Anumati Consultancy and Services Private Limited vs Wellside Global Private Limited
- CitationAIRONLINE 2021 CAL 129
Ratio decidendi
The rule this decision rests on
Where a suit involves a money claim arising from a contract for immovable property, and triable issues are raised by both parties as to the terms and performance of the contract, but it can be established at the interim stage that the defendant is liable to pay the plaintiff (even if the quantum remains to be determined), the Court may grant an order of injunction restraining the defendant from creating third party rights over the specific immovable property that was the subject-matter of the contract, pending final determination of the suit. The mere fact that a claim is for money does not preclude the Court from granting an order of injunction under Order 39 of the Code of Civil Procedure, 1908, or from exercising its inherent jurisdiction under Section 151 of the Code to grant such relief where an unimpeachable liquidated claim is demonstrated and it is established that the defendant is taking steps to improperly deny realization of the claim.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
For the Plaintiff : Mr. Ratnanko Banerjee, Sr. Advocate Mr. Jishnu Chowdhury, Advocate Mr. Shaurav Mitra, Advocate Mr. Suryaksh Manot, Advocate
For the Defendant : Mr. Surojit Nath Mitra, Sr. Advocate Mr. Samik Chakraborty, Advocate Mr. Mayank Kakrania, Advocate
Hearing concluded on : February 9, 2021
Judgment on : February 19, 2021
DEBANGSU BASAK, J. :-
1. In a suit where the plaintiff has money claim against the defendant,
the plaintiff has sought interim order of attachment before judgment
and an order of injunction against the defendant by this application. 2
2. Learned Senior Advocate appearing for the plaintiff has submitted
that, the plaintiff is not pressing for an order of attachment before the
judgment at this stage. He has limited the prayers of the application to a
prayer for injunction only.
3. Learned Advocate appearing for the plaintiff has submitted that, the
parties agreed that the defendant will construct and sell three flats to
the plaintiff. By reason of such agreement, the plaintiff had from time to
time paid a sum of Rs. 14,06,70,000/-. The plaintiff had thereafter
found that the defendant was not performing its part of the obligations.
The plaintiff had terminated the agreement and called upon the
defendant to refund the principal amount along with interest thereon.
The defendant had claimed that, it was entitled to deduct an amount on
account of premature termination of the contract by the plaintiff. The
plaintiff had approached the National Company Law Tribunal under the
provisions of the Insolvency and Bankruptcy Code, 2016. In such
proceedings, the defendant had tendered a sum of Rs. 12,81,22,349/-
claiming that such sum was due and payable after adjustment of the
amount that the defendant was entitled to deduct under the
contract. The National Company Law Tribunal (NCLT) had
disposed of such proceeding. The plaintiff being entitled to the 3
entirety of the sum of Rs. 14,06,70,000/- together with interest thereon,
had not accepted the tender of the sum of Rs. 12,81,22,349/- before the
NCLT. The plaintiff has now a claim in excess of Rs. 81 crores as against
the defendant.
4. Learned Senior Advocate appearing for the plaintiff has relied upon
2019 Volume 4 Calcutta High Court Notes 412 (Harleen Jairath v.
Prabha Surana) in support of the contention that, the plaintiff is
entitled to an order of injunction as prayed for.
5. Learned Senior Advocate appearing for the defendant has submitted
that, the petition does not contain any averment with regard to
attachment before judgment. He has relied upon 2008 Volume 2
Supreme Court Cases page 302 (Raman Tech. & Process Engg. Co.
& Anr. v. Solanki Traders) in support of his contention that an order
of attachment before judgment should not be passed in the facts and
circumstances of the case.
6. Referring to the averments made in the application and relying upon
All India Reporter 2009 Calcutta (Sunil Kakrania & Ors. v. M/s.
Saltee Infrastructure Ltd. & Anr.) learned Senior Advocate appearing
for the defendant has submitted that, the plaintiff is neither entitled to 4
an order of attachment nor an order of injunction. He has submitted
that, the flats were agreed to be handed over in May, 2020. Prior to the
expiry of time for handing over the flats, the plaintiff had unilaterally
terminated the contract. Under the Contract, the defendant is entitled to
deduct money from out of the consideration paid by the plaintiff in the
event of premature termination of the contract at the behest of the
plaintiff. He has submitted that, the plaintiff terminated the contract in
April, 2019 much prior to the date of expiry of the time to perform the
contract in May, 2020. According to him, the defendant cannot be said
to be in breach of the contract. The defendant had offered to refund the
price for the flats received from the plaintiff after deducting the amount
stipulated under the contract for premature termination of the contract.
The plaintiff did not accept such offer. Therefore, according to him, the
defendant cannot be faulted.
7. Raman Tech. & Process Engg. Co. & Anr. (supra) has
considered a petition under Order 38 Rule 5 of the Code of Civil
Procedure, 1908. Since the plaintiff has given up the prayer for
attachment before judgment, the ratio laid down in Raman Tech. &
Process Engg. Co. & Anr. (supra) need not be discussed herein. 5
8. Sunil Kakrania & Ors. (supra) has considered applications both
under Order 38 Rule 5 of the Code of Civil Procedure, 1908 as well as
one under Order 39 Rule 1 and 2 thereof, in suit for recovery of money.
In the facts of that case, the Court had found that the plaintiff therein
was not entitled to an order of attachment before judgment. Again on
facts, the Court had found that the plaintiff did not make out any case
for grant of an order of injunction under Order 39 Rule 1(b) of the Code
of Civil Procedure, 1908 in a suit for recovery of money.
9. Harleen Jairath (supra) has considered both Raman Tech. &
Process Engg. Co. & Anr. (supra) as well as Sunil Kakrania & Ors.
(supra). After reviewing the various authorities on the subject, it has
observed as follows :-
"49. In Chinese Tannery Owners' Association (supra) the Calcutta High Court was examining an interim order of injunction that had been granted in favour of the plaintiff in a suit for money decree. The defendant appellant raised the plea that the provisions of order 39 Rule 1 of the Code was not applicable and the Civil Court could not have invoked its inherent power under Section 151 of the Code. The Division Bench held that the mere fact that there are certain provisions as regards the issue of injunctions in Order 39 of the Code does not debar the Court from passing temporary injunctions 6
for doing justice in the exercise of its power under Section 151 of the Code. The relevant paragraphs are:
"3. It is necessary to consider first the point taken by Mr. Sen on behalf of the appellants that it is not open to the Court to pass any order of injunction in the exercise of its inherent jurisdiction under Section 151, Civil P. C. His argument is that where the Code has clearly and fully dealt with a matter, there is no scope for any action under inherent jurisdiction. He further argues in this connection that a reading of Section 94 of the Code makes it clear that the provisions of Order 39, Civil P. C. were intended to be exhaustive as regards this matter of temporary injunction. For this proposition he has relied upon the decisions in the case of 'HEMENDRALAL ROY v. INDO SWISS TRADING CO. LTD.', 24 Pat 496. and in the case reported in NAGABHUSHAN REDDY v. NARASAMMA, (1950) 2 Mad L J 482. Quite clearly an opposite view was taken in the Allahabad case of 'DHANESHWAR NATH v. GHANSHYAM DHAR', ILR (1940) All 201.
50. There cannot be an absolute proposition that in a money claim no order of injunction or attachment or receiver could be made. Order 38 to Order 40 of the Code of Civil Procedure does not restrict the power of the court to pass any order that a court is empowered to pass just because it is a money 7
claim. We have already discussed the circumstances when the court can exercise any of such power.
51. If there were doubts about exercising power under any of the aforesaid provisions, it can be safely stated that the court has inherent power to pass an order of injunction or attachment upon an unimpeachable liquidated claim being demonstrated and upon it being established that the respondents are taking steps to improperly deny the
realization of the claim."
10. In the facts of the present case, the plaintiff has claimed a decree for
a sum in excess of Rs. 81 crores on the basis of an agreement under
which, the defendant was to construct and deliver flats to the plaintiff. The
ultimate agreement between the parties, had obliged the defendant to
construct and make over unit Nos. 12W, 13W and 14W located on the 12th,
13th and 14th floor on the proposed building "Wellside Camac" to be
constructed by the defendant upon the plaintiff paying the agreed
consideration in respect thereof. Admittedly, the plaintiff had paid a sum of
Rs. 14,06,70,000/- to the defendant. Apparently, the parties had fallen out
of the contract. The parties have claimed differently with regard to the
termination of the contract. According to the plaintiff, it has originally
terminated the contract and the defendant is obliged to refund the entirety 8
of the consideration advanced along with interest at the rate of 18 per cent
per annum. According to the defendant, the termination effected by the
plaintiff has been premature therefore entitling the defendant to deduct
amounts stipulated in the contract. According to the defendant, it has to
pay a sum of Rs. 12,81,22,349/- to the plaintiff after deduction as claimed.
The plaintiff has expressed its unwillingness to accept such sum in full
and final settlement of its claim. This stand of the respective parties has
raised triable issues.
11. As noted above, the parties to the instant suit have raised triable
issues. However, it can be garnered out of the facts of the present case at
this stage that, the defendant is liable to pay the plaintiff. The quantum of
liability has to be decided.
12. Till such time such quantum of liability is decided and the defendant
pays the same, and since, the contract that the parties had entered into
related to units Nos. 12W, 13W and 14W on the 12th, 13th and 14th floor of
the proposed building, it would be appropriate to grant an order of
injunction restraining the defendant from creating any third party rights
over and in respect of such units without the leave of the Court. 9
13. IA GA No. 1 of 2020 in CS 142 of 2020 is disposed of accordingly.
[DEBANGSU BASAK, J.]
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free