Bihar State Electricity Board & Ors vs M/S. Allied Refractories (Pvt.) Ltd

Supreme Court25 January 1996K. Ramaswamy

Ratio decidendi

The rule this decision rests on

A consumer entitled under an agreement to a minimum guaranteed charge for electricity supply is entitled to apply for proportionate reduction of that charge when the supply falls below the guaranteed level due to the Board's failure to supply (through trippings, load sheddings, or power cuts), but such relief must be sought by application to the Board under the contractual machinery before resort to court, and the High Court was not justified in granting the relief by writ petition without the consumer first exhausting this contractual remedy.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

PETITIONER:BIHAR STATE ELECTRICITY BOARD & ORS.
Vs.
RESPONDENT:M/S. ALLIED REFRACTORIES (PVT.) LTD.
DATE OF JUDGMENT: 25/01/1996
BENCH:RAMASWAMY, K.BENCH:RAMASWAMY, K.G.B. PATTANAIK (J)
CITATION:JT 1996 (2) 381 1996 SCALE (2)125
ACT:
HEADNOTE:
JUDGMENT:
O R D E RLeave granted.

Though the respondents have been served twice and respondents 1, 2 and 6 were again served on September 22, 1995, they are not appearing either in person or through counsel. Acknowledgments from respondents 3, 4 and 5 for the second occasion have not been received. We, therefore, declare that they are deemed to have been served. The only question is: whether the respondents are entitled to the proportionate reduction of the minimum guaranteed amount for non-supply of the electricity due to disruption by trippings load sheddings and power cuts etc.? Clause [13] of the contract entered into, provides that they are entitled to make an application in such a situation and the Board would consider and pass appropriate orders in that behalf. Admittedly, the respondents had not made such an application, but straightway approached the High Court for the relief. The High Court in the impugned order dated August, 16, 1988 in C.W.J.C. No. 1480 of 1988 directed the appellant to grant them proportionate reduction. The controversy is no longer res integra. This Court in Bihar State Electricity Board & Anr. vs. M/s. Dhanawat Rice & Oil Mills, [(1989) 1 SCC 452] arising from the appellant-Board itself had held that under Section 49, an agreement had been entered into by the consumer with the appellant to pay minimum guarantee of charges to the Board. On failure to consume the minimum guaranteed level of electricity due to non-supply of electricity by trippings, load sheddings or power cuts, the consumer would be entitled to make an application for proportionate reduction of the minimum guarantee. Since respondents had not made such an application, the High Court was not justified in straightaway allowing the writ petitions and directing the grant of the proportionate reduction. The order is set aside. This order does not preclude the respondents to make application accordingly under Section 49 of the Electricity Supply Act and it would be open to the appellant-Board to consider and pass appropriate orders within a reasonable time form the date of making the application.

The appeal is accordingly allowed, but, in the circumstances, without costs.

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free