Miss Lucy
← All judgments

Binabai Bhate vs State Of M.P.& Ors

Supreme Court4 July 2011Mukundakam Sharma · Anil R. Dave

Ratio decidendi

The rule this decision rests on

Under Sections 17A, 18 and 19 of the Madhya Pradesh Nagar Tatha Gram Nivesh Adhiniyam, 1973, the recommendations of a committee constituted to consider objections to a draft development plan are purely recommendatory and advisory in nature; the State Government retains absolute and final authority to approve or reject the draft development plan, or to approve it with modifications it deems appropriate, and is not bound by the committee's recommendations. Where the State Government approves a draft development plan without any modification under Section 19, no further hearing is required to be given to parties whose land may be affected, and there is no violation of the principles of natural justice in the absence of such hearing. A power of review against an order is a creature of statute; where no power of review is explicitly provided for in the Act, no court has the power to conduct a review of orders made under that Act, and the High Court was justified in holding that no review was maintainable.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 4920 OF 2011

[Arising out of SLP (C) No. 28905 of 2008]

Binabai Bhate .... Appellant

Versus

State of Madhya Pradesh and Ors. ...Respondents

JUDGMENT

Dr. MUKUNDAKAM SHARMA, J.

1. Leave granted.

2. This appeal is directed against the judgment and order dated

29.08.2008 passed by the High Court of Madhya Pradesh at Jabalpur, in

Writ Appeal No. 1063 of 2003, whereby the High Court dismissed the said

Page 1 of 12

appeal filed by the appellant herein and upheld the order dated 16.04.2003

passed by the Single Bench of the High Court of Madhya Pradesh at

Jabalpur.

3. The appellant is Bhuswami of certain lands situated at Tehsil

Khandwa, District East Nimar, Madhya Pradesh. A draft development plan

was published under the Madhya Pradesh Nagar Tatha Gram Nivesh

Adhiniyam, 1973 (hereafter referred to as "The Act"). The apellant came to

know that the draft development plan included some portion of her land

with the intention of making it available for Navchandi Mela. However, the

land was ancestral and he appellant intended to transfer it by a will duly

registered and already executed.

4. The Appellant submitted objections on 24.03.2000 and a committee

was constituted consisting of Member of Parliament, Member of Legislative

Assembly, Mayor, President Zila Panchayat, Sarpanch Gram Panchayat and

Collector. The committee considered the objections and decided that the

land was not required and the objections of the appellant and others were

accepted stating that the land in question was not required. Accordingly, a

Page 2 of 12

resolution dated 26.05.2000 was passed by the committee in favour of the

Appellant.

5. In spite of the resolution passed by the committee, by a notification

dated 28.02.2001 published in Madhya Pradesh Raj Patra, the Appellant

came to know that the State Government had included certain lands

belonging to the appellant in the modified development plan. The Appellant

filed review Petition under section 23(A) of the Act before the State

Government which was rejected by order dated 24.07.2002 stating that

there is no provision for review of the order in the Act.

6. The Appellant thereafter, filed Writ Petition in the High Court which

was dismissed by the Learned Single Judge by order dated 16.04.2003.

Since the Letter Patent jurisdiction was abolished, the appellant filed Special

Leave Petition in the Supreme Court. During the pendency of the Special

Leave Petition the provision of Letter Patent jurisdiction was revived. The

Special Leave Petition was allowed to be withdrawn for filing Letters Patent

Appeal in the High Court.

Page 3 of 12 7. The Appellant filed Writ Appeal before the High Court of Judicature,

Jabalpur which was dismissed by order dated 29.08.08. The present appeal,

as stated hereinbefore, is directed against the aforesaid order passed by the

High Court.

8. The learned counsel appearing for the appellant submitted that after

passing of the Resolution by the Committee constituted accepting the

objections/suggestions of the appellant, the said resolution of the

Committee should have been accepted by the Government as the same

was binding, but instead the State Government without providing any

opportunity of hearing to the appellant rejected the said recommendation

of the committee and proceeded to acquire the land without giving any

opportunity of hearing and thus the said action of the State Government

is in violation of the principles of natural justice.

9. It was also submitted that the entire acquisition process was in

colourable exercise of power and not for any public purpose and that it

was done for extraneous consideration. It was also submitted by the

learned counsel appearing for the appellant that the appellant had all

Page 4 of 12

along been assured that the land belonging to her will not be used for or

utilised by the State Government for the purpose of holding a Mela and

therefore, the acquisition of the said land came as a complete surprise to

the appellant.

10. It was also submitted that as per the report of the Committee

constituted of Member of Parliament, Members of Legislative Assembly,

Mayor, President of Zila Panchayat, Sarpanch Gram Panchayat and

Collector, the land, in question was not required and the objections of the

appellant having been accepted there was no requirement of the land in

question and therefore the action taken is a colourable exercise of power.

It was also submitted that the High Court committed a serious error in

interpreting the provisions of Section 23 of the Act and in holding that

there was no provision given under the Act for review of orders.

11. On the other hand, the learned counsel appearing for the respondent

submitted that the resolution passed by the aforesaid committee was not

final and was only of recommendatory nature and that it was open for the

State Government to take its own decision considering the facts of each

Page 5 of 12

case. It was also submitted that there was no violation of the principles of

natural justice and that the appellant was provided sufficient opportunity

of hearing.

12. It was also stated that the appellant would be paid compensation as

and when the land is acquired by the Municipal Corporation of Khandwa,

and therefore, at the present moment, the possession of the land is with

the appellant. It was also submitted that the decision is bona fide and

was taken in accordance with law.

13. Before the High Court also similar submissions were made by the

appellant. In its order dated 16.4.2003 the High Court rejected the said

submissions holding that they are without any merit. The High Court

held that as per the scheme of Sections 17 and 18 of the Act, the

recommendation of the Committee is not final, binding and conclusive

and therefore it was open for the State to take its own final decision in

accordance with law. It was also held by the High Court that a review of

the order of the nature which was filed by the appellant before the High

Court was not maintainable in terms of the provisions of Section 23A of

the Act.

Page 6 of 12 14. In the order passed in the writ appeal dated 29.08.2008, the High

Court while upholding its order dated 16.04.2003 observed that the State

Government did not accept the recommendations made by the Committee,

therefore it was not necessary for the State to issue a modified plan. For the

final plan, the State Government did issue the plan, as per section 19(2) and

had invited objections form the persons who are likely to be affected by

inclusion of their land. The Court also observed that if the appellant was of

the opinion that certain documents had been kept back by the State

Government, then he could have always asked the learned Single Judge to

issue directions to the State Government for the production of said

documents. For failure to call for such documents, it cannot be held that the

State Government accepted the recommendations made by the Committee,

did not include the land in the final plan and all of a sudden issued the final

plan against the interest of the appellant.

15. In the light of the submissions made by the counsel appearing

parties, we have minutely perused the records as also the orders passed

by the High Court. On a careful reading of the provisions of Section 17A,

Section 18 and Section 19 of the Act, we become aware regarding the

Page 7 of 12

procedure and the scheme provided for publication of a draft development

plan and also for approval and preparation of the final development plan.

16. Sub-section (2) of Section 17A of the Act makes it crystal clear that

the Committee has the power to consider the draft development plan

prepared by the Director under Section 14. It also has the power to

suggest modifications and alterations in the aforesaid draft development

plan prepared. The Committee has also been empowered to hear

objections after publication of the draft development plan under Section

18 and suggest modifications or alterations, if any, to the Director. It is,

therefore, clearly established that the aforesaid decision and resolution of

the Committee is only suggestion and recommendation which is required

to be taken notice of by the State Government. Once, the development

plan is submitted on completion of the procedure and process prescribed

under Sections 17 and 18 of the Act, the State Government is empowered

under Section 19 of the Act either to approve the development plan or to

approve the same with some modifications as it may consider necessary.

A further power is also vested on the State Government to return the

same to the Director to modify the same or to prepare a fresh plan in

Page 8 of 12

accordance with such directions as the State Government may deem

appropriate.

17. In the present case, the development plan as prepared under Section

14 was approved by the State Government without any modification and

therefore there was no question of inviting any further suggestions as no

modification was suggested to the said development plan. In view of the

said position also, there was no question of giving any hearing to the

appellant in the present case, and therefore the issue raised with regard

to alleged violation of the principles of natural justice is without any

merit.

18. The aforesaid provisions namely Section 17, 18 and 19 of the Act

give a broad scheme laying down the procedure as to how a development

plan is to be approved by the State Government as also the procedure as

to when it becomes final and operational. The aforesaid scheme of the

provisions clearly states that a recommendation of the Committee is only

recommendatory and advisory in nature and such recommendations of

the Committee are required to be considered by the State Government,

but the absolute and final power is rested on the State Government to

Page 9 of 12

approve or reject the draft development plan or to approve the same with

some modifications as it may deem appropriate.

19. The resolutions passed by the Committee cannot be said to be

absolute, final and binding and the State Government possesses the final

authority in the matter of giving approval to the development plan. In

any case, in the present case, the State Government approved the draft

plan without any modification and therefore provisions of sub-sections (2)

and (3) of Section 19 are not applicable to the facts and circumstances of

the present case. Despite the said legal provision, the State Government

in the present case has issued a final plan and also invited objections

from the persons who are likely to be affected by inclusion of their land.

Even thereafter the appellant did not submit any objection and therefore

the question of giving a hearing to the appellant at that stage did not

arise. So from whatever angle the contentions of the appellant are

examined, the same are not found to be worthy of acceptance.

20. So far the power of review is concerned, the High Court does not

have the power of review as such power of review has to be specifically

provided for in the Act. A power of review against an order passed is a

Page 10 of 12

creature of the statute and since no such power of review is provided for

under the provisions of the Act, the High Court was justified in holding

that there could be no review to the order passed. So far the review and

modifications of the development plan or adjoining plan as provided in

Section 23 and 23A of the Act are concerned, the said provisions are not

applicable in the present case for the State Government has not made any

modification in the development plan, and therefore, the contentions

appearing for the appellant are held to be without any merit. Besides, the

said power is exclusively vested with the State Government and in an

appropriate case, the State Government is empowered to exercise such

power as and when deem proper. This is not a case where the State

Government thought it fit to invoke such power.

21. We, therefore, find no error in the judgment passed by the High

Court. The impugned order does not suffer from any infirmity. The

present appeal is, therefore, dismissed as without any merit. However,

there shall be no order as to costs.

............................................J

Page 11 of 12

[ Dr. Mukundakam Sharma ]

............................................J

[ Anil R. Dave ]

New Delhi,

July 4, 2011.

Page 12 of 12

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free