Bharat Sanchar Nigam Ltd. & Anr vs Dhanurdhar Champatiray

Supreme Court11 December 2009Aftab Alam · Tarun Chatterjee

Ratio decidendi

The rule this decision rests on

Under Section 11(6) of the Arbitration and Conciliation Act 1996, when appointing an arbitrator to fill a vacancy caused by a party's failure to act in accordance with an agreed appointment procedure, the court must have due regard to the qualifications required by the agreement and other considerations necessary to secure an independent and impartial arbitrator, as specified in Section 11(8) of the Act. An appointment made without considering and applying these requirements is vulnerable and liable to be set aside.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

REPORTABLEIN THE SUPREME COURT OF INDIACIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOs.8230 OF 2009(Arising out of SLP) No.8218 of 2007)
Bharat Sanchar Nigam Ltd. & Anr. ...AppellantsVERSUSShri Dhanurdhar Champatiray ...RespondentWITHC.A. No.8231/2009 @ SLP(C)No.8222/2007C.A. No.8232/2009 @ SLP(C)No.8224/2007C.A. No.8233/2009 @ SLP(C)No.8226/2007C.A. No.8234/2009 @ SLP(C)No.8234/2007
J U D G M E N T
TARUN CHATTERJEE, J.
1. Leave granted.
2. These appeals by special leave have been filed
against the orders dated 5th of January 2005 in
A.R.B.P. Nos. 11, 12, 17, 18 and 28 of 2005 passed
by the High Court of Orissa whereby the High Court

had appointed Sh. Bibhudhendra Mishra, a Senior

Advocate of the Orissa High Court as the sole

arbitrator on the application of the respondent

filed under Section 11 (6) of the Arbitration and

Conciliation Act 2006 (hereinafter referred to as

1 "the Act"). Since the parties and the subject

matter of the dispute are the same, we have clubbed

all these appeals and the same are being decided

analogously by this common judgment to avoid any

confusion.

3. The relevant facts leading to the filing of

these appeals as emerging from the records may be

briefly stated as follows :

The parties herein entered into a contract

pursuant to distinct notices inviting tender by

BSNL [in short `the appellant'] for the work of

construction of 4 Nos. of Type-II, 2 Nos. Type-III

and 1 No. of Type-IV Staff Quarters at Bhanjanagar

of vertical extension to combined building at Aska

of 3 Nos. of Type III, 3 Nos. of Type II and 4 K

type T.E. building at Jankia and of vertical

extension to 8 Nos. of Type II and 6 Nos. of Type

IV staff quarters at CTTC compound Vanivihar,

Bhubaneshwar.

2 4. The said contract contained an arbitration

clause in terms whereof the Chief Engineer,

Telecommunication/ Postal Department in charge of

the work at the time of dispute, or if there be no

Chief Engineer, the Administrative Head of the said

Telecommunication/ Postal Department was to be

appointed as a sole arbitrator. The said provision

envisaged that in terms thereof no person other

than the one appointed by such Chief Engineer or

Administrative Head of the Telecommunication/

Postal as aforesaid should act as arbitrator to

decide the disputes referred to him.

5. The Respondent by letters, requested the Chief

Engineer (Civil) for appointment of an arbitrator

to adjudicate the disputes between the parties in

terms of clause 25 of the respective agreements.

According to the respondent, letters were received

by the Chief Engineer of the appellant no.1 on

different dates. The Appellants having failed to

respond to the letters of respondent requiring them

3 to appoint an arbitrator and to appoint an

arbitrator in response to such letters within the

stipulated period in accordance with Clause 25 of

the respective Agreements, the respondent was

constrained to file petitions under Section 11(6)

of the Act for appointment of an Arbitrator.

However, according to the case made out by the

appellants, on 9th of March, 2005, Chief Engineer

(Civil), BSNL had already appointed Sri. Gurbaux

Singh, Principal Chief Engineer (Arbitration) BSNL

vide its office letter No. 69-

41(05)/CE(c)/BBSR/205. By the impugned order, the

High Court allowed application under S. 11(6) of

the Act, and appointed one Sri. Bibhudhendra Mishra

in place of departmental nominee Sri. Gurbaux Singh

who was appointed by Chief Engineer (Civil) BSNL of

appellant No.1.

6. Feeling aggrieved by the said order of the High

Court, the appellant has filed these special leave

4 petitions which on grant of leave, were heard in

the presence of learned counsel for the parties.

7. Before we consider the arguments raised by the

learned counsel for the parties before us, it would

be necessary to refer to Section 11 of the Act,

which reads as under:

"Section 11. Appointment of arbitrators. (1) A person of any nationality may be an arbitrator, unless otherwise agreed by the parties.

(2) Subject to sub-section (6), the parties are free to agree on a procedure for appointing the arbitrator or arbitrators. (3) & (4)..............omitted because these are not necessary for our purpose (5) Failing any agreement referred to in sub- section (2), in an arbitration with a sole arbitrator, if the parties fail to agree on the arbitrator within thirty days from receipt of a request by one party from the other party to so agree the appointment shall be made, upon request of a party, by the Chief Justice or any person or institution designated by him.

(6) Where, under an appointment procedure agreed upon by the parties,- (a) a party fails to act as required under that procedure; or (b) the parties, or the two appointed arbitrators, fail to reach an agreement expected of them under that procedure; or (c) a person, including an institution, fails to perform any function

5 entrusted to him or it under that procedure, a party may request the Chief Justice or any person or institution designated by him to take the necessary measure, unless the agreement on the appointment procedure provides other means for securing the appointment.

(7) A decision on a matter entrusted by sub-

section (4) or sub-section (5) or sub- section (6) to the Chief Justice or the person or institution designated by him is final.

(8) The Chief Justice or the person or institution designated by him, in appointing an arbitrator, shall have due regard to- (a) any qualifications required of the arbitrator by the agreement of the parties; and (b) other considerations as are likely to secure the appointment of an independent and impartial arbitrator..."

8. A plain reading of Section 11 [5] of the Act

would show that if one party demands appointment of

an arbitrator and the other party does not appoint

any Arbitrator within thirty days of such demand,

the right to appointment at the instance of one of

the parties does not get automatically forfeited.

If the appellant makes an appointment even after

thirty days of demand but the first party has not

6 moved the Court under Section 11, that action on

the part of the appellant would be sufficient. In

other words, in cases arising under Section 11 [6],

if the respondent has not made an appointment

within thirty days of demand, right to make an

appointment of an arbitrator is not forfeited but

continues, but such appointment shall be made

before the other party files the application under

Section 11 seeking appointment of an arbitrator

before the High Court. It is only then the right

of the respondent ceases. In this connection, a

three-Judge Bench decision of this Court in Punj

Lloyd Ltd. v. Petronet MHB Ltd., (2006) 2 SCC 638,

may be referred to. In this case, this Court

considered the applicability of Section 11 [6] of

the Act and after considering the scope and object

of the Act held that once notice period of thirty

days has expired and the party has moved the Hon.

Chief Justice of the High Court under Section 11

[6] of the Act, the other party loses his right to

7 appoint an arbitrator on the basis of arbitral

agreement. While taking this view, this Court in

the Punj Lloyd's case [supra] had relied on the

judgment referred in Datar Switchgears Ltd. v. Tata

Finance Ltd. and Another, (2000) 8 SCC 151, wherein

in paragraph 19 at page 158 this Court observed as

follows:

"So far as cases falling under Section 11(6) are concerned such as the one before us no time limit has been prescribed under the Act, whereas a period of 30 days has been prescribed under Section 11(4) and Section 11(5) of the Act. In our view, therefore, so far as Section 11(6) is concerned, if one party demands the opposite party to appoint an Arbitrator and the opposite party do not make an appointment within 30 days of the demand, the right to appointment does not get automatically forfeited after expiry of 30 days. If the opposite party makes an appointment even after 30 days of the demand, but before the first party has moved the Court under Section 11, which would be sufficient. In other words, in cases arising under Section 11(6), if the opposite party has not made an appointment within 30 days of demand, the right to make appointment is not forfeited but continues, but an appointment has to be made before the former files application under Section 11 seeking appointment of an Arbitrator. Only then the right of the opposite party ceases."

8 9. Similarly in the case of Ace Pipeline Contracts

Private Limited v. Bharat Petroleum Corporation

Limited, (2007) 5 SCC 304, this Court went to

observe that:

"But in sub-section (6), where, the procedure has already been agreed upon by the parties, as in the present case, and in that event, if a party fails to act as required under that procedure or the parties, or the two appointed arbitrators, fail to reach an agreement expected of them under that procedure or a person, including an institution, fails to perform any function entrusted to him or it under that procedure, a party may in that event, request the Chief Justice or a person or an institution designated by him to make necessary measures, unless the agreement on the appointment procedure provides other means for appointment of arbitrator. Therefore, so far as the period of thirty days is concerned, it is not mentioned in Sub-section (6). The period of limitation is only provided under sub-sections (4) & (5) of Section 11. As such, as per the statute, the period of limitation of thirty days cannot be invoked under sub-section (6) of Section 11 of the Act."

10. On a perusal of the above quoted observations

of this Court made in Ace Pipeline Contracts

Private Limited (supra), the reasons advanced in

9 the orders passed by the High Court must be found

to be a correct interpretation of the aforesaid

provision and so far as the period of 30 days with

regard to Section 11(6) is concerned, there is no

doubt at all that thirty days limitation cannot be

invoked as mandatory period under Section 11 [6] of

the Act. But a somewhat different view was

expressed in a latter decision of this Court in the

case of Union of India vs. Bharat Battery

Manufacturing Co. Pvt.Ltd. [2007 (7) SCC 684]. In

view of the difference of opinion of the two

coordinate benches of this Court, the matter was

referred to a three-Judge Bench in the case of

Northern Railway Administration, Ministry of

Railway vs. Patel Engineering Company Ltd. [2008

(10) SCC 240] in which the decision in Ace Pipeline

Contracts Pvt. Ltd. (supra) was also referred to.

Arijit Pasayat, J. (as His Lordship then was),

heading the three-Judge Bench of this Court, after

considering the scope and object of the Act

1 particularly Section 11 of the Act, concluded the

following :

"A bare reading of the scheme of Section 11 shows that the emphasis is on the terms of the agreement being adhered to and/or given effect as closely as possible. In other words, the Court may ask to do what has not been done. The court must first ensure that the remedies provided for are exhausted. It is true as contended by Mr. Desai, that it is not mandatory for the Chief Justice or any person or institution designated by him to appoint the named arbitrator or arbitrators. But at the same time, due regard has to be given to the qualifications required by the agreement and other considerations.

xxxxxxxxxxxxxx

In all these cases at hand the High Court does not appear to have focused on the requirement to have due regard to the qualifications required by the agreement or other considerations necessary to secure the appointment of an independent and impartial arbitrator. It needs no reiteration that appointment of the arbitrator or arbitrators named in the arbitration agreement is not a must, but while making the appointment the twin requirements of Sub-section (8) of Section

11 have to be kept in view, considered and taken into account. If it is not done, the appointment becomes vulnerable. In the circumstances, we set aside the appointment made in each case, remit the matters to the High Court to make fresh

1 appointments keeping in view the parameters indicated above."

11. In the aforesaid decision in the case of

Northern Railway Administration (Supra), Arijit

Pasayat, J. (as His Lordship then was), found that

the High Court in the said case did not appear to

have focused on the requirement to have due regard

to the qualifications required by the agreement or

other conditions necessary to secure the

appointment of an independent and impartial

arbitrator. In the aforesaid decision, this Court

also concluded that since the requirement of sub-

section (8) of Section 11 was not at all dealt with

by the High Court in its order, the appointment of

an arbitrator without dealing with Sub-Section 8 of

Section 11 of the Act became vulnerable and

accordingly, such appointment was set aside.

Similar is the position in this case. In this case

also, before appointing an arbitrator under Section

11(6) of the Act, the High Court had failed to take

1 into consideration the effect of Section 11(8) of

the Act as was done in Northern Railway

Administration (supra).

12. In view of the discussions made hereinabove and

particularly, in view of the principles laid down

by this Court in Northern Railway Administration

(supra), we set aside the impugned order and remand

the case back to the High Court for fresh decision

of the application under Section 11(6) of the Act

and while considering the application afresh, the

High Court is directed to take into consideration

the aforesaid decision of this Court.

13. The appeals are allowed to the extent indicate

above. There will be no order as to costs.

................................................J. [TARUN CHATTERJEE]

NEW DELHI: .................................................J. DECEMBER 11,2009. [AFTAB ALAM]

1

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free