BASIX SUB-K iTransactions Limited

Reserve Bank Of India3 May 2000

Ratio decidendi

The rule this decision rests on

The compounding authority, exercising power under Section 15(1) of the Foreign Exchange Management Act, 1999, may compound admitted contraventions of the Act and its regulations on the basis of the applicant's compounding application, its declarations, and its admissions at personal hearing, by imposing a compounding amount fixed in the exercise of its discretion, where the contravention is the late reporting of foreign inward remittances and late filing of Form FC-GPR under Paragraphs 9(1)(A) and 9(1)(B) of Schedule 1 to Notification No. FEMA 20/2000-RB. Compounding is conditional on the veracity of the applicant's declarations that it is not under any enquiry, investigation or adjudication, and the order is without prejudice to any other action if those declarations are later found false or incorrect. In fixing the compounding amount, the authority takes into account the circumstances of the case, including that the delay was not wilful or mala fide and resulted from staff shortage and lack of guidance, and it treats these as grounds for a lenient view in quantum, though the statutory maximum penalty under Section 13 is up to thrice the sum involved.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

In the RESERVE BANK OF INDIA Foreign Exchange Department Secretariat Road Saifabad, Hyderabad 500 004 Present R Subramanian Regional Director Date: April 03, 2018 C.A. HYD 278 In the matter of M/s. BASIX Sub-K iTransactions Limited 3rd Floor, Surabhi Arcade Troop Bazar Bank Street, Koti Hyderabad – 500 001 (Applicant) In exercise of the powers conferred under Section 15 (1) of Foreign Exchange Management Act, 1999 and the Regulations/ Rules/ Notifications/ Orders made there under, I pass the following Order The applicant has filed the compounding application dated January 22, 2018 received on January 24, 2018 for compounding of contraventions of the provisions of the Foreign Exchange Management Act, 1999 (the FEMA) and the regulations issued thereunder. The contraventions sought to be compounded are (i) delay in reporting receipt of foreign inward remittances and (ii) delay in submission of Form FC-GPR to Reserve Bank of India after issue of shares towards subscription to equity/CCPS in terms of Paragraph 9(1)(A) and Paragraph 9(1)(B) respectively of Schedule 1 to Foreign Exchange Management (Transfer or Issue of Security by a Person Resident Outside India) Regulations, 2000 notified vide Notification No.

Compounding of contraventions under FEMA 1999 M/s BASIX Sub-K iTransactions Limited CA No. HYD 278

FEMA.20/2000-RB dated 3rd May 2000 (hereinafter referred to as Notification No. FEMA 20 /2000-RB) as then applicable.

2. The relevant facts of the case are as follows: a) The applicant is a resident company incorporated as a Limited Company under the Companies Act, 1956 on 02.08.2010 (CIN: U74999TG2010PLC069785). The company is engaged in the business of offering facilitation services in unbanked areas as a Business Correspondent (BC) for various banks. b) M/s Michael and Susan Dell Foundation, a social fund, invested Rs.9 Crores in the company. As per the shareholder’s agreement entered by the applicant with the investor on 15.11.2011, foreign inward remittances were received in four tranches as indicated below:

Sl Name of Particulars Total Amount Date of Date of No Remitter (INR) Receipt Reporting 1 Michael and Tranche 1 39999999.75 21-11-2011 03-01-2012 Susan Dell Foundation 2 Michael and Tranche 2 20000000.00 04-10-2012 29.-01-2013 Susan Dell Foundation 3 Michael and Tranche 3 10000000.00 17-12-2012 19.02.2013 Susan Dell Foundation 4 Michael and Tranche4 20000000.00 15-12-2014 12-01-2015 Susan Dell Foundation Total 8,99,99,999.75

The applicant received the foreign inward remittances amounting to Rs. 8,99,99,999.75/- as indicated above out of which remittances amounting to Rs. 6,99,99,999.75/- were reported to Reserve Bank of India with delays ranging

Compounding of contraventions under FEMA 1999 M/s BASIX Sub-K iTransactions Limited CA No. HYD 278 from 13 days to 2 months 26 days approximately beyond the prescribed period of 30 days. Whereas in terms of Paragraph 9(1)(A) of Schedule 1 to Notification No. FEMA 20/2000-RB, an Indian company issuing shares or convertible debentures in accordance with these Regulations should report to the Reserve Bank of India as per the prescribed procedure not later than 30 days from the date of receipt of the amount of consideration. c) The company allotted shares and filed form FC-GPRs as indicated below:

Sl Name of Date of Number of Amount for Date of No investor allotment of shares/ which shares reporting shares CCPS allotted (INR) 1 21-11-2011 519272 40000000.00 11-01-2012 Michael & CCPS Susan Dell Foundation 100 Equity 2 Michael & 04-10-2012 259615 19999999.70 12.01.2013 Susan Dell CCPS Foundation 3 Michael & 04-02-2013 129807 9999961.33 14.02.2013 Susan Dell CCPS Foundation 4 Michael & 16-12-2014 222222 19999980.00 09-01-2015 Susan Dell Foundation Total 8,99,99,941.03

The applicant filed form FCGPRs for issue of shares amounting to Rs. 8,99,99,941.03/- as indicated above out of which shares amounting to Rs. 5,99,99,999.70/- were reported with delays ranging from 21 days to 2 months 9 days approximately beyond the stipulated period of 30 days. Whereas in terms of Paragraph 9(1)(B) of Schedule 1 to Notification no. FEMA 20/2000-RB, an Indian company issuing shares in accordance with Compounding of contraventions under FEMA 1999 M/s BASIX Sub-K iTransactions Limited CA No. HYD 278 these Regulations has to submit to Reserve Bank of India a report in form FCGPR along with documents prescribed therein within 30 days from the date of issue of shares to person resident outside India.

3. (a) The applicant was given an opportunity for personal hearing vide Reserve Bank’s letter No. HY.FE.FID/1613/14.66.003/2017-18 dated March 15, 2018 for further submission in person and/or producing documents, if any, in support of the application. (b) The applicant appeared for personal hearing on March 21, 2018 during which Shri. Jitender kalwani, Chief Financial Officer and the authorized representative and Shri. T Narendra Babu, Finance Manager represented the applicant. The authorized representative of the applicant admitted the contraventions for which the compounding has been sought. During the personal hearing it was submitted that the delay was not wilful or with a malafide intention but was on account of shortage of staff and lack of proper guidance on compliance requirements. In view of the foregoing, the representative of the applicant requested to take a lenient view in disposal of the application. The application for compounding is, therefore, being considered on the basis of the averments made in the application as well the submissions made in this context by the applicant during the personal hearing.

4. I have given my careful consideration to the documents on record. Accordingly, I hold that the applicant has contravened the following FEMA provisions issued in terms of:- (a) Paragraph 9(1)(A) of Schedule 1 to Notification No. FEMA 20/2000-RB for delay in reporting the receipt of consideration towards issue of shares amounting to Rs.6,99,99,999.75/- and the delay ranges from 13 days to 2 months 26 days approximately. (b) Paragraph 9(1)(B) of Schedule 1 to Notification No. 20/2000-RB for delay in submission of Form FC-GPR to Reserve Bank of India after issue of shares to Compounding of contraventions under FEMA 1999 M/s BASIX Sub-K iTransactions Limited CA No. HYD 278 persons resident outside India and the contravention relates to an amount of Rs. 5,99,99,999.70/- and the delay ranges from 21 days to 2 months 9 days approximately.

5. It has been declared in the compounding application dated January 22, 2018 that the particulars given by the applicant in the application are true and correct to the best of their knowledge and belief. It has been declared in the declaration dated January 22, 2018 furnished with the compounding application that the applicant was not under any enquiry/investigation/adjudication by any agency as on the date of the application and has, in this regard, not informed of initiation of any such enquiry/investigation/adjudication proceedings against it thereafter. Accordingly, the above contraventions which are being compounded in this Order are subject to the veracity of the above declarations made by the applicant and this order is without prejudice to any other action which may be taken by any authority under the extant laws if the said declarations are subsequently discovered to be false and/or incorrect.

6. In terms of Section 13 of the FEMA, any person contravening any provision of the Act shall be liable to a penalty up to thrice the sum involved in such contravention upon adjudication. However, taking into account the relevant facts and circumstances of the case as stated in the foregoing paragraphs, I am persuaded to take a lenient view on the amount for which the contravention is to be compounded and I consider that an amount of Rs.61,500/- (Rupees Sixty One Thousand Five Hundred Only) will meet the ends of justice.

7. Accordingly, I compound the admitted contraventions, namely, the contraventions of Paragraph 9(1)(A) and Paragraph 9(1)(B) of Schedule 1 to Notification No. FEMA- 20/2000-RB by the applicant on the facts discussed above in terms of the Foreign Exchange (Compounding Proceedings) Rules, 2000 on payment of an amount of Compounding of contraventions under FEMA 1999 M/s BASIX Sub-K iTransactions Limited CA No. HYD 278

Rs. 61,500/- (Rupees Sixty One Thousand Five Hundred Only) which shall be deposited by the applicant with the Reserve Bank of India, Foreign Exchange Department, 1st Floor, Saifabad, Hyderabad - 500004 by a demand draft drawn in favour of the "Reserve Bank of India" and payable at Hyderabad within a period of 15 days from the date of this order. In case of failure to deposit the compounded amount within the above mentioned period, Rule10 of the Foreign Exchange (Compounding Proceedings) Rules, 2000 dated May 3, 2000 shall apply.

The application is disposed accordingly.

Dated this 03rd day of April 2018

Sd/- (R Subramanian) Regional Director

Connected matters

Decided by the same order

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free