in the

entire Fort and the neighbourhood. Respondents Nos. 8 and

12 are directed to issue orders within four weeks from today

to the local self-government for the said purpose and the

implementation of the directives, is monitored by the

regional office of Rajasthan State Pollution Control Board

(RSPCB). All the steps needed to implement Solid Waste

Management Rules, 2016, are completed within four weeks

18 from today. A report on periodic monitoring and the progress

made is filed by Respondent No. 12 for and on behalf of

Respondent No. 8. The above takes us to the crux of the

controversy in the SLPs.

24.3 We declare and hold that notwithstanding any

liberal recommendation on undertaking blasting operations

nearer to the Chittorgarh Fort, keeping in perspective the

continuous exposure of ancient monuments to peak particle

velocity (PPV) arising from blasting, a radius of five

kilometres from the compound wall of the Fort shall not be

subjected to mining by blasting or use of explosives for

mining of any minerals. In other words, the

manual/mechanical mining operations permitted within a

radius of five kilometres are allowed to be continued, subject

to the lessees possessing a valid lease in accordance with

law.

24.4 To undertake the study of environmental pollution

and impact on all the structures in the Chittorgarh Fort from

the blasting operations beyond a five-kilometre radius, the

Chairman, Indian Institute of Technology (Indian School of

Mines), Dhanbad, Jharkhand [IIT (ISM)- Dhanbad]

19 constitutes a team of multi-disciplinary experts in civil

engineering, earthquake engineering, structural geology

and mining engineering, within two weeks from the receipt

of a copy of this order and communicates it to the chief

engineer of the RSPCB and the Petitioner herein. The chief

engineer of the RSPCB shall be the member secretary of the

Expert Committee.

24.5 We reiterate the terms of reference already

formulated for the study as well, now ordered by this Order,

the terms read thus:-

i. Whether blasting including the cumulative effect of blasting beyond a specified distance has any impact whatsoever upon the structure of the Fort?

ii. What appeared to be the causes that have led to cracks and other damage caused to the Fort, other than ageing simplicitor? iii. Whether the uncontrolled access to tourist has any adverse impact upon the structure and if so, any suggested steps to regulate this activity.

iv. Whether the activities within the colony situated in the Fort as well as the flow of traffic including heavy traffic in the vicinity of the Fort have any adverse consequences upon the structural integrity of the Fort, and if so the suggested measures to deal with the problems.

v. General recommendations on the steps to be taken to restore the structural integrity to repair the cracks and generally ensure that no damage in future is caused to the structural integrity. vi. A comprehensive Environmental Impact Assessment (EIA) covering all kind of pollution-air, ground water, noise etc. by the complete cycle of mining activities including its transportation.

24.6 With the passage of time, technological

innovations have taken place and are kept in perspective by

20 the Committee for carrying out the proposed study. The

Committee, in addition to the terms of reference, keeps in

perspective, the framework of baseline data collection,

advanced remote sensing techniques, advanced survey

techniques, seismic monitoring and vibration analysis,

geological and geotechnical investigations and structural

analysis, as may be applicable to the study. The study shall

be carried out for four months from the date of

commencement and the blasting activities are allowed to be

undertaken during the study period.

24.7 Respondent No. 8 is directed to prepare the list of

the leaseholders beyond five kilometres and within a ten-

kilometre radius and furnish the details of lessees who

desire to operate by blasting to the Committee.

24.8 The statement of the Petitioner is accepted that in

the proposed study, the Petitioner uses an electronic

blasting system, and the explosives used for delay shall not

exceed the quantity suggested in the Report of Ministry of

Coal and Mines, Indian Bureau of Mines, Mining Research

Cell.

21 24.9 Similarly, any other lessee proposing to

undertake mine blasting shall furnish complete data of the

mining operations to Respondent Nos. 8 and 12, who would,

in turn, pass on the information to the Committee constituted

to study the impact of blasting operations from those sites

as well.

24.10 Respondent No. 8 ensures that no other lessee

undertakes mine blasting operations except the lessees

notified to the Committee.

24.11 The hillock and Nimbahera limestone, a

geological formation, have existed for ages. The structures

on the hillock do not wither away willy-nilly on mineral

extraction.

24.12 Respondent Nos. 8 and 12 are authorised to

direct stopping of blasting operations if the study at any

place results in unexpected damage to the structures in the

Fort without waiting for the orders of this Court.

24.13 The Petitioner/Birla Corporation Limited defray all

the expenses for carrying out the above study by the

committee constituted in terms of this Order.

22 24.14 In the event of any exigency or urgency, the

parties are given liberty to move the Court for directions.

24.15 The Committee files its Report on or before July

5th 2024.

25. Post on July 9th, 2024.

.…..………...................J. [SANJIV KHANNA]

.…....……….................J. [S.V.N. BHATTI]

NEW DELHI;

JANUARY 12, 2024.

23

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free