Ajay Mehra vs Ebercon Gmbh And 3 Ors
- CitationAIRONLINE 2019 BOM 3323
Ratio decidendi
The rule this decision rests on
Based on my careful reading of this judgment, here are the key rationes decidendi: 1. The parties validly waived their right to a closing oral hearing under proviso to Section 24 of the Arbitration and Conciliation Act, 1996 through the statements of counsel at the procedural hearing of 11.12.2015 and Procedural Order No.5, which conditioned oral submissions on the Tribunal's discretion to determine whether they were necessary, and this waiver was not vitiated by the filing of written submissions. 2. The Supreme Court's direction in paragraph 153 of its judgment dated 14.02.2014 to refer "all disputes arising between the parties in relation to the SHA, TKHA, SSHAs, STKHA, Agreed Principles and IPLA" unambiguously vested the Arbitral Tribunal with jurisdiction to adjudicate disputes arising under the Shareholder Agreement despite there being a separate arbitration clause thereunder, given the context of decades-long cross-forum litigation and the intention to arbitrate evident in all agreements. 3. Insufficiency of specific pleadings in the Statement of Claim does not render an issue non-arbitrable where the claim has been continuously ventilated through Written Submissions, Procedural Orders passed by consent make plain that the issue falls within adjudication, the opposing party leads evidence on the issue, and the parties engage in detailed submissions on the issue without raising objection as to pleadings. 4. The Intellectual Property License Agreement signed by both parties with full signatures at the execution page on 30.09.2006, notwithstanding blank spaces, missing annexures, and discrepancies in dating, constitutes a concluded binding contract, as the formality of appending complete signatures at designated execution spots is inconsistent with the hypothesis that signatures were appended merely for identification of a draft. 5. The Tribunal did not exceed its jurisdiction in directing the Mehra brothers to pay WWIL rather than Enercon GmbH for profits wrongfully diverted through Vish Wind transactions, as such direction is grounded in the same premise of breach of the Shareholding Agreement and constitutes an appropriate exercise of discretion under the prayer for "further and other reliefs." 6. The direction that the Mehra brothers bear the costs of arbitral proceedings rather than WWIL is appropriate where those brothers were in de facto control of WWIL during the actionable breaches, as directing WWIL to bear costs would effectively saddle the successful claimant with liability proportionate to its shareholding in WWIL. 7. Allegations of bias and prejudice inferred solely from the use of strong language by arbitrators in evaluating witness credibility, absent any cogent evidence of actual bias, do not provide grounds to set aside an award under Sections 34-37 of the Act. NO_RATIO: The large portion of the judgment dealing with facts, the history of litigation between the parties, and the specific findings on which party's evidence was more credible constitute factual findings and credibility determinations rather than the rules of law on which the decision rests.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
Jdk/pdp 1 jt-comap-315, 314 & 316 -19.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY ORDINARY ORIGINAL CIVIL JURISDICTION IN ITS COMMERCIAL DIVISION
COMMERCIAL APPEAL NO. 314 OF 2019 IN COMMERCIAL ARBITRATION PETITION NO. 205 OF 2016 Ajay Mehra ) being an Indian Inhabitant ) residing at 101, Hare Krishna ) Presidency Society, North ) South Road No. 8, JVPD Scheme, ) Vile Parle (W), Mumbai 400 048. ) .. Appellant
Vs.
1. Enercon GmbH ) a Company incorporated and ) existing under the laws of Germany ) and having its Registered Office at ) Dreekamp 5, D26605, Aurich, ) Germany. ) 2. Wobben Properties Gmbh, ) a company incorporated and ) existing under the laws of Germany ) having its Registered office at ) Dreekamp 5, D26605, Germany )
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 2 jt-comap-315, 314 & 316 -19.doc
3. Wind World India Limited ) a Company incorporated under the ) Companies Act, 1956 and having its) registered office at Plot No.33, ) Daman - Patalia, Bhimpore, ) Daman - 396210 ) 4. Mr. Yogesh Mehra, ) being an Indian Inhabitant ) residing at 101, Hare Krishna ) Presidency Society, North South ) Road No.8, JVPD Scheme, ) Vile Parle (W), Mumbai-400 048 ) ..Respondents
WITH COMMERCIAL APPEAL NO. 315 OF 2019 IN COMMERCIAL ARBITRATION PETITION NO. 196 OF 2016
Yogesh Mehra ) being an Indian Inhabitant ) residing at 101, Hare Krishna ) Presidency Society, North South ) Road No.8, JVPD Scheme, ) Vile Parle (W), Mumbai-400 048 ) .. Appellant
Vs.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 3 jt-comap-315, 314 & 316 -19.doc
1. Enercon GmbH ) a Company incorporated and ) existing under the laws of Germany ) and having its Registered Office at ) Dreekamp 5, D26605, Aurich, ) Germany. ) 2. Wobben Properties Gmbh, ) a company incorporated and ) existing under the laws of Germany ) having its Registered office at ) Dreekamp 5, D26605, Aurich, ) Germany ) 3. Wind World India Limited ) a Company incorporated under the ) Companies Act, 1956 and having its) registered office at Plot No.33, ) Daman - Patalia, Bhimpore, ) Daman - 396210 ) 4. Ajay Mehra ) being an Indian Inhabitant ) residing at 101, Hare Krishna ) Presidency Society, North ) South Road No. 8, JVPD Scheme, ) Vile Parle (W), Mumbai 400 048. ) .. Respondents
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 4 jt-comap-315, 314 & 316 -19.doc
WITH COMMERCIAL APPEAL NO. 316 OF 2019 IN COMMERCIAL ARBITRATION PETITION NO. 16 OF 2017
Wind World India Limited ) a Company incorporated under the ) Companies Act, 1956 and having its ) registered office at Plot No.33, ) Daman - Patalia, Bhimpore, ) Daman - 396210 ) .. Appellant
Vs.
1. Enercon GmbH ) a Company incorporated under the ) provisions of the Companies Act, ) 1956 and having its Registered ) office at Adani House, Near ) Mithakali Circle, Navrangpura ) Ahmedabad- 380 009 ) 2. Wobben Properties Gmbh, ) a company incorporated and ) existing under the laws of Germany ) having its Registered office at ) Dreekamp 5, D26605, Germany )
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 5 jt-comap-315, 314 & 316 -19.doc
3. Mr. Yogesh Mehra, ) being an Indian Inhabitant ) residing at 101, Hare Krishna ) Presidency Society, North South ) Road No.8, JVPD Scheme, ) Vile Parle (W), Mumbai-400 048 ) 4. Ajay Mehra ) being an Indian Inhabitant ) residing at 101, Hare Krishna ) Presidency Society, North ) South Road No. 8, JVPD Scheme, ) Vile Parle (W), Mumbai 400 048. ) ..Respondents
Mr. Shyam Mehta, Senior Advocate i/b Bimal Rajasekhar for the Appellant in COMAP No. 314 of 2019
Dr. Birendra Saraf a/w Mr. Ranjeev Carvalho, Mr. Sachin Chandrana,Ms. Sanaya Dadachanji, Mr. Rohit Lalwani and Mr. S. J. Kakadia i/by Manilal Kher Ambalal and Co. for the Appellant in COMAP No.315 of 2019.
Mr. Zal Andhyarujina a/w Mr. Karan Bhide, Mr. Kartikeya Desai, Mr. Asadali Mazgaonwala and Ms. Devashree Maniar i/by Kartikeya & Associates for Appellant in COMAP No. 316 of 2019, and for respondent No.3 in COMAP Nos.314 and 315 of 2019.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 6 jt-comap-315, 314 & 316 -19.doc
Mr. S. U. Kamdar, Senior Advocate a/w Mr. Sarosh Bharucha, Mr. Jehangir Jeejeebhoy, Mr. Vivek Vashi, Mrs. Kanika Sharma Goenka, Ms. Shaheda Madraswala, Ms. Swati Khinvasara and Mr.Cyrus Jal i/by Vashi and Vashi for respondent Nos.1 and 2 in COMAP No. 314 of 2019.
Mr. Aspi Chinoy, Senior Advocate a/w Mr. Karl Tamboly, Mr. Jehangir Jeejeebhoy, Mr. Vivek Vashi, Mrs. Kanika Sharma Goenka, Ms. Shaheda Madrawala, Ms. Swati Khinvasara and Mr. Cyrus Jal i/by Vashi and Vashi for respondent Nos.1 and 2 in COMAP No. 315 of 2019.
Mr. Janak Dwarkadas, Senior Advocate a/w Mr. Jehangir Jeejeebhoy, Mr. Vivek Vashi, Mrs. Kanika Sharma Goenka, Ms. Shaheda Madrawala, Ms. Swati Khinvasara and Mr. Cyrus Jal i/by Vashi and Vashi for Respondent Nos.1 and 2 in COMAP No.316 of 2019.
CORAM : PRADEEP NANDRAJOG, CJ. & N. M. JAMDAR, J.
RESERVED ON : 12 JUNE, 2019 PRONOUNCED ON : 24 JUNE, 2019
JUDGMENT [PER PRADEEP NANDRAJOG, CJ.]
1. Vide this common judgment we propose to decide a
batch of Commercial Arbitration Appeals preferred under Section
37(1)(c) of the Arbitration and Conciliation Act, 1996
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 7 jt-comap-315, 314 & 316 -19.doc
(Commercial Appeal No.314 of 2019 arising out of Commercial
Arbitration Petition No. 205 of 2016, Commercial Appeal No.
315 of 2019 arising out of Commercial Arbitration Petition No.
196 of 2016 and Commercial Appeal No. 316 of 2019 arising out
of Commercial Arbitration Petition No. 16 of 2017) that are
directed against the common Judgment dated 14.12.2018 passed
by a learned Single Judge of the Commercial Division of this
Court upholding the majority Award passed by the Arbitral
Tribunal. We may note that vide Orders dated 21.01.2019 and
29.01.2019 certain corrections have been incorporated to the
Judgment by the learned Single Judge upon a request in this regard
having been made by the Petitioners/Appellants-herein.
2. The Appellant before us in Commercial Appeal No.
316 of 2019 is Wind World (India) Pvt. Ltd. (WWIL). It is an
unlisted public limited company incorporated under Indian
Companies Act, 1956 as a joint venture between Enercon GmbH
and members of the Mehra family (the Mehra's). Enercon is the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 8 jt-comap-315, 314 & 316 -19.doc
registered holder of 56% of the issued share capital, and the
Mehra's are the registered holders of the residual 44%.
3. The Appellant in Commercial Appeal No. 315 of
2019 is Mr. Yogesh Mehra; who is described as the Managing
Director of WWIL and its shareholder.
4. The Appellant in Commercial Appeal No. 314 of
2019 is Mr. Ajay Mehra; who is the Director of WWIL and its
shareholder.
The Appellants- Mr. Yogesh Mehra and Mr. Ajay
Mehra are brothers; who may conveniently be referred by us as the
'Mehra brothers'.
5. The contesting Respondents before us are body
corporates incorporated under the laws of Germany. Enercon
GmbH (Enercon) is a company incorporated in the year 1984
and carrying on the business of engineering manufacturing and
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 9 jt-comap-315, 314 & 316 -19.doc
marketing Wind Turbine Generators (WTGs) and components.
Wobben Properties GmbH (WPG) is a company incorporated
in the year 2004 to hold the intellectual property acquired by Dr.
Alloys Wobben, the founder of Enercon.
EVOLUTION OF BUSINESS RELATIONSHIP BETWEEN THE PARTIES AND GENESIS OF THE DISPUTE
6. Before proceeding to analyse the Award passed by the
Arbitral Tribunal and examining the impugned Judgment
affirming the majority Award, we embark upon the exercise of
tracing the evolution of the relationship between the parties and
the genesis of the dispute.
7. On 10.05.1993, the Mehra's incorporated Wind
World Power Ltd. as they were desirous of entering the business
of wind energy in India. In September 1993, meetings took place
between Mr. Yogesh Mehra and Dr. Wobben and other
representatives of Enercon. Since the meetings were fruitful and a
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 10 jt-comap-315, 314 & 316 -19.doc
prospective commercial relationship was under contemplation,
requisite permission was sought from the Reserve Bank of India
(RBI).
8. Vide communications/letters dated 14.10.1993 and
20.11.1993, the RBI accorded its "in principle" approval for
financial collaborations. On 23.11.1993 Wind World Power Ltd.
was renamed as Enercon (India) Ltd.
9. On 12.01.1994, Enercon GmbH and Mr. Yogesh
Mehra, acting for himself and on behalf of his family members
(Mehra Group), entered into a Shareholding Agreement (SHA).
At the relevant time, Enercon GmbH was holding 51% of issued
share capital and Mehra's held the residual 49%. A Technical
Know-How Agreement (TKHA) of the even date was also
entered between Enercon GmbH and Enercon (India) Ltd. which
granted Enercon (India) Ltd. the right and licence to use certain
defined technical know-how for manufacturing a specified class of
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 11 jt-comap-315, 314 & 316 -19.doc
WTGs (E-26) and agreed to supply it with certain of essential
components for manufacturing them. The Technical Know-How
Agreement was expressed to continue in force for 10 years. On
19.06.1998, a Supplementary Share Holding Agreement
(SSHA) was entered between the parties. Further on 19.05.2000,
a Second Supplementary Share Holding Agreement (SSSHA)
was entered between the parties, which resulted in an increase of
Enercon GmbH's shareholding to the tune of 56%. On the same
date, a Supplementary Technical Know-How Agreement
(STKHA) was executed by which the grant of Technology was
enlarged to include additional classes of WTGs (E-30, E-40 and at
least two other ranges/models). Enercon GmbH claims that the
obligation to supply the Technical Know-How of two other
ranges/models stood satisfied upon supply of know-how of E-
40/644/E2, E-40/644/E3B and E-40/644/E2B to Enercon (India)
Ltd. However, Enercon (India) Ltd. disputes such assertion.
10. Upon the expiry of the ten-year term on 12.01.2004,
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 12 jt-comap-315, 314 & 316 -19.doc
the parties initiated negotiations to enter into a new TKHA.
Exchange of correspondence reveals that during negotiations Mr.
Yogesh Mehra pitched a proposal that Enercon (India) Ltd. may
not be required to pay royalties accruing from the sale of Wind
Turbine Generators manufactured from the new technology to be
received from Enercon GmbH. However, Enercon GmbH did not
relent, and the Mehra's had to ultimately accept the condition of
payment of royalties. It would be pertinent to highlight that
Enercon GmbH claims that Enercon (India) Ltd. was supplied
confidential technology for manufacturing further models of
WTGs (E-33, E-48 and E-53) in anticipation of a new agreement
which would be shortly formalised and executed between the
parties.
11. On 23.05.2006, the parties signed non-binding
Heads of Agreement on a Proposed Intellectual Property
License Agreement (HoA) at Aurich, Germany. The said
document was expressed to represent the final views of the parties
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 13 jt-comap-315, 314 & 316 -19.doc
on the terms of a new agreement. A draft of the Intellectual
Property License Agreement (IPLA) was attached to the same.
12. During the months to follow, there was an exchange of
drafts of the proposed Intellectual Property License Agreement
(IPLA). One of the primary bone of contentions during these
protracted negotiations was the basis/formula for calculation of
royalty. As a matter of fact, the HoA recorded that the services of
Mr. N. P. Sarda, Partner of Deloitte Haskins and Sells (DHS) be
commissioned to seek their views on a formula for calculating
royalties that would be in consonance with the requirements of
Indian law.
13. A meeting was scheduled in Germany for 17-20th
September, 2006 for finalising the IPLA. On 15.09.2006, a final
version of IPLA was sent by electronic mail by Ms. Fritsch
Nehring to Mr. Yogesh Mehra for his perusal. Since the finalised
draft of the IPLA was only sent at the last moment, Mr. Yogesh
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 14 jt-comap-315, 314 & 316 -19.doc
Mehra postponed his trip to Germany to read the draft.
14. Ultimately, Mr. Yogesh Mehra arrived in Bremen
(Germany) on the morning of 29.09.2006. Discussions on the
proposed IPLA ensued. However, it is common ground that no
document was signed on this date.
15. The controversy stems from the events that transpired
on 30.09.2006. There is marked divergence of claims of rival
litigants in this regard. It is the case of Enercon GmbH that after
intensive discussions, Mr. Yogesh Mehra and Dr. Alloys Wobben
finally executed the IPLA in the presence of Mr. Kettwig, though
he did not append his signatures thereon as a witness. Another
document titled "Agreed Principles" was also executed which
comprised the agreed principles that were binding and would form
the basis of four agreements that would be executed between the
parties, namely (1) IPLA "Draft enclosed" (2) Successive
Technology Transfer Agreement (3) Name Use License
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 15 jt-comap-315, 314 & 316 -19.doc
Agreement (4) Amendment to the existing Shareholder
Agreement. A note received from DHS comprising of the
proposed formula for the computation of royalties was also
initialled by the parties. Per contra, the Mehra's contend that only
the Agreed Principles were executed between the parties and the
IPLA in question was a mere draft attached to the Agreed
Principles. The same was initialled on each page by the parties
merely for identification.
16. The relations between the parties seem to have
embittered in view of the fact that Dr. Wobben was not in favour
of permitting an Initial Public Offering (IPO) for Enercon (India)
Ltd. as intently canvased by Mr. Yogesh Mehra; who wanted to
raise additional money for his family. Floating of an IPO was
subject matter of discussion between parties for some time,
however, the said proposal of Mr. Mehra was perhaps conclusively
rejected by Dr. Wobben in the meetings dated 29-30 September
2006 in Germany. Subsequent thereto, the negotiations between
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 16 jt-comap-315, 314 & 316 -19.doc
Dr. Wobben and Mr. Yogesh Mehra with regard to purchase of
additional shareholding by Enercon GmbH in Enercon (India)
Ltd. also failed. Mr. Yogesh Mehra intended to monetise his
shareholding.
17. Significantly, Mr. Yogesh Mehra through an electronic
mail dated 03.11.2006 addressed to Ms. Fritsch-Nehring expressed
his understanding that the draft of IPLA contained certain
inconsistencies, thereby implying that it was still a draft. Further
correspondence was exchanged between the parties in this regard,
which we shall advert to in greater detail a little later. Suffice would
it be to state that Enercon GmbH ultimately refuted the claim of
Mr. Mehra that IPLA had not been executed as a concluded
contract.
18. Enercon GmbH claimed that it was illegally ousted by
the Mehra's from the management of affairs of Enercon (India)
Ltd. and no information was shared with regard to the activities of
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 17 jt-comap-315, 314 & 316 -19.doc
the company. The issue precipitated, and Appellants claim that
supplies of equipment were abruptly stopped by Enercon GmbH
in the month of February, 2007. The said events resulted in a spate
of unsavoury litigations between parties before various forums
including the Company Law Board, Civil Court at Daman,
Bombay High Court, the Hon'ble Supreme Court and certain
Foreign Courts.
19. The Mehra's instituted a derivative suit in this Court
bearing Suit No. 2667 of 2007, inter alia, seeking directions to
ensure continuous and uninterrupted supply of parts and specific
performance of certain contracts. Certain interim arrangements
were made under the Orders of the Court to ensure supplies.
20. Enercon GmbH, on the other hand, invoked the
jurisdiction of the Company Law Board (CLB) in terms of Section
397/398 of the Companies Act, 1956 and preferred Company
Petition No. 121 of 2007 alleging oppression and
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 18 jt-comap-315, 314 & 316 -19.doc
mismanagement. The Mehra's filed an application under Section 8
of the Arbitration and Conciliation Act, 1996 seeking reference to
arbitration, however, the same was dismissed by the CLB vide
Order dated 29.10.2007. Shortly thereafter, the Mehra's followed
the suit and filed Company Petition No. 74 of 2008 also casting
allegations of oppression and mismanagement against Enercon
GmbH. We may note that both the petitions were disposed by the
CLB in terms of its common Judgment dated 14.12.2012. The
CLB dismissed the petition filed by Enercon GmbH opining the
same to be not maintainable and allowed the petition preferred by
the Mehra's holding that they had succeeded in making out a case
of oppression at the hands of Enercon GmbH. The said decision of
the CLB was assailed before this Court in Company Appeal No.s
42-43 of 2013 and vide Judgment dated 20.08.2015 the Company
Petitions were remanded to CLB for fresh consideration. We are
informed that the said proceedings are pending before the CLB.
21. It would be pertinent to highlight that Enercon
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 19 jt-comap-315, 314 & 316 -19.doc
GmbH demanded royalties payable in its favour as mandated
under the IPLA. On 22.08.2007, Enercon (India) Ltd. belatedly
transmitted royalties to the tune of 986,399.88 pounds for the
period 01.10.2006 to 31.12.2006. Similarly, further royalties to the
tune of 1.64 million pounds were transmitted to Enercon GmbH
on 16.10.2008 in respect of the period 01.01.2007 to 31.03.2007,
and 570,000 pounds were remitted in respect of the period from
01.04.2007 to 31.12.2007. On 14.11.2009, Enercon (India) Ltd.
made a last payment of royalties in the sum of 2,114,852 pounds.
It is the claim of the Appellants that the said royalties were not
payable and were transmitted under bonafide mistaken belief.
They attempt to explain that the said payments were not made
pursuant to the IPLA, which was never executed to bind the
parties. The Appellants contend that the monies were transmitted
pursuant to the obligations perceived by Enercon (India) Ltd.
under the Agreed Principles.
22. On 13.03.2008, Enercon GmbH addressed a
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 20 jt-comap-315, 314 & 316 -19.doc
communication to the Mehra brothers invoking the arbitral
agreement as comprised in Clause 18.1 of the IPLA. Mr. V.V
Veeder, QC was nominated as an Arbitrator on their behalf.
23. Consequent thereto, on 27.03.2008 'Arbitration
Claim Form' was issued by Enercon GmbH seeking several
declaratory reliefs in relation to the IPLA from the High Court of
Justice, Queens Bench Division, Commercial Court- United
Kingdom.
24. The claim form was enclosed along with a
communication dated 02.04.2008 and was sent to the Appellants-
herein. The form was served upon Enercon (India) Ltd. on
04.04.2008 at Daman.
25. On 08.04.2008, the Appellants-herein instituted
Regular Suit No. 9 of 2008 before the Court of the Civil Judge,
Senior Division-Daman seeking, inter alia, a declaration to the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 21 jt-comap-315, 314 & 316 -19.doc
effect that the draft IPLA was not a concluded contract capable of
binding parties and consequently, there was no arbitration
agreement. The learned Trial Court at Daman directed the
Respondents to maintain status quo with regard to the proceedings
initiated by them before the English High Court.
26. In the interregnum, Enercon (India) Ltd., without
prejudice to its rights, nominated Mr. Justice B.P Jeevan Reddy,
Former Judge-Supreme Court of India, as Arbitrator.
27. That on 05.08.2008 both the nominated Arbitrators
addressed a joint-letter to the effect that there were inherent
defects in the arbitration clause and they were unable to proceed
further to appoint the third/Presiding Arbitrator.
28. During the course of proceedings in the Civil Suit
instituted at Daman, an application in terms of Section 45 of the
Arbitration & Conciliation Act, 1996 was filed by Enercon
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 22 jt-comap-315, 314 & 316 -19.doc
GmbH seeking to invoke the arbitration clause as comprised
under the IPLA. The Mehra's resisted to submitting themselves to
arbitration by inter alia, contending that the IPLA executed
between the parties was a mere draft and not a concluded contract.
Vide Order dated 05.01.2009 the Daman Court dismissed this
application and subsequently vide Order dated 09.01.2009 it
proceeded to allow the application preferred by the Appellants
seeking interim reliefs in the form of anti-arbitration injunction.
29. The Orders passed by the Trial Court at Daman were
assailed before the Daman Appellate Court. Vide Order dated
27.08.2009 the Court allowed the appeals. The anti-arbitration
injunction was vacated, and the application under Section 45 of
the Arbitration and Conciliation Act, 1996 was allowed.
30. The aforesaid Order of the Appellate Court was
challenged by the Appellants before this Court by preferring Writ
Petition No. 7636 of 2009 and Writ Petition No. 7804 of 2009.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 23 jt-comap-315, 314 & 316 -19.doc
Ultimately the said petitions came up to be dismissed by the
Bombay High Court vide Order dated 05.10.2012.
We do not propose to delineate in detail the
chequered history of litigation that ensued between the parties
before the English Courts as the same remains a mere historical
event and has no bearing upon the issues involved for our
consideration.
31. The decision of this Court was carried by the
Appellants to the Supreme Court by preferring Special Leave
Petitions. The Supreme Court in its decision dated 14.02.2014
while referring the parties to arbitration authoritatively held that
the seat of arbitration would be India, however the venue of
arbitration would be London as stipulated by the parties in the
agreement. As stated in the agreement, the applicable law
governing the dispute would be the Indian Law. In paragraph 153
of the report of the Judgment the Court directed -
"...All the disputes arising between the parties in
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 24 jt-comap-315, 314 & 316 -19.doc
relation to the following agreements viz. SHA, TKHA, SSHA, STKHA, Agreed Principles and IPLA including the controversy as to whether IPLA is a concluded contract are referred to the Arbitral Tribunal."
32. Further, the Court was pleased to appoint Lord
Hoffmann as the third Arbitrator, and it was held that he would
act as the Chairman of the Arbitral Tribunal. The conclusion
arrived by the Bombay High Court that English Courts would
enjoy concurrent jurisdiction was set aside. Consequently, the
Respondents were restrained from further prosecuting the
proceedings instituted by them before the English Courts. The
proceedings pending before the Trial Court at Daman and the
Civil Suit No. 2667 of 2007 before the Bombay High Court along
with the Contempt Petition filed in relation thereof were directed
to be stayed during the pendency of arbitration.
33. It is pertinent to note for the purpose of lending
clarity to our factual narrative that the name of Enercon (India)
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 25 jt-comap-315, 314 & 316 -19.doc
Ltd. was changed to Wind World (India) Ltd. (WWIL) with
effect from 01.01.2013.
34. The Arbitration proceedings were finally set into
motion in terms of directions passed by the Supreme Court. Since
many years had lapsed since the invocation of arbitral clause and
the same had come to a grinding halt, Mr. Justice B.P Jeevan
Reddy expressed his inability to undertake the assignment any
further. Consequently, the Appellants nominated Mr. Justice R.V
Raveendran, Former Judge- Supreme Court of India as an
Arbitrator.
35. With a view to avoid prolixity, we eschew unnecessary
reference to the itinerary of the proceedings, save and except to
deal with the submissions of the parties at the relevant stage. The
chronology of proceedings has been exhaustively catalogued in
paragraphs 25 to 83 of the Final Award as passed by the majority -
Lord Hoffmann (Presiding Arbitrator) and Mr. VV Veeder, QC.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 26 jt-comap-315, 314 & 316 -19.doc
36. The Final Award passed by the Tribunal was a split
verdict. The majority comprising of Lord Hoffmann (Presiding
Arbitrator) and Mr. VV Veeder, QC substantially upheld the
claims of the Claimants (Respondents-herein) and rejected the
counterclaims set up by the Respondents (Appellants-herein). The
dissenting opinion dated 26.08.2016 was authored by Mr. Justice
R.V Raveendran.
37. We now proceed to microscopically analyse the Award
delivered by the Arbitral Tribunal.
ANALYSIS OF THE MAJORITY AWARD
38. The Tribunal concatenated the issues arising for their
consideration in paragraphs 84 to 89 of the Final Award authored
by the majority Arbitrators (Lord Hoffmann and Mr. VV Veeder,
QC).
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 27 jt-comap-315, 314 & 316 -19.doc
39. The central issue upon which the rights of parties
would have to be adjudicated was naturally whether the
Intellectual Property License Agreement (IPLA) could stated to
have been a concluded contract that would bind the signatories. It
was also required to be considered if the said Agreement even if
executed with the intent to create binding legal relations was liable
to be declared void on the ground of uncertainty. The Tribunal
also posed and proceeded to answer an alternative issue as to the
rights of parties under the Technical Know-How Agreement
(TKHA), if the IPLA was held not to be a binding contract.
The next set of issues pertain to the alleged breach of
provisions of IPLA by Wind World (India) Ltd. (WWIL) and
whether Enercon GmbH was entitled to terminate the agreement
for repudiatory breach. The said issue was required to be answered
only if it was held by the Tribunal that the IPLA was a binding
agreement.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:57 ::: Jdk/pdp 28 jt-comap-315, 314 & 316 -19.doc
The Tribunal also considered the counter-claim set up
by WWIL against Enercon Gmbh for damages for breach of
contracts to deliver components and other materials in the year
2007-08.
The last group of issues proposed to be dealt by the
Tribunal pertain to the alleged breaches of fiduciary and
contractual duties owed personally by the Mehra directors to
EnerconGmbH under the Share Holder Agreement (SHA).
WHETHER THE IPLA IS A CONCLUDED CONTRACT
40. The Tribunal elaborately considered the events as they
unravelled after the expiry of the TKHA on 12.01.2004. The
correspondence between the parties for executing a new agreement
was noticed wherein an initial stance was adopted by Mr. Yogesh
Mehra that royalty may not be charged for new models proposed to
be launched in the Indian market. However, Enercon GmbH were
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 29 jt-comap-315, 314 & 316 -19.doc
categoric that Dr. Wobben was considering the levy of royalty to
the tune of 4% or 5%. On 02.11.2004, Drafts of royalty agreements
were provided to Mr. Mehra during his visit to Enercon in
Germany. Thereafter, it seems that Mr. Mehra had reconciled to
the fact the royalties would be payable for the new models of Wind
Turbine Generators (WTGs) and the discussions centered upon
the issue of computation of royalty. As highlighted earlier, on
23.05.2006 the parties signed non-binding Heads of Agreement
on a Proposed Intellectual Property License Agreement (HoA)at
Aurich, Germany. The said document was expressed to represent
the final views of the parties on the terms of a new agreement. A
draft of the IPLA was attached to the same. Clause 5.1 of the draft
IPLA contemplated royalty of 5% on the net sales value of
products sold by WWIL. The net sales value was elaborately
defined to mean -
"the net ex-factory sales price of the Products, exclusive of excise duties, minus the cost of the standard bought out Wind Energy Technology
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 30 jt-comap-315, 314 & 316 -19.doc
components and the landed costs of imported Wind Energy Technology components, irrespective of the source of procurement, including ocean freight, insurance, custom duties and the like."
As a matter of fact, the HoA recorded that the services
of Mr. N. P. Sarda, Partner of Deloitte Haskins and Sells (DHS) be
commissioned to seek their views on a formula for calculating
royalties that would be in consonance with the requirements of
Indian law.
41. In furtherance thereof, Mr. Yogesh Mehra
corresponded with Mr. Sarda and elicited his opinion on a formula
provided by him in his letter dated 23.06.2006. The formula sent
by Mr. Mehra upon which opinion of Mr. Sarda was sought is
extracted hereunder :
"Net Ex-Factory Sales Price of the Wind Energy Converters, excluding Excise duty, Taxes, Levies ,
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 31 jt-comap-315, 314 & 316 -19.doc
Cess etc. LESS:
Landed cost of all imports, other than capital equipment and the cost of standard bought out components and raw material procured locally"
42. The Tribunal noticed that this was not the formula as
comprised in the draft IPLA on which it had been agreed that
opinion of Mr. Sarda be sought. Rather it was a formula of Mr.
Mehra's own devising. It included deductions which did not form
part of the RBI formula. On 16.06.2006, Mr. Sarda is stated to
have replied by reciting the RBI formula and certifying that the
formula proposed by Mr. Mehra fell within it. The Tribunal
observed that Enercon GmbH did not notice this discrepancy at
this stage and the same caused difficulties later.
43. During the months to follow, there was exchange of
drafts of the proposed IPLA. A meeting was also held in Aurich on
07-08 August 2006 where the parties signed Heads of Agreement
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 32 jt-comap-315, 314 & 316 -19.doc
with regard to a Share Holder Agreement. A meeting was
scheduled in Germany for 17-20th September 2006 for finalising
the IPLA. On 15.09.2006, a final version of IPLA was sent by
electronic mail by Ms. Fritsch-Nehring to Mr. Yogesh Mehra for
his perusal. It was also stated therein that Dr. Wobben had desired
that he would like to first discuss the final version of the IPLA
before any discussion takes place on other issues. Since the
finalised draft of the IPLA was only sent at the last moment, Mr.
Yogesh Mehra postponed his trip to Germany with a view to
consider the said draft.
44. Ultimately, Mr. Yogesh Mehra arrived in Bremen
(Germany) on the morning of 29.09.2006. Dr. Wobben received
him at the Airport and accompanied him to the Hilton Hotel.
Discussions on the proposed IPLA ensued. They were joined at
lunch by Mr. Hans Dieter Kettwig. The Tribunal noticed the
evidence of Mr. Kettwig where he testified that he sensed the
discussions had not gone smoothly and he could feel some
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 33 jt-comap-315, 314 & 316 -19.doc
tension. Dr. Wobben had informed Mr. Kettwig in the presence of
Mr. Mehra that Mr. Mehra also wanted a further document to set
out certain principles that would be reflected when it came to
subsequently finalising other contracts. However, this was on a
clear understanding that the IPLA was to be entered into without
change and the agreed principles related to other agreements
which would be shortly entered into. Before leaving, Dr. Wobben
had frustratingly exclaimed that the IPLA should be accepted in its
current form. Dr. Wobben had left Mr. Kettwig to discuss the new
document headed "Agreed Principles". However, it is common
ground that no document was signed on this date.
45. The Tribunal was of the considered view that the
evidence furnished by Mr. Kettwig appeared to be reliable vis a vis
the version of events disclosed by Mr. Yogesh Mehra. The
Tribunal observed that the objections/reservations expressed by
Mr. Mehra to the drafts of IPLA shared with him earlier by
Enercon GmbH had been firmly dealt by Dr. Wobben in August
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 34 jt-comap-315, 314 & 316 -19.doc
2006. It was improbable that Dr. Wobben would now have made a
'U-turn' on the issues canvassed by Mr. Mehra during negotiations
which took place 29.09.2006.
46. Mr. Kettwig stated in evidence that to the best of his
recollection, Mr. Mehra had brought with him a draft of Agreed
Principles in hard copy. The Agreed Principles were
predominantly drafted by Mr. Mehra in advance of the meeting
rather than being drafted together in the meeting. Mr. Kettwig
further deposed that Mr. Mehra accepted at the meeting that he
would enter into the IPLA the next day, and this was unaffected by
the Agreed Principles. Per contra, Mr. Mehra claimed in his
evidence that the draft of Agreed Principle had not been brought
by him. He stated that this document had been typed on the
computer in the Bremen Hotel. In this regard, the Tribunal
observed that Mr. Kettwig was neither a lawyer nor fluent in
English, unlike Mr. Mehra. The language of the Agreed Principles
suggested that its substance was derived from Mr. Mehra and his
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 35 jt-comap-315, 314 & 316 -19.doc
legal advisors in India. It was further held that Mr. Mehra
understood that the Agreed Principles would have no effect upon
the IPLA and that the IPLA was expected to be executed by the
parties during his stay in Aurich, Germany.
47. The Tribunal observed that Mr. Kettwig was not an
astute lawyer. He could thus could not visualise the effect of the
words- "Draft enclosed" comprised in the document-Agreed
Principles and that these words could later be construed to be
inconsistent with Enercon's intention of executing the IPLA
without any amendment. It was held that evidence of relevant
surrounding circumstances emerging from the contemporaneous
correspondence between parties and the evidence of Mr. Kettwig
established that both sides clearly understood that before any
discussion of other agreements took place, IPLA had to be
executed.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 36 jt-comap-315, 314 & 316 -19.doc
48. It was also observed that it was highly implausible that
the parties would sign the IPLA (twice in the case of Dr. Wobben
as he appended his signatures on behalf of Enercon GmbH aswell
as WPG) and initial every page merely to identify it as the latest
draft under discussion. The Tribunal noticed that such an
approach had not been adopted by the parties before with respect
to other documents that were available for similar treatment.
49. The Tribunal also held that the assertion of Mr.
Kettwig that after the execution of IPLA; which had been pending
since a long time, Mr. Mehra appeared rather emotional, was
supported by the contents and tenor of a letter authored by Mr.
Mehra on that very day viz. 30.09.2006. The letter was addressed
to Dr. Wobben and was penned by Mr. Mehra at his hotel before
leaving for India.
50. The contents of the said letter read :
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 :::
Jdk/pdp 37 jt-comap-315, 314 & 316 -19.doc
"Dear Dr. Wobben, Today when I reached back to Bremen, and before I leave back to India Mr. Wobben, in the last 13 years since I first met you, I have never felt so de-motivated lost, confused and empty! Mr. Wobben, my this trip to Germany was besides of course to clarify al the points of the agreements, was to also find some solutions to my problems which you had also promised to do. But I am sorry to state that I go back without any solutions! Mr. Wobben, you asked me to trust you, which I have always done-
(1) I signed the agreement, without even reading it, only because I trust you. (2) I did not even speak when Mr. Kettwig decided to write the royalty figure at 5%, because I trusted you, to be fair, because you always told me, that you wanted to make Enercon India Ltd.
financially strong. Now with this, it reduces the profitability of Enercon India Ltd by 40% straight away. [I have never
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 38 jt-comap-315, 314 & 316 -19.doc
said no to paym (sic.) of royalty, only I thought you will be fair and just].
This royalty, is when the agreements do not ev (sic.) provide for any other technologies. In fact it does not even provide for the E-82! (3) I trusted you, when you told me, that I should not pursue the 'UBS' proposal, because you did not feel comfortable, I dropped the idea totally, because you promised me that we would find a solution to my 'family' issues. But I go back again without any solution! Respected Mr. Wobben, it hurt me, when Mr. Kettwig mentioned today, that the value of Enercon's operations in India should be of a value of 250 Million Euro. If you believe that this is correct, than [sic] I personally take responsibility of the fact that, I failed, and for which I am willing to resign.
Mr. Wobben, you asked me to be truthful and open to you, which I always will be, and I thought I must write to you on exactly how I
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 39 jt-comap-315, 314 & 316 -19.doc
feel, because one thing for sure, is if I am not motivated, how can I motivate my team in India? If I cannot do that, all I can say is it is not fair for Enercon India! Dear Mr. Wobben, you have always been my source for inspiration and you have always motivated me, to be able to do my best! Mr. Wobben, I go back to India a disappointed man, as I have no face to show to my family, whom I promised, and who have always supported me for the last 13 years! Mr. Wobben, the decision is in your hands and please do not ask me to talk to anyone else about the issue, because I will not! At the end all I want to say is I trust you. Do not let me down! Regards! Yogesh Mehra."
\
51. The Tribunal observed that this reproachful letter was
inconsistent with Mr. Mehra's claim that only a draft had been
signed. None of this recrimination would have made sense if
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 40 jt-comap-315, 314 & 316 -19.doc
everything was still open to negotiation. The Tribunal did not
accept the explanation tendered by Mr. Mehra in evidence that
that the agreement which referred in his letter to have signed was
the Agreed Principles and not the IPLA and that he was not to be
taken literally.
52. Perusal of the majority Award reveals that the Tribunal
also formed an adverse opinion on the credibility of Mr. Mehra,
especially in view of his vacillating stand before different forums.
The Tribunal noticed that in July 2008, Mr. Mehra had stated on
solemn affirmation in the criminal proceedings initiated in India
before the Court of Magistrate that he had been coerced into
signing the Agreed Principles. It was observed that there were no
allegations of coercion made before the Tribunal and rather it was
claimed that almost immediately upon his arrival in Germany Dr.
Wobben accepted his objections to the IPLA and agreed that it
should be renegotiated at some indeterminate future date.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 41 jt-comap-315, 314 & 316 -19.doc
53. The Tribunal was of the considered view that it
appeared that Mr. Mehra was unwilling to execute the IPLA,
however after extensive rounds of deliberations and sustained
obstinacy of Dr. Wobben, he succumbed to sign the IPLA. He
later regretted the execution of the IPLA as Dr. Wobben did not
favourably acede to his proposal of floating an IPO to raise
additional money and neither did Dr. Wobben purchase additional
shareholding from the Mehra's on the tentative terms indicated
earlier during the course of negotiations. In the considered view of
the Tribunal, Mr. Mehra sought to retrace his acts by belatedly
propounding the version that he had merely signed a draft when
he sent an electronic-mail dated 03.11.2006 expressing his
disappointment at the withdrawal of the offer to purchase
additional shareholding.
54. The Tribunal also attached significance to the
circumstance that the parties appended their signatures at the spot
where they are expected to be placed when a contract is to be
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 42 jt-comap-315, 314 & 316 -19.doc
signed with an intent to create legal obligations and not for the
purpose of mere identification for future reference. It held that
though the surrounding circumstances that the IPLA is referred as
a draft in the Agreed Principles and that the IPLA as executed
omitted certain annexes which had been referred to in the body of
the document, were relevant, yet other circumstances as alluded to
by the Tribunal tilted the scales in favour of the conclusion that
the IPLA had been executed as a concluded contract.
55. While rendering its findings, the Majority in its
wisdom did not choose to comment upon the dissenting views
expressed by Justice Raveendaran on this issue. Further, it was
deemed unnecessary to undertake the exercise of analysing the
Agreed Principles to decide whether or not the IPLA was
inconsistent with them.
IPLA VOID FOR UNCERTAINTY
56. An alternate contention that was canvassed on behalf
of the Appellants-herein before the Arbitral Tribunal was that
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 43 jt-comap-315, 314 & 316 -19.doc
even if it were held that the IPLA was executed with the intent of
creating binding legal obligations, yet the same was not liable to be
enforced as the same was void for uncertainty. Reliance was placed
upon Section 29 of the Indian Contract Act, 1872.
57. It was submitted that the IPLA was inchoate. The
annexes with regard to trademarks and patents were not present,
and thus the identity of the licensed patents/trademarks was not
discernible.
58. In the absence of identification of patents, it was
submitted that the date of expiry of the agreement could also not
be determined as Clause 12.1 of the agreement provides that the
agreement would expire upon the expiry of the last to expire
patents.
59. Further, there existed discrepancies, which resulted in
the date of commencement of the agreement being uncertain.
Clause 1.1 mandates the 'effective date' as the date on which the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 44 jt-comap-315, 314 & 316 -19.doc
agreement is executed by the parties. It was highlighted that the
cover sheet bears the date 29 September 2006 whereas the
agreement commences with the recital that this agreement is
entered into at Aurich on 17 September 2006.
60. The Tribunal noticed decisions of various High
Courts wherein it had been held that the Courts ought not to
readily declare the solemn contracts entered into between parties
void for apparent vagueness or uncertainty which may otherwise
be capable of being removed by a process of proper interpretation.
61. Apropos, the contention with regard to date of
commencement of the agreement it was observed that there was
no doubt that the same was executed on 30.09.2006 and therefore
the same was liable come in effect from the same date as mandated
by Clause 1.1 of the agreement itself. The fact that the cover sheet
and the introductory recital contains other dates was explainable as
Mr. Mehra was initially expected to visit Germany on 17.09.2006
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 45 jt-comap-315, 314 & 316 -19.doc
for signing this agreement and in view of the same the opening
recitals contained reference to execution of the agreement on
17.09.2006. The said inaccuracies and clerical discrepancies would
not in the opinion of the Tribunal make the date of
commencement of IPLA uncertain.
62. With regard to the argument of absence of discernible
identity of patents and trademarks licensed, it was observed by a
matter of construction that license must have extended to include
all Indian patents and trademarks to Enercon's name. Such patents
and trademarks were clearly identifiable as being available on the
face of public record. It was observed that there was no evidence to
suggest the reason why parties would have wished to exclude
certain patents/trademarks from the license. In wake of the finding
that the Tribunal was of the view that the patents which formed
the subject matter of the agreement were capable of being
identified, it could be no longer be contended that the date of
expiry of the agreement could not be ascertained.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 46 jt-comap-315, 314 & 316 -19.doc
NATURE OF RIGHTS STEMMING FROM THE TKHA
63. The Tribunal noted that in view of the fact that it had
held that the IPLA was a concluded contract capable of binding
the signatories thereto, it was not necessary to opine upon the
rights of the parties flowing from the TKHA as the same had
expired and at any rate stood superseded by the IPLA. However, in
view of the fact that a substantial amount of time had been
dedicated to this issue during the proceedings and expert evidence
had been led by the parties, the Tribunal chose to render its
findings on this aspect of the matter.
64. That it had been contended before the Tribunal on
behalf of the Appellants-herein that the TKHA resulted in
outright transfer of rights in perpetuity of the technology
comprised therein. Emphasis was laid upon the meaning of the
term 'transfer' and the regulatory backdrop of RBI in which it was
required to be interpreted. It was submitted that the approvals
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 47 jt-comap-315, 314 & 316 -19.doc
accorded by the RBI were predicated on the premise that the
transfer of technology was in perpetuity and the same would stand
absorbed/indigenized. Expert evidence was led in the form of
testimony of Mr. Khizer Ahmed to suggest that mere license of
technology for a specified duration would fall foul of the
regulatory framework of the RBI. Thus, the Appellants-herein
were entitled to manufacture WTG's comprised under the
TKHA/STKHA and no longer be required to pay royalty to the
Claimants (Respondents-herein) upon the expiry of the agreement
or in the case of reaching the ceiling cap of two million five
hundred thousand Deutsche Mark; which limit had reached in the
year 2002 itself. It was further submitted that the transfer of
technology of the various models of WTG's in favour of the
Appellants-herein was pursuant to the stipulated contractual
obligations upon the Claimants (Respondents-herein) under the
TKHA and STKHA.
65. The Tribunal held that the issue was required to be
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 48 jt-comap-315, 314 & 316 -19.doc
answered essentially upon the construction of the terms of the
TKHA and STKHA itself. However, it would also be permissible
to look into the terms of the SHA in order to ascertain if they
throw light upon the nature of rights under the TKHA. It was
observed that the SHA was simultaneously executed by the parties
on 12-01-1994 along with the TKHA as part of the same
transaction. Reference to the term-'license' found at various
junctures in the agreements was noticed. The Tribunal refused to
look into the contents of documents which comprised the views of
the parties at the stage of negotiations preceding the execution of
the TKHA. The Tribunal observed that negotiation of a contract
is an iterative process in which only the final contract represents
the concluded intention of the parties. With regard to the expert
evidence on the regulatory background led by the parties, the
Tribunal was pleased to observe that it derived no assistance
therefrom. It appeared that there seemed no published guideline
to unequivocally indicate that outright transfer of technology was
a sine qua non for approval to be accorded by the RBI. The
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 49 jt-comap-315, 314 & 316 -19.doc
Tribunal noted that reported decisions of various Courts had been
referred before it which would indicate that the Court had no
hesitation in arriving at the conclusion that an agreement by which
a foreign company licensed an Indian company to use know-how
for a limited period was not an outright sale of property and that
the payments received by the foreign company were in the nature
of royalty rather than a capital receipt for the transfer of an
intangible asset. There was no suggestion of any regulatory
obstacle to this conclusion.
66. Upon adverting its consideration primarily to the
provisions comprised in the agreements themselves, the Tribunal
concluded that the TKHA contemplated a license to use the
technical know-how of the technology comprised therein,
however, the same was not limited for a period of 10 years as
suggested by the Claimants (Respondents-herein). It was held that
that the right to utilise the technical know-how transcended
beyond the period of expiry of the TKHA. The Tribunal fortified
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 50 jt-comap-315, 314 & 316 -19.doc
its conclusion in this regard by citing Article 5.5 of the TKHA,
inter-alia, which obliged the Claimant (Respondents-herein) to
ensure supplies of Electronic Control Components to WWIL. The
Tribunal observed that the fact that WWIL was given a right to
buy the components would necessarily entail that it must have the
right to manufacture the WTG's in which they would be used.
67. The Tribunal, however, repelled the contention of the
Appellants-herein that the TKHA and the STKHA enwombed
within its fold the right to manufacture E-48 and E-53 models of
the WTG's. It had been contended on behalf of the Appellants-
herein that the STKHA had contemplated supply of atleast two
other ranges/models in addition to E-26, E-30 and E-40. It was on
strength of this recital comprised in STKHA that the Appellants
staked the claim to manufacture E-48 and E-53 as a matter of
right. It was observed by the Tribunal that the transfer of
technology for E-33, E-48 and E-53 models of WTG's was
initiated by Enercon GmbH only after the expiry of the TKHA
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 51 jt-comap-315, 314 & 316 -19.doc
and STKHA in January 2004. The said transfer was made in
anticipation of a fresh agreement that would be formalised
between the parties after negotiations. The Tribunal held that the
right to receive technical know-how and manufacture atleast two
other ranges/models stood satisfied upon the receipt of technical
know-how of E-40/644/E2, E-40/644/E3B and E-40/644/E2B,
as explained by Mr. Kettwig in his evidence. Further, the Tribunal
placed reliance upon Mr. Yogesh Mehra's letter dated 17-10-2008
wherein he listed each of the E-40's separately as a model for
which technology had been supplied to WWIL. The position was
similarly stated by him in the draft of the new TKHA prepared by
him and shared with Enercon GmbH on 14-10-2004.
CLAIMS UNDER THE IPLA
68. The Tribunal observed that WWIL did not comply
the terms of IPLA. However, on 22.08.2007 royalties to the tune
of 986,399.88 pounds were remitted for the period 01.10.2006 to
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 52 jt-comap-315, 314 & 316 -19.doc
31.12.2006. Similarly, further royalties to the tune of 1.64 million
pounds were transmitted to Enercon GmbH on 16.10.2008 in
respect of the period 01.01.2007 to 31.03.2007, and 570,000
pounds were remitted in respect of the period from 01.04.2007 to
31.12.2007. On 14.11.2009, WWIL made a last payment of
royalties in the sum of 2,114,852 pounds. It was however
submitted by the Claimants (Respondents-herein) that the
payments were not accompanied by Statement of Accounts/books
and thus there were no means to verify if the royalties had been
paid appropriately. It was the claim of the Appellants-herein that
the said royalties were not payable and were transmitted under
bonafide mistaken belief. It is in this view of the matter that they
counterclaimed for repayment. They attempt to explain that the
said payments were not made pursuant to the IPLA, which was
never executed to bind the parties. It was contended that the
monies were transmitted pursuant to the obligations perceived by
WWIL under the Agreed Principles.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 53 jt-comap-315, 314 & 316 -19.doc
69. The Tribunal observed that after termination of IPLA,
the Claimant (Respondents-herein) were entitled to damages for
wrongful use of its Intellectual Property and Technology. The
royalty which WWIL had agreed to pay was the best measure for
the loss occasioned to the Claimants (Respondents-herein).
70. The Tribunal observed that Appellants own expert-
Mark Taylor assessed the total of royalties which fell due from the
inception of IPLA until 08.09.2015 using the IPLA method of
calculation (but without interest) to be 62.5 million pounds. The
Tribunal noticed that in fact, the said figure was more than the
amount assessed by the expert witness produced by the Claimants
(Respondents-herein). The expert witness produced by the
Claimant, Nicolas Good, assessed the amount due to be 63.1
million pounds together with interest. The Tribunal noted that the
Claimants (Respondents-herein) were content to accept the
amount assessed by their own expert witness even though it was
substantially less than the amount computed by the expert witness
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 54 jt-comap-315, 314 & 316 -19.doc
produced by the Appellants-herein.
71. The Tribunal also observed that at the relevant time,
WWIL was only manufacturing E-53 WTG. There was no dispute
that the said product was being manufactured by the Technical
Know-How provided by Enercon GmbH. The Tribunal was
pleased to grant injunctive relief against WWIL for manufacturing
the said WTG. The Tribunal was pleased to direct WWIL to
return the documents and other materials containing the
confidential technology as defined in the IPLA.
CLAIM FOR GOODS SOLD AND DELIVERED
72. Before the termination of IPLA, Enercon GmbH
supplied WWIL with components and raw materials upon its
standard Terms and Conditions. The Tribunal observed that it had
not been disputed that in May 2008 WWIL owed Enercon
GmbH 19,025,296.38 pounds for these supplies.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 55 jt-comap-315, 314 & 316 -19.doc
COUNTERCLAIM
73. The Appellants-herein set up a counterclaim before
the Arbitral Tribunal alleging breach of contract by the Claimants
(Respondents-herein) in failing to supply parts and raw materials
ordered by WWIL. The breaches are alleged to have occurred (a)
between 16.02.2007 and third week of March 2007 (b) between
13.07.2007 and December 2007. It was further contended that
even when supplies were resumed pursuant to directions passed by
the Bombay High Court by an interim Order dated 31.10.2007,
the said supplies were deliberately mismatched. It was submitted
that as a result of suspension of supplies and mismatching of parts,
WWIL was able to make and sell fewer WTGs than it would have
done if Enercon had complied with its contractual obligations. It
was claimed that the contribution which the additional sales would
have made to the revenue during the first spell of disruption of
supplies was estimated to be Rs. 43 crores and Rs. 429 crores for
the second.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 56 jt-comap-315, 314 & 316 -19.doc
SUSPENSION OF DELIVERIES
74. The Tribunal observed that the TKHA was no longer
in force and had been replaced by the IPLA. There was no specific
reference to a failure to deliver Electronic Control Components,
for which Enercon GmbH was saddled with a positive contractual
obligation to ensure supplies. It was held that with respect to other
parts and raw materials there was no pre-existing contractual
obligation to ensure supply. The Tribunal analysed the mechanism
of processing orders that was in place at Enercon GmbH. It was
observed that no contract was created until the purchase order had
been accepted. In the case at hand, the grievance of the
Appellants-herein was that the purchase orders had not been
accepted by the Claimants (Respondents-herein) rather than the
Claimants having failed to honour them. The Tribunal further
observed that a prior discussion of production plans between
parties assumed a mere moral commitment to use their best
endeavours to enable them to be carried into effect. However, the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 57 jt-comap-315, 314 & 316 -19.doc
same did not fasten any contractual liability on either side. The
production plan was a plan to which the parties hoped to adhere
but not a contract for the sale of goods. In view of the said reasons,
the Tribunal opined that the two spells of suspension of deliveries
in the year 2007 were not breaches of contract.
MISMATCHED DELIVERIES
75. Apropos, the allegation of deviousness on part of the
Claimant (Respondents-herein) to deliberately mismatch the
deliveries, it was observed by the Tribunal that perusal of
correspondence revealed that the Appellants-herein were
themselves reluctant to assist the Claimants (Respondents-herein)
when a query had been posed to remedy the situation. Therefore,
the claim in this regard was rejected.
TORT CLAIMS
76. In the defence and counterclaim, the Appellants-
herein had alleged that by suspending deliveries and certain other
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 58 jt-comap-315, 314 & 316 -19.doc
actions, Claimants (Respondents-herein) had intentionally caused
WWIL loss by unlawful means and intimidation. The Tribunal
observed that no evidence had been led in this regard, and the
claims were not mentioned by the Appellants-herein at the hearing
or in closing submissions. The Tribunal assumed that the same
had been abandoned.
SAP SYSTEM
77. Enercon had a computerised data-processing system
(SAP system) on a server in Aurich which was used by all its
subsidiaries to maintain their records, each having access to its own
information. The Appellants-herein had alleged that there was a
three day interruption in August 2007. Upon termination of
IPLA, WWIL was disconnected from the server. It was contended
that this was a malicious act to cause harm to WWIL. The
Claimants (Respondents-herein), on the other hand, submitted
that the Mehra Directors were abusing the system by attempting
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 59 jt-comap-315, 314 & 316 -19.doc
to obtain information about Enercon's worldwide activities. The
Tribunal observed that there was no evidence of any particular loss
occasioned by such disconnection. Further, the merits of the
dispute were not explored by the parties. Under such
circumstances, the Tribunal chose not to render any findings on
this issue.
REPAYMENT OF ROYALTIES
78. The Tribunal held that it had already adjudged that
royalties were payable by the Appellants-herein. Therefore,
counterclaim for return of royalties was rejected.
CLAIMS AGAINST MEHRA DIRECTORS
79. The Claimant (Respondents-herein) contended that it
was illegally ousted from the management of WWIL in as much as
it was being denied its rights in the governance of WWIL,
contrary to the terms of the SHA. No prior notice of meetings
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 60 jt-comap-315, 314 & 316 -19.doc
was dispatched as required by the agreement. Further, its consent
was not sought with respect to 'reserved matters'. It was further
contended that it was not allowed to appoint an Auditor as
contemplated under the Agreement, and no information with
regard to the affairs of WWIL was shared. Other instances of
usurpation of power by Mehra Directors were also illustrated. It
was also claimed that the Mehra Directors breached the fiduciary
duties under the SHA and company law by effecting transfers of
value and confidential technology from WWIL to companies
owned/controlled by the Mehra directors. A list of 37 such
companies and partnerships owned/controlled by the Mehra
Directors were annexed to the Statement of Claim.
80. In this regard, the Appellants-herein pressed
jurisdictional objections with regard to the arbitrability of these
claims as the same were overlapping and also pending adjudication
before the Company Law Board.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 61 jt-comap-315, 314 & 316 -19.doc
81. The Tribunal observed that the judgment of the
Supreme Court of India dated 14.02.2014 unequivocally
mandated that all disputes arising from the SHA, inter alia, were
referred for arbitration. The Tribunal accepted the contention of
the Appellants-herein that the issues raised by the Claimants
(Respondents-herein) may indeed overlap with the issues pending
adjudication before the Company Law Board. However, it was
observed that it was a matter of procedural discretion, whether to
await the decision of the Company Law Board. The Tribunal
noticed the delay which had already been occasioned in
adjudicating these disputes. It was held that it would be unjust to
the parties not to proceed with the mandate given by the Supreme
Court by awaiting the outcome of proceedings before the
Company Law Board.
82. With respect to the allegations of having being ousted
from the management of the affairs of WWIL, it was contended
on behalf of the Appellants-herein that the Claimants
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 62 jt-comap-315, 314 & 316 -19.doc
(Respondents-herein) had rather abdicated their responsibilities by
not attending meetings. Thus, the right of notice to such meetings
stood waived. It was observed that it had not been demonstrated
that Enercon GmbH was served with prior notice of meetings and
yet its representatives consciously chose not to attend the
meetings. The Tribunal did not accept the extreme proposition
propounded by the Appellants-herein that the express obligations
under the SHA could be circumvented by inferring a waiver from
the conduct of the other party to whom such obligation was owed.
83. The Tribunal observed that the Articles of
Associations (AoA) were mysteriously amended to remove Art.
170 (a) and substitute the same. The said provision dealt with
'reserved matters', which conferred a valuable right in favour of
Enercon GmbH in governance of WWIL. No valid special
resolution to amend the AoA was passed. The Tribunal found that
it was highly improbable that Enercon GmbH would have
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 63 jt-comap-315, 314 & 316 -19.doc
consented to a resolution cutting down its rights in respect of the
'reserved matters'.
84. The Tribunal also held that the Board resolution dated
26.04.2007 conferring wide powers on Mr. Yogesh Mehra,
including the power to commence legal proceedings that fell with
the ambit of 'reserved matters', was illegal. No notice of the
meeting had been given to Enercon. It was observed that the
Mehra Directors were not entitled to ignore the solemn
undertakings made to Enercon GmbH in the SHA. The plea
raised on behalf of the Appellants-herein that the powers were
exercised only in the interest of WWIL was negatived by the
Tribunal, and it was held that the parties may have different
perception of what is in the interest of the Company.
85. The Tribunal also observed that the since the
breakdown of relations between the parties, Enercon GmbH was
not consulted in the matter of appointment of Auditor and
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 64 jt-comap-315, 314 & 316 -19.doc
therefore they were unable to exercise its rights under Art. 8.2 of
SHA. It was held that Enercon had a right of access and
participation in an audit conducted by the Auditor which had in
effect been appointed by the Mehra's.
86. The Tribunal also accepted the contention of the
Claimants (Respondents-herein) that information with regard to
the functioning of WWIL was wrongly withheld by the
Appellants-herein and the said right stemmed from the SHA as
well as Company law.
87. Thereafter, the Tribunal proceeded to adjudicate upon
the last limb of issues which pertained to transfer of technology
and/or value to Vish Wind Companies/ Partnership.
88. The Tribunal noticed that in paragraphs 84 and 92.2
of the Statement of Claim, the Claimants (Respondents-herein) at
the very outset had pleaded their apprehensions in this regard.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 65 jt-comap-315, 314 & 316 -19.doc
However, in absence of information with regard to the affairs of
WWIL from which they have been ousted, the Claimants
(Respondents-herein) were then not in a position to substantiate
their claims.
89. The Tribunal traced the events as they dramatically
unravelled during the course of Arbitral proceedings. It emerged
that the Appellants-herein had not faithfully complied with the
directions of the Tribunal with regard to disclosure of documents
pertaining to transactions between WWIL and the Vayuu
Companies. On day 7 of the evidential hearing, the relevant
documents were ultimately produced.
90. It appeared from these documents that substantial
sums in the form of interest-free loans were doled out to these
Companies and LLPs from WWIL. Further, development rights
were purchased by WWIL from these companies and, in such
transactions, huge profits were earned by the Vish Wind
Companies/Partnerships that were owned/controlled by the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 66 jt-comap-315, 314 & 316 -19.doc
Mehra's.
91. In view of this fresh material that had come on record
during the course of evidential hearings, parties were permitted to
lead further evidence on this issue.
92. The Tribunal observed that the Vish Wind
transactions were a breach of express terms of Art. 4 of the SHA.
The transactions required the consent of Enercon representative.
Instead, Enercon was not even given notice of the transactions.
The Tribunal held that such conduct also amounted to breach of
fiduciary duty to act in good faith. The evidence led by the
Appellants-herein to justify the valuations of these transactions
was not accepted. The Tribunal did not accept the explanation
offered by Mr. Mehra that WWIL did not embark upon the task to
itself develop rights and rather chose to purchase them as it would
have caused distractions from the core activity of WWIL. The
Tribunal further observed that the acts of Mehra directors fell foul
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 67 jt-comap-315, 314 & 316 -19.doc
of the mandate of Section 88 of Indian Trusts Act, 1882. The
Mehra directors had a conflict of interest and duty in as much as
they made profit by sale of development rights to WWIL in which
Enercon had a majority interest, whereas, their family exclusively
owned/controlled the companies/partnerships with whom such
transactions for purchase of development rights were made. The
Tribunal noticed that according to accounts Vish Wind had no
employees, business and virtually no money. It financed the
purchases of land with loans from WWIL.
93. The Tribunal rejected the objection raised by the
Appellants-herein that the claim in respect of Vayuu Companies
was not sufficiently pleaded. The Tribunal observed that concrete
evidence emerged towards the end of the hearing in view of the
fact that the Appellants-herein had themselves breached the earlier
Order of the Tribunal directing supply of relevant documents.
Hearing was kept open to enable the Appellants-herein to counter
the allegations of the Claimants (Respondents-herein). Sufficient
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 68 jt-comap-315, 314 & 316 -19.doc
opportunity was given to lead evidence, and the Appellants availed
of such opportunity by tendering evidence of two experts, namely,
Mr. Kaushik Khona and Mr. D. Vaidyanathan.
94. The Tribunal noticed that the Claimants
(Respondents-herein) sought damages from Mehra directors and
claimed that the same be paid directly to Enercon GmbH. The
Tribunal, however, observed that it was WWIL which was most
immediately affected by the breaches committed by the Mehra
directors. Therefore, the Tribunal held the Mehra directors
accountable to WWIL for the 97 million pounds profit, which
Vish Wind made on the development rights transactions.
95. The Tribunal did not proceed to make any award with
respect to Vayuu Renewable Energy (Purna) Pvt. Ltd. in view of
the fact that there was no evidence to demonstrate that Purna and
its subsidiaries had yet succeeded in attracting any business.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 69 jt-comap-315, 314 & 316 -19.doc
96. The Tribunal refused to grant costs in favour of the
Claimants (Respondents-herein) for expenses incurred on
litigation before the commencement of arbitration. The Tribunal
also negatived the contention of the Claimants that the Mehra
Directors ought to be held personally liable for the debts of
WWIL stemming from failure to pay royalties and price for the
goods supplied.
97. The Tribunal was pleased to direct that Enercon
GmbH was entitled to the unredacted documents supplied by the
Appellants-herein under Procedural Order No. 1 and therefore
LCIA was directed to release them in favour of the Claimants
(Respondents-herein). The said documents contain information
with regard to WWIL's suppliers and components manufactures.
98. In paragraph 316, the Majority concatenated its
conclusions on various issues which had arisen for its
consideration. The same are summarised for the sake of
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 70 jt-comap-315, 314 & 316 -19.doc
convenience. The Tribunal held that the Claimants (Respondents-
herein) were entitled to the declaration that the IPLA was valid
and binding but lawfully terminated on 08.12.2008 upon which
WWIL ceased to be entitled to use the technology of the
Claimant. The Claimants were entitled to payment of arrears of
Royalty and outstanding monies due for the parts/materials
supplied to WWIL. Mehra Directors were required to account for
97 million pounds to WWIL for the profits on sale of
development rights wrongly diverted to Vish Wind. The
Claimants were entitled to injunctive relief to restrain the Mehra
Directors from preventing them to exercise their rights under the
SHA to participate in the management of the Company, have
access to information, and appoint the Auditors. It was held that
the Claimants were entitled to injunctive relief to restrain the
Mehra Directors from causing WWIL to take actions within the
reserved matters of Art. 4 of SHA.
99. With regard to the issue of payment of costs of
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 71 jt-comap-315, 314 & 316 -19.doc
arbitration, the Tribunal held that the Claimant (Respondents-
herein) had substantially prevailed on merit and were entitle to
cost. It was however clarified that this was not a case in which the
Tribunal would award the Claimants (Respondents-herein) costs
on full indemnity basis. In paragraph 330 of its Award, the
Tribunal fixed the reasonable cost of arbitration to be 3,794,970
pounds which was payable in favour of Claimants (Respondents-
herein) within 28 days.
100. In paragraph 331 of the Award, the Tribunal
crystallised its final directions and the sums of monies which the
Appellants-herein were liable to be pay in terms of the findings.
We reproduce the same for the sake of clarity.
"(1) The Tribunal declares:
(a) The IPLA executed by the parties thereto on
30 September 2006 was intended to create legal relations and was a valid and binding contract;
(b) The Mehra directors caused WWIL to repudiate liability under the IPLA and to commit
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 72 jt-comap-315, 314 & 316 -19.doc
breaches of the IPLA amounting to a repudiation thereof.
(c) The Claimants accepted the repudiation and terminated the IPLA on 8 December 2008;
(d) WWIL was indebted to Enercon in respect of
(a) royalties due under the IPLA until its date of termination and (b) damages for wrongful use of its intellectual property and technology after termination until 8 September 2015 in the sum of €55.2 million and interest;
(e) Pursuant to clause 13(1)(b) of the IPLA, WWIL is not entitled to use or exploit the confidential Technology disclosed by the Claimants to WWIL during or before the subsistence of the IPLA and is obliged to return to Enercon documents or materials which contain such Technology
(f) WIL is indebted to Enercon for components and materials sold and delivered before May 2008 in the sum of €19,025,296.38 and interest;
(2) The Tribunal orders WWIL -
(a) To pay to Enercon
(i) €55,200,000 in respect of royalties due under the IPLA together with interest thereon
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 73 jt-comap-315, 314 & 316 -19.doc
in the sum of €7.9 million until 8 September 2015 and thereafter at the rate of 3% over European Central Bank rate until the date of this Award;
(ii) €19,025,296.38 in respect of components and materials sold and delivered together with interest in the sum of €5.9 million until 31 March 2016 and thereafter at the rate of 3% over European Central Bank rate until the date of this Award;
(b) To return to Enercon the documents and other materials containing the
confidential Technology (as defined in the IPLA) disclosed to WWIL pursuant to the TKHA and IPLA;
(c) To allow Enercon, pursuant to clause 6.1(b) of the IPLA, to inspect its books and records and take relevant copies.
(3) The Tribunal orders the Second and Third Defendants: (a) Not to prevent or obstruct Enercon or
its nominated directors from exercising their rights under the SHA or as directors to -
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 74 jt-comap-315, 314 & 316 -19.doc
(i) Receive notice of board and company meetings; (ii) Obtain information about the affairs of the company; (iii) Secure the appointment of auditors by the company in general meeting; (b) Jointly and severally - (i) to pay to WWIL the sum of INR 6,772,456,570, being the profit made by Vish Wind on the sale of allotment rights to WWIL in the years ending 31 March 2011 and 2012 together with interest thereon at the rate of 3% over European Central Bank rate from those dates until the date of this Award. (ii) To pay to the Claimants their legal and other costs in the sum of €3,794,970 4. All other claims and counterclaims are dismissed. 5. From the date of the award, all sums
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 75 jt-comap-315, 314 & 316 -19.doc
payable will carry interest in accordance with section 31(7)(b) of the Indian Arbitration and Conciliation Act 1996."
ANALYSIS OF MINORITY AWARD
101. Justice R.V Raveendran expressed his inability to agree
with the views of the majority with regard to four issues namely,
(i) That IPLA is a completed contract and not a
draft;
(ii) That WWIL is liable to pay a sum of Euro 55.2
million towards Royalty and Euro 7.9 million towards
interest thereon; and
(iii) That Yogesh Mehra and Ajay Mehra were
accountable to WWIL for Euro 97 million, towards
the profit on development right transactions made by
M/s. Vish Wind Infrastructure LLP.
(iv) That Yogesh Mehra and Ajay Mehra were
liable to expend the costs of the proceedings rather
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 76 jt-comap-315, 314 & 316 -19.doc
than WWIL.
WHETHER IPLA IS A CONCLUDED CONTRACT OR A DRAFT
102. The learned Arbitrator took notice of the fact that the
Claimants (Respondents-herein) had deliberately filed the
document titled "Agreed Principles" separate from the IPLA
despite the fact that the document titled "Agreed Principles"
referred to the draft IPLA as an enclosure. It was observed that the
Appellants-herein had in fact filed the "Agreed Principles" along
with the entire bundle of enclosures which included the note(s) of
Deloitte Haskins and Sells (DHS) and the IPLA. The conduct of
the Claimant (Respondents-herein) was chastised by observing
that the apparent reason for suppressing the two attachments to
the Agreed Principles was that if they were produced they would
support the case of the Appellants-herein that the IPLA was a
mere draft which was enclosed along with the document titled
'Agreed Principles' and would militate against the stand of the
Claimant (Respondents-herein).
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 77 jt-comap-315, 314 & 316 -19.doc
103. The learned Arbitrator noticed that the
correspondence exchanged between the parties since 15.09.2006
clearly indicated that there was no consensus between the parties
in regard to the terms of the IPLA. It is in this view of the matter
that Dr. Wobben and Mr. Mehra met on 29-30 September 2006
in Germany to find a solution to the impending issue of
computation of royalty and certain other aspect relating to IPLA
amongst other issues relating to sale of shares. The discussions for
three long hours on 29.09.2006 did not bear any fruit as Mr.
Mehra did not agree to the terms of draft IPLA. Thus, Dr.
Wobben asked Mr. Kettwig to join Mr. Mehra and prepare the
Agreed Principles in regard to the various pending issues so that it
could be executed on 30.09.2006. It was observed that if the issue
regarding IPLA had been creased out during the discussions on
29.09.2006, there would be no need for the Agreed Principles to
have been drawn and executed by the parties. Significance was
attached by the learned Arbitrator to the fact that the document
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 78 jt-comap-315, 314 & 316 -19.doc
titled Agreed Principles referred to the IPLA as a draft.
104. It was further noticed that the disputed document in
question contained several indications which probablised that it
was only a draft. There was a blank space in the title portion at
page 1 where the parties were described. Similarly, blank spaces
were also observed in clause 15/Page 23 relating to delivery of
notice. Further certain particulars were left blank with regard to
name and address of the person to whom notices addressed to the
licensor should be endorsed. Blank spaces could also be observed
in the particulars of Respondent licensee. The learned Arbitrator
was pleased to observe that it would militate against the natural
course of probabilities that a final document which was ready to be
executed would contain numerous blank spaces considering big
companies like Claimants (Respondents-herein) are involved and
are ably assisted by their legal teams.
105 It was also highlighted that the IPLA refers to certain
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 79 jt-comap-315, 314 & 316 -19.doc
annexures with regard to trademark and patent portfolio amongst
others. However, such annexures were not produced.
106. The learned Arbitrator also noticed that the opening
recital indicates that the agreement was entered into at Aurich on
17.09.2006 whereas it is the case of the Claimant (Respondents-
herein) that it was executed on 30.09.2006. It was observed that if
this document was intended to be the final IPLA, it was expected
that the date of the document would have been corrected as
30.09.2006.
107. It was held that the question was not whether the
blank spaces in the agreement and absence of annexures were with
reference to material terms or not. In the view of the learned
Arbitrator, such facets probabalised the conclusion that the
document was a mere draft, especially in light of the fact that the
agreed principles described it as a draft IPLA.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 80 jt-comap-315, 314 & 316 -19.doc
108. With regard to the circumstance that the parties had
appended their full signatures on the last page of the disputed
document along with their initials, it was observed that the
explanation tendered by Mr. Mehra in his evidence that he merely
followed the suit and appended his signatures following Dr.
Wobben, merited acceptance.
109. The correspondence and conduct of the parties
subsequent to the execution of the Agreed Principles on
30.09.2006 were also taken into consideration to fortify the
conclusion that the disputed document was a mere draft. The
learned Arbitrator referred to an email dated 18.10.2006 sent by
Ms. Fritsch Nehring to Mr. Mehra wherein she stated that that the
IPLA was in consonance with the Agreed Principles and any
amendment of IPLA was not required. It was observed that if the
IPLA had been already executed as a concluded contract, there was
no requirement for Ms. Fritsch Nehring to persuade Mr. Mehra
that the amendments to IPLA in terms of Agreed Principle was
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 81 jt-comap-315, 314 & 316 -19.doc
not required.
110. It was also noticed that Mr. Mehra in his electronic
mail dated 03.11.2006 expressly pronounced that the IPLA was a
draft which contains certain inconsistencies. However, the
Claimants (Respondents-herein) did not denounce this assertion
in their response dated 24.11.2006. Rather the tenor of the reply
probablised the case of the Appellants-herein. The learned
Arbitrator extracted the relevant portion of the said response,
which we reproduce hereunder:
"Thema: Final IPLA, shareholding and other successive agreements Dear Yogesh, First I have to apologise for the delay in sending you the outstanding drafts of the agreements mentioned above. At present, there are still some discrepancies in the contract compared to the agreed principles which we have to discuss internally..."
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 82 jt-comap-315, 314 & 316 -19.doc
111. Thereafter the Learned Arbitrator proceeded to
analyse the ocular evidence led by the parties in support of their
claims with regard to what transpired on 29-30 September 2006.
At the outset, it was noticed that Ms. Nicole Fritsch Nehring was
not present during the meetings whereas Mr. Kettwig was only
present during part of the discussions. The evidence tendered by
Mr. Kettwig was found to be vague, uncertain and inconsistent. It
was noticed that he could not remember many details. The
evidence tendered by this witness was found contrary to
documentary evidence i.e. Agreed Principles. It was observed that
Mr. Kettwig had no explanation why Dr. Wobben signed the
Agreed Principles on 30.09.2006 agreeing to change the draft
IPLA to the satisfaction of the parties if the IPLA had been finally
concluded. It was not the case of the Claimant that on 30.09.2006
the Agreed Principles was signed and thereafter the draft IPLA was
corrected to the satisfaction of Mr. Mehra, and then the final
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 83 jt-comap-315, 314 & 316 -19.doc
version of IPLA was signed on 30.09.2006 itself. On the other
hand, the learned Arbitrator found evidence of Mr. Mehra as to
what transpired on 29-30 September 2006 to be more probable,
logical and in consonance with the documentary evidence.
112. The learned Arbitrator negatived the contention of
the Claimants (Respondents-herein) that in his emotional letter
dated 30.09.2006, Mr. Mehra admitted to have signed the
agreement and therefore the hypothesis of IPLA having been
merely initialled as a draft was debunked. It was observed that Mr.
Mehra was a layman and loosely referred to the Agreed Principles
as the Agreement.
113. An adverse inference was also drawn against the
Claimants (Respondents-herein) considering their conduct in
arbitrarily novating the initial offer to purchase additional
shareholding of WWIL to the tune of 6% Equity Shares for a sum
of Euros 40 million.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 84 jt-comap-315, 314 & 316 -19.doc
COMPUTATION OF ROYALTY/DAMAGES
114. It was observed that since it had been held that the
IPLA was not executed as a concluded contract capable of binding
parties, therefore it necessarily follows that the terms of the draft
IPLA would not govern the royalty.
115. The learned Arbitrator held that Enercon (India)
Ltd./WWIL continued to use the technology provided by the
Claimants (Respondents-herein) and was therefore liable to pay
royalty in terms of DHS formula agreed under the Agreed
Principles, from the period commencing 30.09.2006.
116. The evidence tendered by expert witnesses produced
by both the sides with respect to computation of royalty was
analysed by the learned Arbitrator and it was opined that the
report of Mr. Nicholas Good; the expert witness produced by the
Claimant (Respondents-herein), was liable to be accepted in so far
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 85 jt-comap-315, 314 & 316 -19.doc
as the calculation of quantum is concerned.
117. It was concluded that upon adjustments of the
payments already made, the Appellants-herein were liable to pay
Euro 39.8 million as total amount due towards royalty along with
interest upto 30.09.2015.
DIRECTIONS TO MEHRAS' TO PAY WWIL EURO 97 MILLION IN REGARD TO SALE OF DEVELOPMENT RIGHTS BY VISH WIND
118. At the outset, the learned Arbitrator noted that the
reliefs sought by the Claimants (Respondents-herein) in the
Statement of Claim did not include a prayer for payment of any
sum by the Mehra brothers in favour of WWIL. All reliefs sought
in the statement of claim were proposed to be in favour of the
Claimants themselves. Further, there was no indication that the
present claim is a derivative action by Enercon GmbH as a
shareholder for grant of relief in favour of WWIL from Mehras.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 86 jt-comap-315, 314 & 316 -19.doc
119. It was also observed that in absence of pleadings, no
amount of evidence could be looked into to grant reliefs that were
not expressly sought. It was held that the Mehra brothers did not
have the opportunity to submit their defence in regard to the
proposed relief. It was highlighted that there was no averment for
sale of development rights in the Statement of Claim.
120. The learned Arbitrator held that if the claimants
(Respondents-herein) became aware of the development right
transactions belatedly, they ought to have sought amendment of its
Statement of Claim. No amount of proof could substitute the
pleadings, which are the foundation of a claim by a litigating party.
Reliance was placed upon the decision of the Supreme Court
reported as (1995) 5 SCC 612 'Abubakar Abdul Inamdar v.
Harun Abdul Inamdar'. It was observed that the statement of
claim merely comprised the averment of an apprehension that
confidential technology was being unauthorisedly passed on to the
Vayuu Companies.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 87 jt-comap-315, 314 & 316 -19.doc
121. The learned Arbitrator did accept that some material
disclosed during evidence gave rise to an inference of impropriety
on the part of Mehra's, however, in absence of pleadings, due
opportunity for letting in evidence and arguments on the specific
issue, liability for a huge sum of Euro 97 million could not be
fastened.
122. In paragraph 58 of the Award, the learned Arbitrator
expressed his respectful agreement with the views of the majority
on all other issues. However, with the regard to the directions of
payment of costs, the learned Arbitrator was of the opinion that
WWIL ought to be liable to pay such costs and not the Mehra
brothers.
123. The Conclusions and consequent directions recorded
in the dissent were crystallized in paragraph 59 of the Award.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 88 jt-comap-315, 314 & 316 -19.doc
"59. In view of the above, I record my dissent to the Award by the majority and make the following Award:
(a) I declare that the 'IPLA' relied upon by claimants is not a finally executed IPLA, but a draft enclosed to Agreed Principles which was intended to be finalised and signed after certain pending issues were sorted out;
(b) I declare that as first respondent continued to use technology, it is liable to pay royalty in terms of the DHS formula agreed under the 'Agreed Principles' from 30.9.2006; and
(c) WWIL shall pay to Enercon, Euro 35.2 million towards royalty and Euro 4.6 million as interest upto 30.9.2015, and thereafter, simple interest at the rate of 3% over European Central Bank rate until date of Award.
(d) Agreeing with the majority, I direct that WWIL shall pay to Enercon, Euro 19,025,296 in respect of components and materials sold and delivered, with interest of Euro 5.9 million till
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:58 ::: Jdk/pdp 89 jt-comap-315, 314 & 316 -19.doc
31.3.2016 and thereafter, simple interest at the rate of 3% over Europoean Central Bank rate until the date of the Award;
(e) Agreeing with the majority, I direct that WWIL shall return to Enercon the documents and other material containing the confidential technology disclosed to WWIL by Enercon;
(f) Agreeing with the majority, I order that respondents 2 & 3 not to prevent or obstruct Enercon or its nominated Directors from exercising their rights under the SHA or as Directors to (i) receive notice of Board and company meetings; (ii) obtain information about the affairs of the company; and (iii) secure the appointment of auditors by the company in General Meeting.
(g) The amounts awarded shall carry simple interest from the date of Award till date of realisation at the rate of 3% over European Central Bank Rate.
(h) I direct WWIL to pay to the claimants, their legal and other costs in the sum of Euro 3,794,970
(i) Agreeing with the majority, all other claims and counter-claims are dismissed. "
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 :::
Jdk/pdp 90 jt-comap-315, 314 & 316 -19.doc
ANALYSIS OF THE IMPUGNED JUDGEMENT
124. The Arbitral Award was assailed before this Court by
preferring three petitions under Section 34 of the Arbitration and
Conciliation Act, 1996. The said petitions were dismissed by a
common judgment dated 14.12.2018 passed by the learned Single
Judge of this Court.
125. Perusal of the judgment reveals that it was strongly
urged by the Petitioners (Appellants-herein) that the award was
liable to be set aside in view of the fact that opportunity was not
granted to the parties to make oral submissions upon conclusion of
evidence. It was submitted that the approach adopted by the
learned Tribunal was violative of the principles of natural justice
and was in breach of Section 24(1) of the Arbitration and
Conciliation Act, 1996. Thus, the award was said to have been
passed in a manner which is opposed to the fundamental policy of
India and warranted interference.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 91 jt-comap-315, 314 & 316 -19.doc
126. Apropos, the relief granted in respect of purchase of
development rights from Vish Wind, it was contended that the
Arbitral Tribunal adopted an approach which was patently
perverse and opposed to the quintessential norms of fair play. The
issue was not sufficiently pleaded yet the Tribunal proceeded to
grant relief on the strength of the fact that some material had
emerged in evidence. It was highlighted that the relief granted was
not even expressly sought and the Tribunal exceeded its
jurisdiction to mould relief.
127. The Petitioners also reiterated their submissions as
made before the Tribunal that the IPLA was not a concluded
contract capable of binding the signatories but was a mere draft
that had been initialled and signed merely for the purpose of
identification.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 92 jt-comap-315, 314 & 316 -19.doc
128. Before adverting its consideration to the above-noted
submissions, the Court elaborately set out the factual backdrop of
the dispute and the spate of litigation initiated between the parties
before different forums.
129. While dealing with the contention of failure to grant
an oral hearing, the Court took note of the calendar of proceedings
before the Tribunal and proceeded to analyse the Procedural
Orders passed at each stage. The Court observed that it had been
made amply clear at the stage of passing Procedural Order No. 5
that closing oral submissions would be granted only if determined
necessary and could not be claimed as a matter of right. In this
regard, the dates 27-28 April 2016 were reserved for the purpose
of oral evidence with respect to the issue of Vish Wind
Infrastructure LLP and closing oral submissions, if any. The Court
extracted the transcripts of proceedings on Day 10 of the
evidential hearings, wherein, the learned Senior Counsel
appearing on behalf of the Petitioners was categorically intimated
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 93 jt-comap-315, 314 & 316 -19.doc
the course proposed by the Tribunal, and he approved of the same.
130. During the course of evidential hearings, the team of
lawyers representing the Petitioners sought discharge and
expressed their inability to continue to represent them. The
Tribunal modified its calendar on numerous occasions to
accommodate the newly engaged legal team.
131. Vide an e-mail dated 13.04.2016, the Tribunal
reminded the advocates for parties that closing submissions were
due to be filed on 22.04.2016 and the Tribunal would notify the
parties as soon as possible after receiving closing submissions
whether the Tribunal wishes to hear any oral submissions. If not,
the provisional arrangements for the oral hearings on 27-28 April
2016 would be cancelled. In response to this e-mail, the counsels
for the Petitioners herein sought further time to file closing written
submissions and reserved their right to apply to the Tribunal for
permission to make closing oral arguments after 30.06.2016.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 94 jt-comap-315, 314 & 316 -19.doc
However, since the closing written submissions were not
submitted promptly in accordance with the proposed schedule and
could be submitted after submitted only on 25.05.2016 after
seeking further extension of time, no opportunity was provided for
further oral hearing. The Court observed that it could not be
demonstrated that absence of an opportunity to advance closing
oral submissions occasioned any prejudice. It was held that the
approach of the Tribunal had by far been transparent.
132. The Court repelled the contention that the Tribunal
fell in error by proceeding to grant relief in absence of specific
pleadings. The Court observed that the Statement of Claim sets
out the loss caused to Enercon by the Mehra's by breach of their
duties under the SHA. Further, material evidence with regard to
Vish Wind transactions had only emerged belatedly during the
cross-examination of Mr. Mehra as the same had been suppressed
by the Petitioners. In view of such disclosure, the Tribunal while
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 95 jt-comap-315, 314 & 316 -19.doc
formulating Procedural Order No. 5 categorically alerted the
Petitioners that Vish Wind transactions would be an integral issue
to be adjudicated during the course of the proceedings and
evidence in this regard could be adduced. The Court observed that
the decision of the Supreme Court reported as 1966 2 SCR 286
'Bhagwati Prasadv.Chandramaul' was squarely applicable to the
case at hand. It was held by the Supreme Court that if a plea was
not specifically made and yet it was covered by an issue by
implication and the parties knew that the plea was involved in the
trial then the mere fact that the plea was not expressly taken in the
pleading would not disentitle a party from relying upon it if it is
satisfactorily proved by evidence. The test is whether the parties
knew that the matter in question was involved in the trial and
whether they did lead evidence about it. The Learned Single Judge
further observed that in the context of arbitration proceedings,
strict rules of pleadings as comprised in the Civil Procedure Code
would not apply with the same rigor as the Arbitral Tribunal is not
bound by the Code of Civil Procedure, 1908 in view of Section
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 96 jt-comap-315, 314 & 316 -19.doc
19(1) of Arbitration and Conciliation Act, 1996.
133. The Court held that the findings of the Tribunal that
the IPLA was a concluded contract could not be faulted. It was
observed that royalties were paid by the Petitioners, and if the
IPLA was not treated to have been binding, there would have been
no obligation to make such payments. The Court expressed a note
of caution that proceedings under Section 34 of the Arbitration
and Conciliation Act, 1996 were not akin to an appeal and do not
entail a review on merits of the dispute.
134. Further, the submission that the approach of the
Tribunal reeked with bias was merely noted to be rejected as the
Court found no justification for such an allegation.
135. We have carefully perused the Award passed by the
Arbitral Tribunal, including the dissent authored by Mr. Justice
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 97 jt-comap-315, 314 & 316 -19.doc
Raveendaran and also the impugned Judgment upholding the
majority Award. The raison d'etre forming the basis for the
conclusions has sought to be comprehensively culled out in the
preceding paragraphs. In light of the same, we now proceed to
note the submissions made before us.
SUBMISSIONS OF MR. SHYAM MEHTA, SENIOR ADVOCATE APPEARING ON BEHALF OF THE APPELLANT- AJAY MEHRA IN COMMERCIAL APPEAL NO. 314 OF 2019
136. Mr. Shyam Mehta, learned Senior Counsel ventured to
make submissions on two counts.
First, that the Arbitral Tribunal fell in grave error by
denying oral hearing upon the culmination of proceedings despite
a request having been made.
Second, that the relief granted by the majority
Arbitrators with respect to Vish Wind transactions was beyond the
scope of pleadings and the reliefs sought therein.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 98 jt-comap-315, 314 & 316 -19.doc
137. Apropos, the first proposition with respect to absence
of oral hearing it was submitted that the proviso to Section 24 (1)
of the Arbitration and Conciliation Act, 1996 mandates that the
arbitral tribunal shall hold oral hearings, at an appropriate stage of
the proceedings, on a request by a party. It was pointed out that
the only exception to this proviso is a specific agreement between
the parties not to hold oral hearings. It was thus submitted that in
the present case, there was no agreement by the Appellant's-herein
to exclude oral hearings.
138. Mr. Mehta drew attention of the Court to Procedural
Order No. 4, wherein the Arbitral Tribunal gave liberty to the
parties to apply for further hearings on oral closing submissions at
the discretion of the Tribunal. However, the said Procedural Order
recorded the disagreement on part of the Appellant's with the
aforesaid direction. It was submitted that the Appellant's had
unequivocally indicated their intention to request for further oral
hearings even after the filing of written submissions, as it was their
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 99 jt-comap-315, 314 & 316 -19.doc
understanding that it was open for them to do so.
139. With respect to the contents of the Procedural Order
No. 5 wherein the Arbitral Tribunal, inter alia, reserved 27-
28.04.2016 as dates for oral evidence and oral submissions, if any
were requested and if determined necessary by the Arbitral
Tribunal, it was submitted that the said Order was in the nature of
directions and could not be construed to contemplate any
agreement between the parties to not hold oral hearings. At best, it
was an agreement on the timetable to be followed.
140. Taking the argument forward, Mr. Mehta submitted
that Procedural Order No. 5, which was issued on 11.12.2015, is
required to be read with Procedural Order No. 4 issued on 26.11.
2015, wherein in Paragraph 8, a similar direction is comprised as
contained in Sr. No. 9 of Procedural Order No. 5. As highlighted
earlier, the note forming part of Procedural Order No. 4 clearly
records that the Appellants-herein desired an oral hearing to make
submissions although Enercon desired to leave this to the Arbitral
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 100 jt-comap-315, 314 & 316 -19.doc
Tribunal's discretion. Procedural Order No. 4 and Procedural
Order No. 5 were passed in close succession i.e. within a span of
merely fifteen days, and it could not be construed that the
Appellants had changed their stand during that period.
141. It was contended that at any rate, the Arbitral
Tribunal in its Order dated 26.05.2016 had not provided any
reason for refusing to hold an oral hearing. The Arbitral Tribunal
merely observes that the Act does not provide that the Arbitral
Tribunal shall hold as many hearings as a party may request and at
such times as a party may propose. The Arbitral Tribunal referred
to hearings held in December 2014 and November and December
2015. It was submitted that it was apparent that the Arbitral
Tribunal failed to appreciate the distinction between a hearing to
record evidence and a hearing to hear submissions / arguments of
the parties.
142. Mr. Mehta submitted that the Appellant's-herein
repeatedly pleaded and sought an oral hearing, however, they were
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 101 jt-comap-315, 314 & 316 -19.doc
denied the same. The requirement of oral hearing assumed all the
more significant considering the abstruse issues involved in the
case at hand, and the voluminous evidence led during the course
of proceedings. Furthermore, the Arbitral Tribunal proceeded to
adjudicate upon the issues which were not even pleaded and
therefore atleast a fair opportunity of closing oral submissions
ought to have been granted to also effectively raise an objection in
this regard.
143. It was highlighted that the Arbitral Tribunal vide e-
mails dated 14.02.2016 and 13.04.2016 had informed the parties
that it would decide whether or not to hold oral hearings only after
receiving their written submissions. By an email dated 18.02.2016,
the Advocates representing the Appellant's-herein informed the
Arbitrators that the new legal team would not be able to peruse the
voluminous record within the close deadline of 22.04.2016. It was
suggested that an oral hearing was necessary and if necessary, the
same could be held in Hong Kong. Curiously, on 20.04.2016 the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 102 jt-comap-315, 314 & 316 -19.doc
Arbitral Tribunal hastily cancelled the dates tentatively reserved
for oral hearings (27-28.04.2016) without considering the written
submissions, even before the scheduled date for filing written
submissions. Mr. Mehta urged that even assuming without
conceding that the parties had agreed that oral arguments would
be permitted only at the discretion of the Arbitral Tribunal, such
an agreement was necessarily premised on the Arbitral Tribunal
deciding on this aspect after a fair consideration of all relevant
factors including change in advocates and the Tribunal's own
declarations that it would determine the request for oral hearings
only after considering the parties written submissions. It was thus
submitted that the decision to refuse oral hearings was not arrived
at upon a determination having been made upon perusal of
written submissions. It appeared that the Arbitral Tribunal
cancelled the oral hearings solely on account of its own scheduling
constraints and its difficulty in finding appropriate dates.
144. It was highlighted that the learned Single Judge placed
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 103 jt-comap-315, 314 & 316 -19.doc
reliance on the transcripts of Day 9 and Day 10 of the evidential
hearings to hold that the learned Counsel for the Appellant's-
herein was made aware that the Arbitral Tribunal was not
committed to oral hearings. In this context, it was submitted that
the awareness exhibited by the learned Counsel to the course
proposed to be adopted by the Tribunal would not be sufficient to
clothe the same as a waiver to oral hearings which assumed the
character of a statutory right. The statement made by the learned
Counsel in a polite verbal interchange with the Arbitrator's ought
not to be construed as an agreement of waiver to exclude oral
hearing as contemplated in the exception to proviso to Section
24(1) of the Act.
145. While summing up his submissions on this aspect, Mr.
Mehta clarified that the fact that the Appellant's-herein repeatedly
applied/requested for oral hearing during the course of arbitral
proceedings did not imply that they accepted the course proposed
under the Procedural Order No. 5 and pursued the same by
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 104 jt-comap-315, 314 & 316 -19.doc
abdicating their statutory right of oral hearing by relegating the
decision to the discretion of the Tribunal. It was submitted that
such requests were made to the Tribunal in terms of the mandate
of Section 24 of the Act itself which requires such a formal request
to be made.
146. The next plank of submissions sought to be urged by
Mr. Mehta pertained to insufficiency of pleading with respect to
Vish Wind transactions of sale of development rights to WWIL on
which the Tribunal has proceeded to make an award. Linked with
this issue is also the grievance that the novel relief of directing the
Mehra brothers to recompense WWIL; a co-respondent at the
Arbitration was not even sought. The majority Award, inter alia,
directs the Mehra brothers to pay a sum of Rs. 677,24,56,570/- to
WWIL, towards profits allegedly made by Vish Wind
Infrastructure LLP on the sale of allotment (development) rights
to WWIL.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 105 jt-comap-315, 314 & 316 -19.doc
147. Attention of the Court was drawn by the learned
Senior Counsel to the Statement of Claim submitted by the
Claimants (Respondents-herein). It was submitted that perusal of
the Statement of Claim establishes that the damages sought against
the Mehra's were with regard to (i) the alleged wrongful
dissemination of the technical know-how (in relation to wind
turbine generators) of Enercon GmbH by WWIL and the
Mehra's; and (ii) the alleged breaches committed by the Mehra's
under the SHA, namely relating to no proper notice to Enercon
regarding board meetings, passing of board resolutions in respect
of reserved matters without Enercon's affirmative vote, etc. The
only mention of Vaayu Companies (including Vish Wind) in the
Statement of Claim is in relation to the alleged receipt or
exploitation by the Vaayu Companies, of Enercon's technical
know-how and the resultant transfer of value from WWIL to the
Vaayu Companies. There is no mention in the Statement of Claim
with regard to any purported wrongful profiteering by Vish Wind
by transfer of allotment / development rights to WWIL.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 106 jt-comap-315, 314 & 316 -19.doc
148. It was further highlighted that in prayer I (c) of the
Statement of Claim, Enercon GmbH sought damages and/or on
account of profits from the Mehra's for their alleged breaches of
the SHA and /or duties arising as a matter of Indian Law. It was
submitted that this was a vague prayer and is not supported by any
particulars, much less material particulars, in the Statement of
Claim. Prayer I(d) seeks an award against the Mehra's for payment
of all sums and damages and/or an account of profits that may be
ordered to be paid by WWIL. Thus, the relief claimed is of
payment by Mehra's to Enercon GmbH and not of any payment
to be made by Mehras to WWIL as finally granted.
149. Elaborating on his submissions, Mr. Mehta submitted
that the alleged damages claimed by Enercon are not quantified
either in the Statement of Claim or in any witness statement.
Accordingly, apart from not pleading any case for damages on
account of profits allegedly made by Vish Wind or the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 107 jt-comap-315, 314 & 316 -19.doc
quantification thereof, Enercon even failed to prove the same by
way of evidence. If loss was caused to WWIL, the effect of the
same on Enercon GmbH would at the highest be by way of a loss
in the value of the shareholding. There was neither any pleading
nor proof in this regard. The action initiated by Enercon GmbH
was not in the nature of a derivative action on behalf of WWIL
but was a proceeding in their personal capacity seeking damages
caused to them. In the absence of the requisite pleadings with
proper particularization, such proceedings could not have been
converted into a derivative proceeding leading to an award in
favour of WWIL against the Mehra's.
150. It was contended that though by Procedural Order
No.5, the Arbitral Tribunal granted an opportunity to the parties
to lead evidence responsive to the documents pertaining to Vish
Wind produced by the Mehras, however, since these facts were
neither pleaded nor proved, there was no fair opportunity to the
Mehra's to meet any allegations. There was neither any affidavit of
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 108 jt-comap-315, 314 & 316 -19.doc
evidence supporting any claim awarded nor was any such claim
proved. It was pointed out that Enercon did not even amend their
Statement of Claim to incorporate any such claim for damages nor
led any effective evidence in support thereof. In this regard
reliance was placed on the decision of the Supreme Court reported
as (2008) 17 SCC 491 Bachhraj Nahar v. Nilima Mandal & Anr
and AIR 2008 SC 2594 State Bank of India v. S.N Goyal.
151. It was submitted that the Appellants-herein filed two
affidavits pursuant to Procedural Order No.5 - one of Mr. D.
Vaidyanathan and the other of Mr. Kaushik Khona. It was sought
to be clarified by Mr. Mehta that these Affidavits were filed only to
allay a prejudicial impression which was perceived to be held by
the majority arbitrators as regards the conduct of Mehra's pursuant
to the production of documents by them and also the recusal of
their advocates. Neither of these Affidavits dealt with the merits of
the claim that allegedly arose out of the documents produced by
the Appellants. The Affidavit of Mr. Vaidyanathan was restricted
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 109 jt-comap-315, 314 & 316 -19.doc
to explaining the procedure for obtaining rights to establish wind
farms (namely allotment/ development rights). The Affidavit of
Mr. Khona was restricted to placing on record instances of the
benefits received by WWIL from the sale of development rights
acquired from Vish Wind. It was urged that the Appellants did not
venture to lead evidence as regards the merits of the allegations or
the alleged claim since these were not even a subject matter of the
pleadings.
152. It was highlighted that the Appellants in their Written
Submissions, at the outset itself, stoutly raised a contention that
the claim for alleged profits wrongfully earned by Vish Wind was
not pleaded in the Statement of Claim and hence the same could
not be considered by the Arbitral Tribunal. Without prejudice to
this contention, they sought to deal with this claim on merits, even
though no evidence was led by either party in respect thereof. The
same was dealt with only by way of abundant caution.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 110 jt-comap-315, 314 & 316 -19.doc
153. It was submitted that the findings comprised in the
impugned majority award were based only on the written
submissions filed by the parties and not on the basis of any
pleadings and/or evidence. Further, even while dealing with the
submissions of the Appellant's-herein with respect to these
transactions, the Arbitral Tribunal glossed over material
contentions raised therein. Various contentions of the Mehras in
the Written Submissions while justifying that no improper profit
was made by Vish Wind were completely overlooked. It had been
pointed out in the Written Submissions that in fact, WWIL had
made profits by selling development rights which it acquired from
Vish Wind to third parties. It was also highlighted that Enercon
had not led any evidence that the acquisition by Vish Wind was at
an over valuation. The Appellant's had produced valuation
reports, which went unchallenged. Even the evidence of Mr.
Vaidyanathan and Mr. Kona, which explained that the transaction
between WWIL and Vish Wind were at arms length, were
completely ignored and not dealt with. The said witnesses had
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 111 jt-comap-315, 314 & 316 -19.doc
already pointed out that time and effort expended in developing
the rights and obtaining various permissions which added value.
154. Learned Senior Counsel further submitted that the
majority Award accepts the position that the required pleadings
and particulars were absent in the Statement of Claim but holds
that the same were present in the application filed by Enercon
under Section 17 of the Arbitration and Conciliation Act, 1996
which was sufficient. The majority Award grants this relief under
the head of "further and other reliefs". In this context, it was
contended that pleadings set up in interim proceedings can never
be the substitute for the main pleadings and evidence in support
thereof.
155. It was emphasized that the pleadings are a
concomitant of natural justice and any relief granted sans
pleadings is clearly in teeth with the principles of natural justice.
Even if the strict rules of CPC and Evidence do not apply to
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 112 jt-comap-315, 314 & 316 -19.doc
arbitrations, the same surely are applicable to the extent necessary
for compliance of the avowed principles of fairness and natural
justice.
156. The learned Senior Counsel drew support from the
reasons advanced in the minority opinion on the aspect of lack of
pleadings. It was submitted that a minority view ought not to be
lightly brushed aside. The Supreme Court, in various cases, has
taken note of a minority opinion and has, in fact, affirmed the
minority opinion in preference to the majority view. Reliance in
this regard was placed on the judgment reported as (2007) 8 SCC
466 Numaligarh Refinery Ltd. v. Daelim Industrial Company Ltd.
SUBMISSIONS OF DR. BIRENDRA SARAF, ADVOCATE APPEARING ON BEHALF OF THE APPELLANT-
YOGESH MEHRA IN COMMERCIAL APPEAL NO. 315 OF 2019
157. Dr. Saraf addressed submissions on broadly three
issues, namely-
(i) That the majority Award dealt with and decided
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 113 jt-comap-315, 314 & 316 -19.doc
disputes emanating from the SHA which were foreign to the IPLA and rather fell within the domain of the CLB proceedings. Such disputes were therefore not arbitrable under the IPLA, and it was the arbitral clause comprised in the IPLA alone that had been invoked by the Claimants. It was thus submitted that such disputes relatable to the SHA could not fall within the scope of reference to arbitration as set out by the Supreme Court in paragraph 153 of its judgment dated 14.02.2014, if the same was construed meaningfully in light of the factual setting under which the arbitral machinery was set into motion.
(ii) Likelihood of Prejudice/Bias in the mind of the Tribunal as inferred from the disparaging and vitriolic remarks against Mr. Yogesh Mehra contained in the majority Award.
(iii) Perverse approach adopted by the majority Arbitrators whilst levying costs upon the Mehra brothers rather than WWIL.
158. Commencing his submissions on the issue of
arbitrability of the disputes relatable to the SHA in the present
arbitration, it was submitted that the disputes which were referred
to arbitration were in relation to the IPLA. The disputes in relation
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 114 jt-comap-315, 314 & 316 -19.doc
to SHA were never intended to and were in fact not referred to
arbitration.
159. In the alternative and without prejudice, it was
contended that even if it were held that the disputes in relation to
SHA were also referred to arbitration, the disputes which formed
the subject matter of proceedings before the CLB were certainly
not within the scope of reference to arbitration.
160. Dr. Saraf drew our attention to the SHA executed
between the parties on 12.01.1994. Clause 16 thereof incorporated
an arbitration agreement which reads as under:
"16.1 If any dispute, difference, claim or question shall arise between the parties hereto concerning the contents of this Agreement, or in any way relating to the contents of this agreement, or arising from the contents of this Agreement or the operation thereof, or the rights, duties, or liabilities of either party thereof in connection with this Agreement, the parties
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 115 jt-comap-315, 314 & 316 -19.doc
hereto shall do their best to settle the said disputes or differences amicably between themselves.
16.2 All disputes, differences, claims, questions, and controversies arising in connection with this Agreement and the operation of this Agreement which the parties are unable to settle between themselves are to be brought in writing to the attention of the Indo-German Chamber of Commerce in Bombay. The Indo-German Chamber of Commerce will finally settle the said disputes by arbitration. Both parties expressly agree to be bound by the results of said arbitration." (emphasis supplied).
161. This was in clear contrast to the arbitration clause
comprised under the IPLA which reads as under:
"17. GOVERNING LAW
17.1 This Agreement and any disputes of claims arising out of or in connection with its subject matter are governed by and construed in accordance with the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 116 jt-comap-315, 314 & 316 -19.doc
Law of India.
18. DISPUTE AND ABRITRATION
18.1 All disputes, controversies or differences which may arise between the Parties in respect of this Agreement including without limitation to the validity, interpretation, construction, performance and enforcement or alleged breach of this Agreement, the Parties shall, in the first instance, attempt to resolve such dispute, controversy or difference through mutual consultation. If the dispute, cotroversy or difference is not resolved through mutual consultation within 30 days after commencement of discussions or such longer period as the Parties may agree in writing, any Party may dispute(s), controversy(ies) or difference(s) for resolution to an arbitral tribunal to consist of three (3) arbitrators, of whom one will be appointed by each of the Licensor and the Licensee and the arbitrator appointed by Licensor shall also act as the presiding arbitrator.
18.2 The arbitrators shall have powers to award and/or enforce specific performance. The award of the arbitrators shall be final and binding on the Parties.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 117 jt-comap-315, 314 & 316 -19.doc
IN order to preserve its rights and remedies, either Party may seek preliminary injunctive relief or other temporary relief from any court of competent jurisdiction or from the arbitration tribunal pending the final decision or award of the arbitrator(s). Any such application to a court of competent jurisdiction for the purposes of seeking injunctive relief, shall not be deemed incompatible with this agreement to arbitrate or as a waiver of this Agreement to arbitrate.
18.3 All proceedings in such arbitration shall be conducted in English. The venue of the arbitration proceedings shall be London. The arbitrators may (but shall not be obliged to) award costs and reasonable expenses (including reasonable fees of counsel) to the Party (ies) that substantially prevail on merit. The provisions of the Indian Arbitration and Conciliation Act, 1996 shall apply. ..."
162. It was submitted that disputes arose between the
parties as to whether the IPLA was a binding and concluded
agreement or was it only a draft which was finalized. There were
disputes as regards the rate of royalty and also the basis of
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 118 jt-comap-315, 314 & 316 -19.doc
computation of royalty. It was the case of Appellants that the IPLA
was not a concluded contract and that the draft was at variance
with the Agreed Principles and yet to be finalised. It was signed
only for the purpose of identification.
163. Dr. Saraf painstakingly traced the sequence of events
that transpired thereafter. It was pointed out that the first
proceeding between the parties was a petition being Company
Petition No. 121 of 2007 filed by Enercon GmbH before the
Company Law Board, Bombay under Section 397 and 398 of the
Companies Act, 1956. Various allegations were made in the said
petition as regards the functioning of the Joint Venture Company,
Enercon (India) Limited / Wind World India Limited
(WWIL),about alleged wrongdoings of the Mehra Group, alleged
breach of the SHA and also alleged siphoning off funds by the
Mehras to various other companies, which companies were
impleaded as party respondents to the petition. Vish Wind
Infrastructure Limited (Vish Wind) was arrayed as Respondent
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 119 jt-comap-315, 314 & 316 -19.doc
No.33. It was contended that a bare perusal of the petition would
clearly evince that all issues regarding their functioning of WWIL
and the alleged siphoning away of funds were raised in the said
petition and reliefs were sought in that regard. Some of the
relevant averments comprised in the petition are extracted as
under:
"21. ... Despite the Technical Know-How Agreement between the Petitioner and the Company having expired and despite demanding new and newer technology (which were invariably made available by the Petitioner) Respondent No.2 resisted efforts to formalize a new technology arrangement. When at last the Intellectual Property Licence Agreement was entered into between the Petitioner and the Company (through Respondent No.2) pursuant to the Agreed Principles, copies of which are annexed hereto and marked Annexure P-7, Respondent No.2 would neither reveal the "net sales" figures of the Company, nor carry out the required self assessment of royalties. Most
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 120 jt-comap-315, 314 & 316 -19.doc
importantly the financials of the Company were hidden by Respondent No.2.
...In other words, the Company is being run by manipulation of its accounts to portray a rosy picture so as to dip into public funds by indulging in excessive and unjustified borrowings from banks, including PSU Banks, which would never agree to become lenders to the Company if the true and fair accounts were known.
...Instead of concentrating the core area of specialization of the Enercon Group, that is manufacture of wind turbines, Respondent No.2 has diverted the focus of the Company to indiscriminately acquiring land and capacity for power generation, vesting these in many separate companies. Thus Respondent Nos. 2 and 3 authored a slew of companies (the subsidiary and associate companies - Respondents 9 to 35 herein), many of which became Independent Power Producers (IPPs) under the Electricity laws of the country. All the associate companies are owned by Mehra Group.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 121 jt-comap-315, 314 & 316 -19.doc
...Being the Managing Director of the Company and in actual day-to-day control of its affairs; Respondent No.2 is in a position to cause the books of account of the Company to reflect only what suits him. Restricting access to accounts and doctoring accounts for unfairly depriving the other shareholder from exercising its rights to purchase offered shares, a right provided by Article 58 of the Articles, makes it clear case of oppression and mismanagement and it is imperative, in the most respectful submission of the Petitioner that an independent audit be immediately conducted. ...
24. ... So long as the Petitioner shall own not less than 51% of the total issued equity shares of the Company, the Petitioner shall have the right to appoint two directors, one of whom to be a non retiring director and so long as the Mehra Group shall own not less than 49% of the total issued equity shares of the Company, the Mehra Group shall have the right to appoint two directors, one of whom to be a non retiring director. This was given effect to (including the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 122 jt-comap-315, 314 & 316 -19.doc
change in shareholding to 56% of Petitioner and 44% Mehra Group) in Article 128 of the Articles of Association of the Company and the said Article, as it reads today, states that so long as the Petitioner is holding 56% of the total Equity share capital of the Company and the Mehra Group is holding 44% of the total Equity share capital of the Company, ....
74. Another aspect of the way the business of the Company was being conducted by Respondent No.2 was his focus on acquiring land and capacity for power generation, vesting these in a separate company. The deal with the future customer would include complete management of the power utility by Respondent No.2. Thus Respondent No.2 authored a slew of companies (the subsidiary and associate companies - Respondents 9 to 35 herein), many of which became Independent Power Producers (IPPs) under the Electricity laws of the country. Furthermore, Respondent Nos. 2 and 3 have set up some of the associate companies themselves wherein utilizing the monies of the Company
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 123 jt-comap-315, 314 & 316 -19.doc
assets such as land have been acquired in the name of such associate companies. This also constitutes a wrongful diversion of funds and amounts to grave mismanagement of the affairs of the Company.
...
76. When the Petitioner, having left the day- to-day management to the Mehra Group, started to have serious reasons to doubt the rosy picture portrayed by the Mehras, the Petitioner commissioned financial audit and legal due diligence so as to determine the actual state of affairs of the Company and its subsidiary and associate companies. The facts of mismanagement of the affairs of the company that emerged included: ...
81. Restricting access to accounts and doctoring accounts for unfairly depriving the other shareholder from exercising its rights to purchase offered shares, a right provided by Article 58 of the Articles, makes it imperative that an independent audit be immediately conducted.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 124 jt-comap-315, 314 & 316 -19.doc
PRAYERS
88. It is therefore respectfully prayed as under:
Main Prayers
a) pass appropriate orders and directions removing the Respondent Nos. 2 and 3 from the positions of Managing Director and Whole Time Director respectively of Enercon (India) Limited.
b) Pass appropriate orders and directions removing the Respondent Nos. 2 and 3 from the positions of Managing Director and/or Whole Time Director and respectively of the said subsidiary and associate companies of Enercon (India) Limited.
...
e) Direct Respondent Nos. 2 to 8 to transfer their entire shareholding (44% in Enercon (India) Limited to the Petitioner at a fair value to be independently arrived at on the basis of the balance sheet of the Company giving the true view of the Company.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 125 jt-comap-315, 314 & 316 -19.doc
f) Direct Respondent Nos. 2 to 8 to transfer their entire shareholding in the subsidiary and associate companies of Enercon (India) Limited including but not limited to Respondent Nos. 9 to 35 herein to the Petitioner at a fair value to be independently arrived on the basis of the balance sheet of each of the said companies giving the true view of each company.
g) Direct an investigation to ascertain the conduct of the Respondent Nos. 2 to 8 in dealing with assets, properties, monies and management of the Respondent No.1 Company.
h) Direct Respondent No.1 to take all necesary and consequential action to the report of the investigation, including but not limited to tracing out the monies, property and assets of the Company in the hands of the Respondent Nos. 2 to 8 or any of them and direct restoration of such monies, properties and assets to Respondent No.1.
Interim prayers
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 126 jt-comap-315, 314 & 316 -19.doc
...
iv. Restrain Respondent Nos. 9 to 35 being the subsidiary and associate companies of Enercon India Limited, their employees, officers, servants and agents, from dealing with, transferring or creating any third party interests in their respective assets except in the ordinary course of business.
viii. Injunct Mehra Group (Respondent Nos. 2 to
8) or any of them from transferring, selling, mortgaging, creating third party rights of all or any part of their shareholding in the Company to any other person, except the Petitioner;
ix. Direct the Respondent Nos. 2 to 8 to furnish an affidavit before this Hon'ble Board the details of contracts between the Mehra Group or any of the Respondent Nos. 2 to 8 and the Company.
x. Restrain Respondent Nos. 1 to 35 from divulging or diverting to third parties the Technical know-how and proprietary informations of the Petitioner;"
164. It was highlighted that in the said petition, the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 127 jt-comap-315, 314 & 316 -19.doc
Appellant's-herein filed Company Application No. 484 of 2007
under Section 8 of the Arbitration and Conciliation Act, 1996
seeking reference to arbitration. The same was opposed by
Enercon GmbH (Respondent-herein) and vide Order dated
29.10.2007 the said application was dismissed.
165. The relevant portions of the said Order as referred to
by Dr. Saraf during the course of his submissions are reproduced as
under:
"5. Shri Sarkar, Senior Advocate for the petitioner submitted: In terms of Section 8, to refer the parties to arbitration, this Board should be satisfied that the subject matter of the petition is the subject matter of the arbitration agreement and that there is a commonality of parties. In the present case, the SHA is between the petitioner and the Mehra group and the company is not a party. Similarly, TKA is an agreement between the petitioner and the company and Mehra group is not a party. This
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 128 jt-comap-315, 314 & 316 -19.doc
TKA has already expired by efflux of time and is no longer effective. That is why IPLA was entered into. As a matter of fact, when the petitioner stopped supply of equipments etc., the Mehra group filed a suit seeking for a direction to the petitioner to supply equipment in terms of SHA/TKA. Instead of submitting the same to arbitration, thus, very clearly indicating that Mehra group has given a go bye to arbitration. This would indicate that they do not rely on the arbitration clauses. Further, respondents 9 to 35, against which reliefs have been sought, are not parties to either of the two agreements. Further in the petition, the petitioner alleged mismanagement and there is no provision regarding the same in either of the two agreements. Even in respect of removal of
nd rd the 2 and 3 respondents and also relating to transfer of shares, the petitioner has relied on the Articles and not on the terms of the SHA. Therefore, in view of the fact that there is no commonality of parties, and that many of the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 129 jt-comap-315, 314 & 316 -19.doc
allegations particularly in relation to financial mismanagement are not matters arising out of the arbitration agreements and that bifurcation between the Board and the Arbitration Tribunal is not permissible, the application should be dismissed.
...
8. It is evident from the provisions of Section 8 that if the subject matter brought before this Board is the subject matter of arbitration agreement, the Board is bound to refer the parties to arbitration. Therefore commonality of the subject matter is a prerequisite to invoke/apply Section 8. Likewise, a reading of Section 7(1) read with Section 2(1)(h) would indicate that the parties before the judicial proceedings should be parties to the arbitration agreement to refer the disputes between them arising out of the defined relationship. This would indicate that there should be a commonality of parties also. Section 7(3) mandates that an arbitration agreement has to be in writing or in terms of Section 7(4), it should satisfy one of the requirements as specified in sub-Sections (a) to (c).
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 130 jt-comap-315, 314 & 316 -19.doc
Thus, before referring parties to arbitration, this Board has to satisfy itself, that there is commonality of parties, subject matter and the requirements of Section 7(3) or 7(4) are met with.
9. Having dealt with the legal position, I shall deal with the factual aspects of this case. There are two agreements viz. SHA and TKA in which the parties thereto have agreed to refer the disputes to arbitration. The admitted fact is that the company is not a party to SHA and Mehra group is not a party to TKA. As a matter of fact, ShriSarkar pointed out that the currency of TKA has expired by a flux of time and that is why IPLA relating to supply of technical know how was entered into in September 2006, the existence of which has also been challenged by Mehra group. On the basis of the reliefs sought, Mehra group is contending that the reliefs sought arise out of the SHA. It is on record that the terms relating to shareholding and directorship as in the SHA have been incorporated in the Articles in toto. In such a situation, in Goyal M Gases case relying on the decision of this Board in EIH Limited vs. Mashobra Resort Ltd. (119 CC 993), this Board has held that
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 131 jt-comap-315, 314 & 316 -19.doc
once terms of SHA containing arbitration clause have been incorporated in the Articles of the company, then the terms of the Articles will prevail over the SHA. It also further held that once the terms of the shareholders' agreement have been incorporated in the Article with the omission of arbitration clause, that clause has no validity. In the present case, the petitioner has relied on the Article 58(a) of the Articles of Association of the company in regard to the allegation of depriving the petitioner of its pre- emption rights and likewise the petitioner has sought for amendment to the Articles regarding directorship. Both these matters can be decided independent of the terms of SHA. ... Even otherwise, in view of the judgment of the Apex Court in Sukanya Holdings, there is no possibility of bifurcation of the subject matter between the CLB and the Arbitrator. Whether, there is a breach of right of pre-emption, whether the Mehra group is guilty of financial mismanagement meriting their removal as MD and WTD and whether Articles relating to directorship is to be amended etc. would all depend on the merits of the case and need not be gone into while dealing with the instant
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 132 jt-comap-315, 314 & 316 -19.doc
petition under Section 8 of the Act.
10. Considering the fact that the company is not a party to SHA and that some of the allegations cannot be traced to the terms of the SHA, even assuming that pre-emption rights and directorship are covered under the terms of SHA, the application is not maintainable and is accordingly dismissed."
166. Emphasis was laid on the circumstance that the
Appellants request for referring the disputes which were subject
matter of the CLB proceedings was opposed by Enercon GmbH
(Respondent-herein) and such request was rejected by the CLB,
making it clear that Enercon GmbH never intended to be refer
such disputes to arbitration. In this context, it was submitted that
the Respondents-herein cannot be permitted to belatedly set up an
inconsistent plea of 'intent to arbitrate' even for the disputes
relatable to the SHA, as sought to have been done in the case at
hand.
167. Taking the argument forward, Dr. Saraf highlighted
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 133 jt-comap-315, 314 & 316 -19.doc
that on 13.03.2008, a notice invoking arbitration was issued by
Enercon GmbH invoking Clause No. 18 of the IPLA and seeking
to refer the disputes in respect of IPLA to arbitration. The relevant
portion of the notice are as under:
"There have arisen in respect of the IPLA a series of substantive disputes, controversies and differences between Enercon GmbH, WPG on the one hand and EIL on the other hand which EIL is obliged to refer to arbitration in London. Further, to the extent that you yourselves seek to advance such claims in the name of or derivative of EIL, you are both likewise bound to refer such claims to arbitration in London.
The parties' substantive disputes in respect of the IPLA cover at least the following:
1) The extent to which the supply of Special Components, any other parts, components, etc. to EIL since September 2006 and the further supply since November 2007 is governed by and protected by the terms of IPLA and the amount
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 134 jt-comap-315, 314 & 316 -19.doc
payable towards the sale of Special and other components, parts and materials by Enercon to EIL and any questions relating to the alleged claim of EIL for damages for non-supply of Special Components.
2) The validity of the IPLA ...
3) Whether the parties have concluded a binding agreement to refer disputes in respect of the IPLA to arbitration ...
4) The amount of royalty payable by EIL to Enercon ... pursuant to the terms of clause 5 of the IPLA.
5) The access to and provision of accounts pursuant to ... IPLA ...
6) EIL's and your liability in damages.
In respect of these disputes, Enercon GmbH and WPG hereby give notice of their Joint nomination of Mr VV Veeder QC as the Licensors' arbitrator pursuant to clause 18.1 of the IPLA. ...
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 135 jt-comap-315, 314 & 316 -19.doc
...As you know we have also looked to the need for the regularisation of the affairs of EIL through the appointment of the joint managing directors to EIL as mandated by the order of the Company Law Board's decision dated 29 October 2007. Notwithstanding, however the appointment of a joint managing director on 28 November 2007, effectively, EIL has continued to be run as it was before the joint managing director's appointment. Further, in light of the discoveries of systematic financial and managerial abuse of EIL's affairs that we discovered in the short review that we had in January 2008, we have had no option but to apply to the CLB for further orders protecting Enercon's position in EIL as a shareholder. In so doing Enercon GmbH has not submitted any of the above substantive disputes arising out of the IPLA to the CLB. "
168. From the notice of invocation, it was apparent that
what was invoked was the arbitration clause in the IPLA
incorporated in Clause 18 therein. No disputes in relation to the
SHA were referred to arbitration. In fact, it was expressly made
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 136 jt-comap-315, 314 & 316 -19.doc
clear that disputes which were pending before the CLB would not
be a subject matter of the arbitration and would be prosecuted
independently. It is on the basis of the arbitration clause in the
IPLA that it was stated that the venue should be London and the
reference would be to three arbitrators. Under the SHA, the
arbitration was contemplated under the aegis of the Indo German
Chambers of Commerce.
169. Consequent thereto, on 27.03.2008 Enercon GmbH
filed an Arbitration Claim Form being Claim No.2008 F 040296
in the Queen's Bench of the Commercial Court in England based
on Clause 18 of the IPLA seeking a declaration that there was a
valid and binding arbitration agreement, and also seeking a
restraint on the proceedings initiated by the Mehra's in the
Bombay High Court. Under the head of 'Relief Claimed' at page 2
of the said proceeding, it was apparent that the entire reference was
to the IPLA and Clause 18 thereof being the arbitration agreement
on the basis of which the proceedings were initiated.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 137 jt-comap-315, 314 & 316 -19.doc
170. Proceeding further in his endeavour to highlight that
the intention expressed by Enercon GmbH to arbitrate was
confined to disputes under the IPLA in view of which only the
arbitral clause comprised therein was invoked, Dr. Saraf referred to
the contents of the application filed by Enercon GmbH under
Section 45 of the Arbitration and Conciliation Act, 1996 in the
Daman Suit. As highlighted by us in our factual narrative, on
08.04.2008 the Mehra's had instituted Regular Civil Suit No. 9 of
2008 before the Court of Civil Judge, Senior Division, Daman.
The suit sought a declaration that the IPLA was not a concluded
contract between the parties and that there was no valid arbitration
agreement for submission of disputes between the parties. The
plaintiffs in the suit asserted that the invocation of English
Arbitration Act and the initiation of proceedings in England were
without jurisdiction and sought relief restraining the proceedings
initiated by Enercon GmbH in England in Claim No.2008 F
040296.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 138 jt-comap-315, 314 & 316 -19.doc
171. Significantly, it was pointed out that the application
filed by Enercon GmbH under Section 45 of the Arbitration and
Conciliation Act, 1996 on 28th July 2008 also sought to invoke
arbitration agreement as enmeshed in Clause 18 of the IPLA.
Much emphasis was laid on the said circumstances as it was
contended that it was this application which ultimately formed the
subject matter of consideration before the Supreme Court; where
reference to arbitration was authoritatively made by judgment
dated 14.02.2014.
172. Dr. Saraf elaborately took us through the judgment of
the Supreme Court to buttress his submission that the operative
text contained in paragraph 153 directing all disputes to be
referred for arbitration including those emanating from the SHA
had to be read in the context of what had arisen for consideration
of the Court. Emphasis was laid on the issues formulated by the
Supreme Court that it proceeded to ultimately answer. We
reproduce the relevant portion hereunder.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 139 jt-comap-315, 314 & 316 -19.doc
"69. ...The issues that arise for consideration of this Court are :
(i) Is the IPLA a valid and concluded contract?
(ii) Is it for the Court to decide issue No. (i) or should it be left to be considered by the Arbitral Tribunal?
(iii) Linked to (i) and (ii) is the issue whether the Appellants can refuse to join arbitration on the plea that there is no concluded IPLA?
(iv) Assuming that the IPLA is a concluded contract; is the Arbitration Clause 18.1 vague and unworkable, as observed by both the Arbitrators i.e. Mr. V.V. Veeder QC and Mr Justice B.P. Jeevan Reddy?
(v) In case the arbitration clause is held to be workable, is the seat of arbitration in London or in India?
(vi) In the event it is held that the seat is in India, would the English Courts have the concurrent jurisdiction for taking such measures
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 140 jt-comap-315, 314 & 316 -19.doc
as required in support of the arbitration as the venue for the arbitration proceedings is London?
(vii) Linked to (v) & (vi) is the issue whether the Appellants are entitled for an anti-suit injunction?
These, of course, are only broad based issues; many other supplementary questions will have to be examined in order to give a definitive determination."
173. It was urged that from the issues framed by the
Supreme Court, it was pellucid that the Court was only
considering the IPLA, whether the IPLA was a concluded
contract, the validity of the arbitration clause in Clause 18.1 of
IPLA and as to whether the same was workable. Further, the
Supreme Court was also considering whether the seat of the
arbitration was in India or in England solely with reference to
Clause 18 of IPLA and the effect of London being specified as
venue therein. The entire gamut of consideration of the Supreme
Court revolved around the IPLA and the arbitration clause
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 141 jt-comap-315, 314 & 316 -19.doc
incorporated therein.
174. Dr. Saraf submitted that the decision of the Supreme
Court bears not even a reference to the arbitration clause
comprised under the SHA. The SHA is referred to only as a
historical fact.
175. It was pointed out that the Supreme Court ultimately
allowed the application under Section 45 filed before the Daman
District Court and while various proceedings in Daman Court and
the English Courts were stayed, the Supreme Court in its
considered wisdom consciously chose not to stay the proceedings
before the CLB.
176. On the strength of this circumstance, it was therefore
submitted that the only discernible reason for choosing to exercise
such a course was that the disputes under the SHA were subject
matter of adjudication before the CLB and were never
contemplated to be referred to arbitration. It was reiterated that
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 142 jt-comap-315, 314 & 316 -19.doc
the directions of the Supreme Court cannot be read out of context
to expand a scope of reference much beyond the invocation and
also the proceedings under Section 45. In this regard reliance was
placed upon the decision of the Supreme Court reported as (2006)
7 SCC 735 Commissioner of Central Excise, Delhi v. Allied Air-
Conditioning Corporation (Regd).
177. It was highlighted that the issue of want of jurisdiction
of the Arbitral Tribunal to adjudicate upon disputes arising under
the SHA was raised before the Tribunal. The Arbitral Tribunal
dealt with the issue of jurisdiction in paragraphs 227 and 230 of
the Award. Paragraphs 227 and 230 read as under:
"A. Jurisdiction and Discretion
227. The first question is whether the Tribunal has jurisdiction to deal with these matters and if so, whether as a matter of procedural discretion it should exercise that jurisdiction. The SHA has a clause (16.2) providing for arbitration of "all disputes ... arising in connection with this
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 143 jt-comap-315, 314 & 316 -19.doc
agreement and the operation of this agreement"
by the Indo-German Chamber of Commerce in Bombay.
...
230. In the Tribunal's view, the last point is fallacious. The refusal to stay the CLB proceedings does not entail staying these arbitration proceedings. Both may continue. The Tribunal considers that the judgment of the Supreme Court makes clear this Tribunal's mandate to resolve the disputes under the SHA. It is true that the Supreme Court did not stay the CLB proceedings (correctly, if one may say so with respect), for the same reason as the CLB itself refused to stay such proceedings in 2007. The issues may overlap; but they are not the same and the statutory remedies sought are not necessarily available to the Tribunal. The Supreme Court did not stay the proceedings before the CLB but neither did it stay the arbitration. The resolution of issues of fact or law by either the CLB or the Tribunal may give rise
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 144 jt-comap-315, 314 & 316 -19.doc
to issue estoppels or other forms of res judicata in the proceedings before the other, but the question of whether the one should wait for a decision by the other is a matter of procedural discretion and case management for the CLB and the Tribunal. The Tribunal notes that it took from 2007 until 2012 for the CLB to deliver a final judgment on the Company Petitions and a further three years for that judgment to be set aside on appeal by the Bombay High Court. The Tribunal therefore considers that it would be procedurally unjust to the parties not to proceed with the mandate which it has been given by the Supreme Court."
(emphasis supplied)
178. It was thus submitted that the Arbitral Tribunal
clothed itself with the jurisdiction on the specious basis that there
would be delays in disposal of proceedings in the CLB. It was
urged that such considerations could supply no legitimate basis for
conferring jurisdiction on an Arbitral Tribunal which it inherently
lacked.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 145 jt-comap-315, 314 & 316 -19.doc
179. While summing his submissions on this issue, which
needless to state goes to the root of the matter, Dr. Saraf submitted
that in the aforesaid circumstances, it was apparent that neither
were the disputes referred to arbitration nor were the same
adequately pleaded before the Arbitral Tribunal and as such, the
Award against the Appellants on the aspect of breach of SHA is
without jurisdiction.
180. In the context of scope of reference, reliance was
placed on a passage from Russel On Arbitration, 24 th Edtn, which
reads as under:
"5-028 Scope of the reference. Whether a particular is within the reference will be determined as a matter of construction of the notice of arbitration, giving the words used their natural meaning in the context in which they were used and applying an objective test. The scope of matters that can be referred will normally be constrained by the scope of the agreement to arbitrate, although the parties may
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 146 jt-comap-315, 314 & 316 -19.doc
agree that the reference should be broader and can agree an adhoc submission of issues enlarging the scope of the Tribunal's jurisdiction beyond their original agreement to arbitrate. The scope of reference may include both claims by a claimant and counterclaims brought by a respondent, which again must be within the agreement to arbitrate. The factual background to the giving of the notice and any previous communications between the parties concerning the issues between them will also be relevant in construing the scope of the reference to arbitration. If, by the time the notice of arbitration is given, the parties' previous communications indicate that it would be natural to expect the reference to arbitration to include all the outstanding disputes, that fact may be taken into consideration. The reference may also include claims arising subsequent to the commencement of arbitration if the notice of arbitration demonstrates the parties' intention to do so. Provided they are within the scope of reference, the Tribunal has a discretion whether
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 147 jt-comap-315, 314 & 316 -19.doc
to permit new claims to be introduced in the course of the arbitration, but if they are outside the scope of reference new claims cannot be entertained without agreement of the parties."
181. Reliance was also placed on the judgment of the
Supreme Court reported as (2011) 5 SCC 532 Booz Allen and
Hamilton Inc. v. SBI Home Finance Limited & Ors. and in
particular paragraph 34 (iii) which we reproduce as under:
"34. The term "arbitrability" has different meanings in different contexts. The three facts of arbitrability, relating to the jurisdiction of the Arbitral Tribunal, are as under:
...
(iii) Whether the parties have referred disputes to arbitration?
That is, whether the disputes fall under the scope of the submission to the Arbitral
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 148 jt-comap-315, 314 & 316 -19.doc
Tribunal, or whether they do not arise out of the statement of claim and counterclaim filed before the Arbitral Tribunal. A dispute, even if it is capable of being decided by arbitration and falling within the scope of arbitration agreement, will not be "arbitrable" if it is not enumerated in the joint list of disputes referred to arbitration, or in the absence of such joint list of disputes, does not form part of the disputes raised in the pleadings before the Arbitral Tribunal."
182. It was therefore contended that in these circumstances,
the award to the extent that it impinged upon the disputes under
the SHA was liable to be set aside by the learned Single Judge of
this Court under Sub-Section 2 (b)(iv) of Section 34, which reads
as under:
"34. Application for setting aside arbitral award. ...
(2) An arbitral award may be set aside by the Court only if--(a) the party making the application furnishes proof that--
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 149 jt-comap-315, 314 & 316 -19.doc
...
(iv) the arbitral award deals with a dispute not contemplated by or not falling within the terms of the submission to arbitration, or it contains decisions on matters beyond the scope of the submission to arbitration:
Provided that, if the decisions on matters submitted to arbitration can be separated from those not so submitted, only that part of the arbitral award which contains decisions on matters not submitted to arbitration may be set aside; or..."
183. Grievance was also raised that the Arbitral Tribunal
fell in error by passing the Award directing the Mehra brothers to
make payment of monies to WWIL under the residual head "relief
claimed as further and other reliefs" in the Statement of Claim. It
was urged that it is a settled law that the residual head of "any relief
of further and other relief" has to be read in the context of entirety
of the pleading and the main relief claimed in the proceedings and
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 150 jt-comap-315, 314 & 316 -19.doc
cannot be read de hors the same. It was submitted that at any rate
it must derive colour from the main relief claimed and must not be
materially different so as to radically alter the nature of
proceedings. In this regard reliance was placed on the decision of
the Privy Council reported as 1927 SCCOnline PC 98 (527)
Abdur Rahim & Ors. v. Mahomed Barkat Ali & Ors.
184. Incidentally entrenching upon the issue of absence of
requisite pleadings that was separately dealt by Mr. Mehta, learned
Senior Counsel, Dr. Saraf placed reliance upon Section 23 of the
Arbitration and Conciliation Act, 1996 which mandates that a
statement of claim needs to be filed by a claimant pleading and
stating "the fact supporting the claim, the points at issue and the
relief or remedy sought" and the respondent is entitled to state his
defence in respect of these particulars. Under Section 23 (3) a right
is conferred on any party to amend or supplement his claim. It
was, therefore, urged that in the absence of any relief claimed or
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:44:59 ::: Jdk/pdp 151 jt-comap-315, 314 & 316 -19.doc
any basis of such relief being stated in the Statement of Claim, no
award could have been passed by the Arbitrator as done in the
instant case. Without prejudice to the contention that the entire
controversy was beyond the scope of arbitration, it was submitted
that Enercon GmbH did not even amend its statement of claim to
incorporate such pleadings /relief as mandatorily required.
185. The next contention canvassed by Dr. Saraf was that
the entire majority Award was vitiated by the prejudice/bias
formed by the learned Arbitrators against the Mehras. The said
argument was essentially anchored on the observations made in
the majority Award against the Mehras, in particular, Mr. Yogesh
Mehra whilst appreciating his account tendered as a witness. It was
pointed that extremely sharp and strong observations were made
against Mr. Yogesh Mehra, which was a tell-tale sign of the fact
that the Arbitrators formed a prejudicial opinion about Mr. Yogesh
Mehra's character. The two Arbitrators holding a majority opinion
completely disregarded the evidence of Mr. Yogesh Mehra because
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 152 jt-comap-315, 314 & 316 -19.doc
they formed an adverse opinion that Mr. Yogesh Mehra was
"devious, manipulative and dishonest." Having formed this
opinion, the two Arbitrators holding the majority view completely
disregarded the only direct evidence of the meeting in the form of
testimony of Mr. Yogesh Mehra and instead placed heavy reliance
on the testimony of two witnesses on behalf of Enercon GmbH
whose evidence as regards what happened at the said meeting was
nothing beyond hearsay evidence and hence not admissible. It is
in this context that Dr. Saraf ventured to draw our attention to the
relevant portions of the majority Award which we reproduce
hereunder.
"VII. THE WITNESSES
90. The Tribunal considers that, with the exception of Mr. YogeshMehra, all the witnesses were honest and trying to assist the Tribunal. Their memories may sometimes have been inaccurate, but they were doing their best with events taking place many years ago. Mr. Mehra, as will be apparent from many places in this
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 153 jt-comap-315, 314 & 316 -19.doc
Award, was not a reliable witness. He is a highly emotional man who felt very strongly that his German counterparties had treated him unfairly. His deep sense of grievance may have enabled him to believe that what he would have liked to have happened had actually happened. But it also made him feel that he was entitled to behave in a way which, viewed objectively, was devious, manipulative and dishonest. In his testimony to explain away this behaviour, he gave evidence to the Tribunal that sometimes even he must have known to be untrue, as indeed it manifestly was.
(emphasis supplied)
...
119. On the morning of 29 September 2006 Mr. Mehra arrived in Bremen. DrWobben met him at the airport and took him to the Hilton Hotel. They had a discussion together in the morning and were joined at lunch by Mr. Kettwig. We do not of course have Dr. Wobben's evidence about what was discussed in the morning, but Mr. Kettwig said that when he arrived, it appeared that the discussions had not gone smoothly.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 154 jt-comap-315, 314 & 316 -19.doc
He said he could "feel some tension, or an atmosphere that was not quite normal ... I tried to calm them down because there were a lot of emotions". The main issue appeared to be that "Dr. Wobben had pointed out that the IPLA should be accepted in its current form". In his witness statement, Mr. Kettwig added a detail:
"After having made this clear, I recall that Dr.Wobben put his things into his bag and shut the clasp. From my experience of Dr.Wobben, this was a typical reaction of his where he was frustrated or annoyed...
...
121 Mr. Mehra's account of the discussions with DrWobben at the Hilton Hotel is very different. He testified:
"We discussed, amongst other matters, my objections to the draft IPLA (as communicated in August 2006). After about 3 hours of discussion, it became clear that there were outstanding issues between the parties. It was felt that the draft IPLA
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 155 jt-comap-315, 314 & 316 -19.doc
required amendments ... Dr. Wobben assured me that he would decided on a fair basis for computing the royalty ... At that point Dr. Wobben called Mr. Kettwig, Managing Director of Enercon, to join us at the Hilton. Mr. Kettwig arrived at about 4 pm. The three of us then discussed the basis on which we would move forward and Dr. Wobben agreed to some of the key objections raised by me in August 2006."
122. The Tribunal does not accept Mr. Mehra's evidence and prefers the evidence of Mr. Kettwig. The IPLA had been discussed at length and in detail. DrWobben had dealt firmly with Mr. Mehra's comments in August 2006 and was expecting that Mr. Mehra had come to Aurich to sign the IPLA. That Dr. Wobben should now have made a U-turn on MrMehra's points seems to the Tribunal highly improbable and is contrary to all other credible evidence. Nor is it probable that Dr.Wobben would have been willing to re-open discussion about the 5% royalty agreed in the HoA. There is no credible evidence for this either.
(emphasis supplied)
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 156 jt-comap-315, 314 & 316 -19.doc
...
124. Mr.Mehra, on the other hand, testified that, it having been decided between himself and Dr.Wobben that "the draft IPLA required amendments", the Agreed Principles were intended to reflect the changes which would have to be made in that document as well as the other agreements yet to be finalised. He denied that he had brought a draft of the Agreed Principles: "maybe I had my points with me, but this document was very clearly typed on the computer in the Bremen Hotel."
125. Mr.Kettwig is neither a lawyer nor fluent in English (unlike Mr.Mehra). The language of the document suggests that its substance is derived from Mr.Mehra and his legal advisers in India. ...
...
146. The Tribunal regrets that it is not unanimous on this point. The contrary views of Justice Raveendran will be found in Appendix A. The majority members do not think it would be helpful for them to undertake a point by point examination
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 157 jt-comap-315, 314 & 316 -19.doc
of his reasons. They would only observe that he appears to attach little importance to what the persons involved said and did not say at the time of the meetings in Aurich at the end of September 2006. It is essentially a question of credibility. The majority regard Mr. Kettwig as an honest and credible witness and accept, as explained in paragraphs 127-128 and 131 above, that Dr. Wobben's instructions to him at Bremen, given in the presence of Mr. Mehra, were that he and Mr. Mehra were to settle the Agreed Principles but that the IPLA was to be executed unchanged and that his discussions of the Agreed Principles with Mr. Mehra it was accepted that they would not affect the IPLA. The majority do not regard Mr. Mehra as an honest or reliable witness and in any case, he has not suggested that he said anything to contradict what he must have known that Dr. Wobben and Mr. Kettwig understood the position to be."
( emphasis supplied)
186. On the strength of the aforesaid observations, it was
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 158 jt-comap-315, 314 & 316 -19.doc
submitted that it was apparent that having formed a very strong
prejudicial opinion about Mr. Mehra, the majority arbitrators
disregarded every evidence of his and accepted every testimony of
Mr. Kettwig and Ms. Fritsch Nehring as the gospel truth. As
against the aforesaid, the learned Arbitrator holding the minority
opinion, on an impartial and unbiased assessment of evidence held
that Mr. Yogesh Mehra was the only reliable witness and that Mr.
Kettwig and Ms. Fritsch Nehring were unreliable witnesses who
were trying to either skirt the issues or to give erroneous evidence.
Reference was made by the learned Counsel to the observations of
the learned Arbitrator in this regard.
187. Dr. Saraf also sought to give another dimension to his
plea of bias. It was submitted that the ' general territorial bias' of
the majority arbitrators is also apparent from their observations in
paragraph 230 of the award wherein they clothed themselves with
jurisdiction as regards disputes which were the subject matter of
CLB proceedings on the basis that such disputes in India remain
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 159 jt-comap-315, 314 & 316 -19.doc
pending for years. The attention of the Court was drawn to the
relevant observations of the majority Arbitrators on this aspect,
which we quote as under.
"...The Tribunal notes that it took from 2007 until 2012 for the CLB to deliver a final judgment on the Company Petitions and a further three years for that judgment to be set aside on appeal by the Bombay High Court. The Tribunal therefore considers that it would be procedurally unjust to the parties not to proceed with the mandate which it has been given by the Supreme Court..."
188. In support of this plea, reliance was placed on the
following pronouncements.
(i) (1998) 5 SCC 513-State of W.B. v. Shivananda Pathak ; wherein the Supreme Court extensively laid down the contours of the law with regard to bias.
(ii) (2000) Q.B. 451- Locobail (UK) Ltd. vs. Bayfield Properties Ltd.; wherein the Court held that real danger of bias may well exist if credibility of that individual could be significant
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 160 jt-comap-315, 314 & 316 -19.doc
in the decision of the case; or if in a case the credibility of any individual where an issue to be decided by the Judge, he had in a previous case rejected the evidence of that person in such outspoken terms as to throw doubt on his ability to approach such persons evidence with an open mind.
(iii) (2015) 2 Mah LJ 38- Inox Leisure Ltd. v. Goa State Infrastructure Corporation Ltd.; wherein it was observed by this Court that when bias on the part of the arbitrator became evident only upon the receipt of the Award, Section 12 and Section 13 of the Act would not apply in cases of such nature.
189. The last issue agitated by Dr. Saraf during the course
of his arguments was imposition of costs of arbitration upon the
Mehra brothers rather than WWIL. It was submitted that the
majority Award imposes costs of Euro 3,794,970 on the Mehra's
being the entire costs on actuals of the arbitration as assessed by
the Tribunal. It was pointed out that a large part of the award
relates to the claim of royalty against WWIL. The Arbitral
Tribunal in paragraph 306 and 307 of the Award clearly held that
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 161 jt-comap-315, 314 & 316 -19.doc
there is no personal liability of Mehra brothers for the liability of
WWIL under the IPLA. The issues were complex, and Mehras
were under their bonafide rights in contesting the same. In such
circumstances, the award of the entire cost against the Mehras was
perverse. The dissenting Arbitrator in paragraphs 58-59 of the
minority Opinion fairly ordered WWIL to bear the cost. It was
contended that the award of Costs as against the Mehra brothers
cannot be countenanced and is not backed by any reason.
SUBMISSIONS OF MR. ZAL ANDHYARUJINA, ADVOCATE APPEARING ON BEHALF OF THE APPELLANT- WWIL IN COMMERCIAL APPEAL NO.
316 OF 2019
190. The learned counsel at the outset before proceeding to
make his submissions informed the Court that a Corporate
Insolvency Resolution Process in respect of WWIL was initiated
on 20.02.2018 appointing an Interim Resolution Professional and
the moratorium had been imposed.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 162 jt-comap-315, 314 & 316 -19.doc
191. Mr. Andhyarujina addressed the Court on the aspect
whether the IPLA was a concluded contract or a mere draft upon
which signatures had been appended only as a mark of
identification. The learned counsel also dealt with the issue of
payment of royalties in respect of WTG's. He clarified that the
Appellant-WWIL would not be challenging the directions issued
by the Arbitral Tribunal to pay Enercon GmbH the price of
components and materials supplied to it.
192. Apropos the issue whether the IPLA had fructified as
a contract capable of binding parties or had remained in the realm
of incohate draft, the learned counsel submitted that Agreed
Principles admittedly executed between the parties on 30.09.2006
clearly dislodged the theory of IPLA having been executed as a
concluded contract. It was highlighted before us that the Agreed
Principles referred to the IPLA as a draft and therefore it strikes a
discordant note with the assertion of the Respondents-herein that
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 163 jt-comap-315, 314 & 316 -19.doc
the IPLA had been finally executed. It was submitted that both
the documents are admittedly signed on the same date, and
significantly it is not the case of the Respondents-herein that the
IPLA was executed some time after the execution of the Agreed
Principles. Rather, it had emerged in evidence that the documents
were signed by Dr Wobben and Mr Yogesh Mehra in succession at
one sitting.
193. Mr. Andhyarujina further contended that the IPLA
executed by the parties on 30.09.2006 in its present form
unequivocally evidences that the same was a mere inchoate draft in
view of the fact that there are blank spaces comprised therein. The
cover page of the said document bears a date which is different
from the date comprised in the recitals of the agreement . The
Annexures referred in the agreement are not appended and
admittedly not drawn up. It was submitted that the said
circumstances are a tell-tail sign that the IPLA was a mere draft
enclosed to the Agreed Principles.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 164 jt-comap-315, 314 & 316 -19.doc
194. The learned counsel also raised an alternative
submission that even if the IPLA was executed with the intention
to create legal relations, yet the same could not be enforced as it
was uncertain and hit by Section 29 of the Indian Contract Act,
1872.
195. It was urged that given the unambiguous nature of the
Agreed Principles executed between the parties, oral evidence to
dislodge the same could not have been permitted in terms of
Sections 91 and 92 of the Indian Evidence Act.
196. The learned counsel submitted that the handwritten
letter authored by Mr. Yogesh Mehra on 30.09.2006 from his
hotel referred to the execution of the Agreed Principles and not
the IPLA as has been interpreted by the Tribunal.
197. Taking the argument forward, Mr Andhyarujina
placed emphasis on the e-mail sent by Ms. Nehring on 24.11.2006
referring to the IPLA as a final draft.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 165 jt-comap-315, 314 & 316 -19.doc
198. It was contended that it would militate against the
natural course of probabilities that Enercon GmbH handed over
the valuable technical know-how of various WTG's only in mere
anticipation of a formal agreement. In this context, it was
submitted that the plea of the Appellants that they were entitled
to further WTG's in terms of the TKHA (as amended by STKHA)
cannot be brushed aside. According to learned counsel Enercon
(India) Ltd. was entitled to E-26, E-30, E-33, E-40 and E-48
WTG's under the TKHA (as amended by STKHA).
199. The learned counsel contended that the TKHA
contemplated one time transfer of technology and the same was in
consonance with the Industrial Policy of the Government of India
of the year 1991 and the RBI Norms. It was submitted that the
Tribunal did not attach significance to the aspect of indegenisation
as contemplated under Article 5.2 of the TKHA. Further, Article
3.1 of the TKHA employs the expression ' transfer' in respect of
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 166 jt-comap-315, 314 & 316 -19.doc
the supply of technology.
200. With respect to the issue of seeking restitution of
royalties remitted by Enercon (India) Ltd., it was submitted that
the said amounts were transferred under bona fide mistake, and it
is the case of the Appellants that no further royalties were payable
upon the threshold mark of 2.5 Million Deutsche Marks having
reached in the year 2002.
SUBMISSIONS OF MR. ASPI CHINOY, SENIOR ADVOCATE APPEARING ON BEHALF OF THE CONTESTING RESPONDENTS- ENERCON GMBH AND WPG IN COMMERCIAL APPEAL NO. 314 OF 2019
201. Mr. Aspi Chinoy, learned Senior Counsel appearing
on behalf of the contesting Respondents in the above captioned
appeal addressed submissions on two issues that were raised during
the course of hearing by Mr. Shyam Mehta, learned Senior
Counsel appearing on behalf of the Appellants.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 167 jt-comap-315, 314 & 316 -19.doc
First, namely, whether the Award passed by the
Tribunal insofar as 'Vish Wind' transactions were concerned was
liable to be set aside owing to insufficiency of pleadings in that
regard.
The other cardinal issue adverted to by Mr. Chinoy
before us was whether it could be safely concluded that the
Appellants-herein had themselves waived the right to oral hearing
during the course of proceedings before the Tribunal, and thus the
absence of the opportunity to address closing oral submissions
would not vitiate the Award from the root to the fruit.
202. Apropos the first issue with regard to insufficiency of
necessary averments in the pleadings of the Claimants and
consequent failure to raise the foundation of claim with respect to
Third Party transactions, Mr. Chinoy painstakingly alluded to the
various pleadings drawn by the parties at different stage of the
proceedings to trace the genesis and evolution of this claim which
ultimately succeeded before the Tribunal.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 168 jt-comap-315, 314 & 316 -19.doc
203. At the outset attention of this Court was drawn to the
Statement of Claim. It was pointed out that de hors the claims
against WWIL, separate claims had been raised against the Mehra
brothers since the very inception. In this regard, he referred to Para
96.2 and Para 96.3 of Part H of the Statement of Claim, inter alia,
wherein it had been specifically claimed that Vaayu Companies
had been set up for exploiting the claimants technology and value
was transferred from WWIL to such companies. The relevant
extracts are reproduced hereunder.
Para 96.2 of Part H of the Statement of Claim
"...set up the Vaayu Companies for the purpose of receiving and exploiting the Claimants technology and/or have assisted the Vaayu Companies in receiving and/or exploiting the Claimants technology and/or have transferred value from WWIL to the Vaayu companies, such also constitutes breaches of Mr Yogesh Mehra and/or Ajay Mehra's
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 169 jt-comap-315, 314 & 316 -19.doc
obligations under the SHA and/or Indian law, including their duties of good faith, which has caused loss to the claimants and for which the claimants are entitled to damages to be assessed and/or an account of profits, plus interest...".
Para 96.3 of Part H of Statement of Claim
"...The loss caused to Enercon by Mr Yogesh Mehra and/or Mr Ajay Mehra's breach of their duties under the SHA and/or under Indian Law, including their obligations of utmost good faith, trust, confidence and commitment towards Enercon, include the damage caused to the value of Enercon's shareholding in WWIL and Enercon is entitled to Damages (to be assessed) plus interest, in regards to this loss. Further and alternatively, Enercon is entitled to an account of profits plus interest, in relation to Mr Yogesh Mehra and/or Mr Ajay Mehra's breach of their duties of utmost good faith, trust, confidence and commitment towards Enercon..."
Prayer Clause (I)(c) stated as follows:
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 :::
Jdk/pdp 170 jt-comap-315, 314 & 316 -19.doc
"(1) In respect of Mr Yogesh Mehra and Mr Ajay Mehra's breaches of the SHA :
(a) .. .. ..
(b) .. .. ..
(c) An order that Yogesh Mehra and Mr Ajay Mehra pay damages (to be assessed) and/or an account of profits for their breaches of the SHA and/or duties arising as a matter of Indian Law."
204. On the strength of the above noted material, it was
urged that the Statement of Claim contained material pleading to
the effect that the Mehra's had transferred value from WWIL to
the Vaayu Companies in breach of their obligations under the
SHA and/or Indian Law. Further, it had been categorically prayed
that the Mehra brothers be held liable to pay damages and/or
account for the profits made by such transfer. It was emphasised
that this was in clear contra-distinction from the pleadings with
respect to the loss suffered owing to exploitation of Claimants
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 171 jt-comap-315, 314 & 316 -19.doc
technology by the Mehra's.
205. Mr. Chinoy however fairly submitted that the
Statement of Claim fell short of disclosing any concrete particulars
of the manner of such unauthorized transfer of technology and/or
value was effected, The Statement of Claim merely voiced the
apprehensions under which the Claimant's were laboring as they
were in dark about the affairs of WWIL.As events would
subsequently unravel, this deficiency was overcome at a later stage
in the form of Written Submissions and other applications
preferred by the Claimants detailing the Third Party transactions
with a greater degree of specificity. It was submitted that actionable
information with regard to such transactions had started to surface
only sometime around September 2015 in view of the disclosures
made by the Appellants-herein pursuant to Procedural Order
No.2 dated 22.06.2015 passed by the Tribunal. Documents prima
facie revealed that transactions to the tune of Euro 124 million
had taken place between WWIL and Vish Wind; one of the Vaayu
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 172 jt-comap-315, 314 & 316 -19.doc
Companies for the purchase of what was later sought to be termed
as 'development rights' and interest in land. It was pointed out that
even at this stage, financial statements of the Vaayu Companies
were deliberately withheld by the Mehra's.
206. The Claimant's had pursued their apprehension of
unauthorized value transfer from WWIL in favour of Third Party
entities and subjected the documents received through the process
of disclosures to forensic scrutiny by Experts. Report prepared by
Mr. Nicholas Good lent credence to the fears of the Claimant's
and brought to notice past transactions to the tune of Euro 124
million as described above. The said Report was also submitted
before the Tribunal.
207. Armed with this material gained from disclosures
made during the course of Arbitral Proceedings, the Claimants
proceeded to positively aver material particulars in their Opening
Written Submissions submitted on 25.11.2015 with respect to the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 173 jt-comap-315, 314 & 316 -19.doc
claim of value transfer having been made to third parties. Special
emphasis was placed by Mr. Chinoy to the following portions
comprised therein.
"114...In setting up the Vaayu Companies and procuring that WWIL transact with related companies, including but not limited to the Vaayu Companies, Mr Yogesh Mehra and/or Ajay Mehra have breached their obligations under the SHA and/or Indian Law including clauses 2.7 & 4.1 of the SHA and/or their duties of good faith towards Enercon. Accordingly Mr Yogesh Mehra and Mr Ajay Mehra should pay damages and/or account for profit in respect of transactions undertaken by WWIL with these related companies. By way of example it has now been seen that WWIL has purchased from related companies land or land rights at a cost of Euro 124 million in recent years. No valid consent from Enercon has been obtained for these transactions by which very large sums have been paid to entities which Yogesh Mehra or his family own or have a
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 174 jt-comap-315, 314 & 316 -19.doc
significant interest in. It amounts to self dealing on the part of Mr Yogesh Mehra and/or Ajay Mehra and/or consists of breaches by Mr Yogesh Mehra and Mr Ajay Mehra of clauses 2.7 and 4.1 of the SHA and/or their duties of good faith towards Enercon and they are obliged to account for all profits they have earned. The same legal principles apply with respect to benefits received from loans made by WWIL to related companies."
208. It was also highlighted that the Appellant's-herein
also took cognizance of the issue of unauthorized value transfer in
favour of Third Party entities-Vaayu Companies and at various
junctures expressly denounced the same in their Opening Written
Submissions. Attention of this Court was drawn to the relevant
portions on this aspect at Paragraphs 87, 88(iii)(iv) and Para
89(iii) of the Opening Written Submissions submitted before the
Tribunal on behalf of the Appellants. It had been contended that
there has been no transfer of value from WWIL to the Vaayu
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 175 jt-comap-315, 314 & 316 -19.doc
Companies. They also defended the sale and purchase of
Development rights by WWIL from the related companies as
being backed by independent valuation reports.
209. Mr. Chinoy submitted that further discoveries on this
issue were made during the course of cross-examination of Mr.
Yogesh Mehra in consequence of which he finally produced
financial statements of Vish Wind on 07.12.2015 pursuant to the
directions of the Tribunal. The said documents evinced the
following material facts.
-'Vish Wind' had a subscribed capital of Rs. 500,000 [Euro 7500], which had been subscribed by the Mehras.
-From 2007 'Vish Wind' had borrowed substantial sums interest free from WWIL; with Euro 650,000 being owing in 2008. These funds were used for purchasing land.
-In 2010-11 'Vish Wind' had sold development Rights to WWIL for Euro 50 million, as against the total operating expenses incurred of Euro 463,000. The Profit & Loss
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 176 jt-comap-315, 314 & 316 -19.doc
account showed a profit of over Euro 49 million.
-In 2011-12 'Vish Wind' had sold Development Rights to WWIL for Euro 49 million against total expenses incurred of Euro 1.4 million.
-The contracts for the sale of Development Rights were signed by Yogesh Mehra for 'Vish Wind' and by Mr Ajay Mehra for WWIL.
-That 'Vish Wind' had no employees, no business and virtually no money apart from the loans received from WWIL.
210. In view of the dramatic developments that had
transpired during the course of evidential hearings, Procedural
Order No. 5 came up to be passed on 11.12.2015 wherein,
significantly, the Tribunal categorically recorded the fact that it
proposed to give ample opportunity to the parties to adduce
further evidence with respect to Vish Wind Infrastructure LLP. It
was submitted that no objection/demur was raised at this stage to
resist the proposed reception of evidence with respect to Vish
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 177 jt-comap-315, 314 & 316 -19.doc
Wind on any ground including non-arbitrability of this claim or
the alleged insufficiency of pleadings. Rather, the Appellants-
herein ventured to lead evidence in terms of such liberty provided
under Procedural Order No.5 by submitting the statements of Mr.
Kaushik Khona and Mr. D Vaidyanathan to explain/justify these
Third Party transactions.
211. Further, the Closing Written Submissions submitted
by both the parties also unequivocally evidenced detailed exchange
of submissions on the aspect of the Third Party transactions.
Reference was made to the Closing Submissions dated 13.05.2016
tendered by the Claimants wherein this issue was explored at Part
VI(F) whereas the Closing Submissions of the Appellants-herein
dated 25.05.2016 also elaborately dealt with the said issue in
Paragraphs 153-220.
212. It was in this backdrop which we have noted at some
length that Mr. Chinoy submitted that the Appellants-herein were
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 178 jt-comap-315, 314 & 316 -19.doc
well aware that value transfer to Third Party entities was an
integral claim raised by the Claimants and the concise
facts/particulars upon which such claim was founded ultimately
emerged to the fore during the course of the proceedings even if
not discernible at the commencement of the proceeding; when it
remained in the realm of apprehension. It was contended that at
any rate Procedural Order No.5 passed by the Tribunal
sufficiently alerted the Appellant's that the issue of Vish Wind
transactions was well within the domain of adjudication. It was in
this view of the matter that the Appellant's even embarked to lead
evidence with respect to such transactions with a view to render
them innocuous. Thus, it was submitted that there existed no
element of surprise and the circumstance of absence of sufficient
pleadings in the Statement of Claim by itself would not result in
jettisoning such a claim from judicial calculus in view of the host
of subsequent events which unequivocally demonstrate the
conscious awareness exhibited by the Appellant's that the issue was
very much under the lens of adjudication.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 179 jt-comap-315, 314 & 316 -19.doc
213. In support of his submissions, reliance was placed
upon the decision of the Supreme Court reported as AIR 1966 SC
735 Bhagwati Prasad v. Chandramaul , wherein it was observed
that though as a matter of principle the importance of pleadings
could not be underscored enough, however, there may be peculiar
cases where a plea though not expressly adopted at the inception
may, in fact, emerge during the course of a Trial and the parties
may be aware in substance that the plea is being tried. It was held
that under such circumstances when both the parties being aware,
there being no element of surprise and ample opportunity having
been given to lead evidence, the pedantic requirement of pleadings
may stand relaxed provided the possibility of prejudice could be
foreclosed.
214. Adverting to the issue of denial of oral hearing to
present concluding arguments, Mr. Chinoy stoutly refuted the
plea of violation of natural justice as canvassed on behalf of the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 180 jt-comap-315, 314 & 316 -19.doc
Appellants. It was contended that there was no cavil with the
proposition that right to oral hearing was engrafted under Section
24 of the Arbitration and Conciliation Act, 1996. It was submitted
that however, it was open for the parties to waive/exclude such a
right.
215. Extensive reference was made to the proceedings
conducted before the Tribunal as evidenced from the perusal of
the Procedural Orders passed and transcripts of Proceedings. It
was submitted that opportunity for making opening oral
submissions was duly accorded by the Tribunal to both sides
before commencement of evidential hearings.
216. It was highlighted that during the course of recording
evidence, more particularly on Day 6-7, during cross-examination
Mr. Yogesh Mehra, that financial statements of Vish Wind were
required to be produced under the directions of the Tribunal. The
documents revealed high value transactions between WWIL and
Vish Wind, which also took the learned Counsels representing the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 181 jt-comap-315, 314 & 316 -19.doc
Appellants-herein by surprise. In this regard, Mr. Chinoy drew our
attention to the relevant transcript of the Proceedings dated
10.12.2006. For the sake of appreciating the contentions, we
reproduce the relevant portions thereof herein-below.
"We on this side were, I think, by as much surprise as anyone else as to some of the evidence that was heard yesterday and AZB [the Respondents' solicitors] has not yet received instructions from the client on these related party matters, so I am instructed today not to examine Mr Good [the Claimants accounting expert] on these matters."
217. It was submitted that the Tribunal, under these
attending circumstances, proceeded to pass Procedural Order No.5
on 11.12.2015 fixing a proposed calendar enumerating the
timeline to be adhered by the parties. It was contended by Mr.
Chinoy that the said Order was formulated upon clear
consensus/agreement between the parties as expressed by their
lawyers. Significantly, Item No.9 of the Procedural Order No. 5
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 182 jt-comap-315, 314 & 316 -19.doc
recorded the fact that opportunity for Closing Oral Submissions
would be accorded only if determined to be necessary by the
Tribunal. We extrapolate the said Procedural Order in entirety.
"The following Timetable is agreed between the parties:
Sr.No. Particulars Date
1. Claimants to file an Application 13 Dec 2015 under Sec 17 of the Arbitration & Conciliation Act 1996
2. Respondents to file their Reply to 19 Dec 2015 the Claimants Application under Sec 17 of the Arbitration & Conciliation Act 1996
3. Respondents to respond to the 15 Dec 2015 Claimants request for production of documents set out at Annex A
4. Tribunal to make a ruling on the 23 Dec 2015 Claimants Application (i) under sec. 17 of the Arbitration and Conciliation Act 1996 & (ii) in relation to any disputed item in Annex A
5. Respondents to provide any 4 January 2016 documents/information in accordance with (3) and (4) Above
6. An Application to the Tribunal, if 18 January 2016
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 183 jt-comap-315, 314 & 316 -19.doc
either party seeks to adduce further evidence responsive to the Vish Wind Infrastructure LLP documents or the new documents produced at (5) above
7. An Application to cross examine 25 January 2016 or respond to the evidence adduced pursuant to (5) above
8. Exchange of Closing Written 16 March 2016 submissions
9. Any oral evidence in 27 & 28 April accordance with (7) above and 2016 in London.
Closing oral submissions if any are requested and if determined necessary by the Tribunal."
(Emphasis Supplied)
218. It was contended that the transcript of Proceedings
dated 11.12.2015 also contemporaneously recorded the views of
the Tribunal and the learned Counsels representing the parties.
Mr. Chinoy submitted that a perusal of the said transcript also
lends credence to his submission that the Appellants-herein did
not assert any legal right to make Closing Oral Submissions and
rather relegated the decision to the wisdom of the Tribunal. The
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 184 jt-comap-315, 314 & 316 -19.doc
relevant portions of the transcript of Proceedings dated 11.12.2015
is extracted hereinbelow.
"The Chairman : "I assume we are not necessarily committed to an oral hearing at all?".
Mr Khambata : [WWIL & the Mehras Counsel] "No, I understand".
The Chairman : It may be that no one wants to cross examine and then we just do it.
Mr Joseph [Claimants Counsel] : I think Lord Hoffmann, you are absolutely right. We are not committing ourselves, and I think, maybe we said closing submissions, if any are requested, or something along those lines.
The Chairman : Yes.
Mr Khambata : Yes, that would give us the opportunity to go back and make an appropriate application for oral submissions.
Mr Joseph : If any is required and that again would not commit the Tribunal to acceding to the request, if the request were made.
Mr Khambata : Of course not. Of course not."
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 185 jt-comap-315, 314 & 316 -19.doc
219. Mr. Chinoy sought to deal with the contention canvassed by
Mr. Shyam Mehta and Dr. Birendra Saraf, learned Counsels for the
Appellants that the transcript of Proceedings for Day 9 dated
10.12.2015 evidenced categoric request for oral hearing having
been made by Mr. Khambatta, the learned Senior Counsel
representing the Appellants-herein before the Tribunal and
therefore waiver of the right to oral hearing ought not to be lightly
inferred from the statements exchanged on the subsequent date i.e.
Day 10 of evidential hearings on 11.12.2015.
The said contention was countered by Mr. Chinoy by
explaining that a perusal of the transcript of Proceedings dated
10.12.2015 would reveal that the learned Senior Counsel
representing the Appellants-herein did not have proper
instructions and sought time for obtaining the same. The
transcripts further suggest that even on the said date, the learned
Senior Counsel had himself offered the alternative recourse of
submitting Written Submissions instead of oral hearing. It would
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 186 jt-comap-315, 314 & 316 -19.doc
thus emerge that he had no instructions to adopt a hardened
position committed to an Oral hearing. Further, the Procedural
Order No. 5 was made the following day i.e 11.12.2015 upon the
consent of parties, and the same is consistent with the contents of
the verbal interchange that took place between the Tribunal and
the Counsels which was also contemporaneously recorded in a
transcript. It was submitted that the prior intention to the
contrary, if any, stood superseded by the unequivocal and
unambiguous submission by the learned Senior Counsel to the
discretion of the Tribunal to determine the requirement of Closing
Oral Hearing.
220. It was further urged that even the Solicitors which
were inducted subsequently and entered appearance on behalf of
the Appellants-herein on 07.01.2016 did not assert that they had
an indefeasible right to make Closing Oral Submissions. Rather
intent was expressed at repeated intervals to apply to the Tribunal
to take leave to make such submissions. In order to buttress his
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 187 jt-comap-315, 314 & 316 -19.doc
submission, Mr. Chinoy drew attention of this Court to various
communications addressed by the Solicitors to the Tribunal,
including the communication dated 09.02.2016, 14.04.2016,
22.04.2016 and 11.05.2016. It was only on 25.05.2016 that the
Solicitors representing the Appellants-herein belatedly for the first
time asserted that they had a right to oral hearing in terms of
proviso to Section 24(1) of the Arbitration and Conciliation Act,
1996 and that the parties had not excluded such a right. The said
request was promptly rejected by the Tribunal on 26.05.2016 by
highlighting that the Procedural Order No. 5 was made by
consent of parties and it expressly recorded the fact that Closing
Oral Submissions would be granted only if requested and
determined to be necessary by the Tribunal.
222. While summing up his submissions on this aspect, Mr.
Chinoy contended that the procedure adopted by the Tribunal was
transparent and reasonable. Repeated accommodations were
granted in favour of the Appellants-herein by the extending time-
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 188 jt-comap-315, 314 & 316 -19.doc
lines. The Tribunal was considerate to accede to such requests in
view of the fact that the legal team of Counsels and Solicitors
representing the Appellants-herein withdrew from the case on 14-
15.12.2015. Procedural Order No. 5 was subsequently modified
by Procedural Order No. 7 dated 03.02.2016 at the instance of the
Appellants-herein. However, further extensions were sought. It
was owing to such repeated extensions that the dates of 27-28
April 2016 initially reserved for possible Closing Oral Submissions
had to be cancelled by the Tribunal vide communication dated
20.04.2016 as the Appellants-herein had already indicated they
were not in the position to submit their Closing Written
Submissions in the stipulated time and had sought further
extensions. The Appellants-herein ultimately submitted their
Closing Written Submissions only on 25.05.2016 again breaching
the further extended deadline fixed for 13.05.2016. The Tribunal
thus no longer had the opportunity to peruse the submissions in
advance and determine the necessity, if any, of permitting Closing
Oral Submissions.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 189 jt-comap-315, 314 & 316 -19.doc
223. It was further submitted that no prejudice stemming
from absence of such hearing had been demonstrated. All issues,
including the issue of Third Party transactions-Vish Wind, were
comprehensively contested in the exhaustive Written Submissions
submitted on behalf of the Appellant's-herein before the Arbitral
Tribunal and thus the plea was a legal after-thought.
SUBMISSIONS OF MR. S.U KAMDAR, SENIOR ADVOCATE APPEARING ON BEHALF OF THE CONTESTING RESPONDENTS- ENERCON GMBH AND WPG IN COMMERCIAL APPEAL NO.S 314 OF 2019
224. Mr. Kamdar, learned Senior Counsel appearing on
behalf of the contesting Respondents sought to counter the
contentions canvassed by Dr. Saraf.
Mr. Kamdar dealt with three issues, namely-
(i) Whether the disputes relatable to the SHA, which included the 'Vish Wind' transactions could have been the subject matter of the present arbitration.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 190 jt-comap-315, 314 & 316 -19.doc
(ii) The allegations of Bias/prejudice harboured by the majority Arbitrators as sought to have been inferred from the observations contained in the majority Award qua Mr. Yogesh Mehra.
(iii) Whether the Arbitral Tribunal fell in error by saddling the Mehra brothers with the Costs of arbitration rather than having imposed the same upon WWIL.
225. With regard to the issue of arbitrability of disputes in
relation to the SHA, it was submitted that the Supreme Court in
paragraph 153 of its decision made unambiguous directions to
refer all disputes arising between parties in relation to various
agreements, inter alia, the SHA. It was contended that it was
impermissible for this Court to go behind the unequivocal
directions of the Supreme Court and its wisdom could not be
called into question by the Appellants in these proceedings by
posing novel objections that ought to have been urged before the
Supreme Court to resist reference of disputes under the SHA for
arbitration.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 191 jt-comap-315, 314 & 316 -19.doc
226. It was further submitted that it was evident that the
Supreme Court proceeded to comprehensively refer all disputes for
arbitration in view of the fact that the disputes had been
precipitating for nearly a decade before different forums and
inordinate delays had occasioned. It was also highlighted that in
the peculiar facts of the present case, with a view to mitigate
further delays, the Supreme Court in Paragraph 154 of its
judgment itself proceeded to nominate the Third Arbitrator.
227. Mr. Kamdar submitted that the Supreme Court noticed
the circumstance that each of the agreements- IPLA, HoA, SHA,
TKHA comprised arbitral clauses and thus there was a clear
'intention to arbitrate'.
228. It was further contended that the directions passed by
the Supreme Court in the case at hand was somewhat akin to its
approach in an earlier pronouncement reported as (2013) 1 SCC
641 - Chloro Controls India (P) Ltd. v. Severn Trent Water
Purification Inc, which was incidentally cited by the learned
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 192 jt-comap-315, 314 & 316 -19.doc
Counsels before the Supreme Court in another context.
229. It was also urged that Sections 8 and 45 of the
Arbitration and Conciliation Act, 1996 contemplate referring
parties to arbitration and not per se the matters/disputes.
Reliance was placed upon the decision of the Supreme Court
reported as (2012) 12 SCC 581 - State of Goa v. Praveen
Enterprises.
230. Taking the argument forward, Mr. Kamdar submitted
that significantly the Terms and Conditions of Tribunal's
Appointment also expressly contained reference to the directions
passed by the Supreme Court in its judgment dated 14.02.2014.
231. Countering the submissions of the Appellants, Mr.
Kamdar submitted that the Supreme Court in its judgment dated
14.02.2014 did not grant stay to the CLB proceedings as at the
relevant time the said proceedings had already concluded and
statutory appeals u/s 10F Companies Act, 1956 were pending
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 193 jt-comap-315, 314 & 316 -19.doc
before the Bombay High Court. Mr. Kamdar further elaborated
that the ambit of CLB proceedings was not restricted to merely
disputes under SHA but also enwombed within its fold disputes
arising from unauthorized amendment of Articles of Association
and other breaches of other statutory rights/duties under the
Companies Act, 1956 that were not the subject matter of
arbitration. Therefore, the two proceedings though having some
overlap could be permitted to operate concurrently in their own
spheres.
232. It was also urged that the plea of want of jurisdiction
was not raised by the Appellant's-herein before the Arbitral
Tribunal and the Tribunal was merely called upon to exercise its
procedural discretion not to pronounce upon the matters relatable
to SHA as the same were also pending adjudication before the
CLB. It was submitted by Mr. Kamdar that what was urged before
the Tribunal was the plea that exercise of such jurisdiction would
result in duplication of proceedings and not that the Tribunal
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 194 jt-comap-315, 314 & 316 -19.doc
inherently lacked jurisdiction as the Supreme Court did not intend
to refer disputes arising from the SHA. Reference was made to
Paragraphs 83-85, 150 of the Statement of Defence, Paragraphs
XII (A)-(D) of the Written Opening Submissions and Paragraph
139 of the Written Closing Submissions to demonstrate the nature
of objections raised before the Tribunal.
233. In this context, it was submitted that it was a trite
proposition of law that the objection of jurisdiction if not raised in
terms of Section 16(2) and (3) of the Act, 1996 is deemed to be
given up. Reliance was placed upon the decision reported as
(2014) 11 SCC 366 - Union of India v. Pam Development Pvt.
Ltd. and (2002) 3 SCC 572 - Narayan Prasad Lohia v. Nikunj
Kumar Lohia & Ors.
234. On this aspect, Mr. Kamdar while summing up his
submissions, contended that the exercise of jurisdiction by the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 195 jt-comap-315, 314 & 316 -19.doc
Tribunal was on a plausible and sound reasoning. The same had
been affirmed by the learned Single Judge, and this Court must be
slow in interfering. Reliance was placed on the recent decision
reported as (2019) 4 SCC 163 - MMTC Ltd. v. Vedanta Ltd.
235. Adverting to the next set of issue pertaining to bias,
Mr. Kamdar submitted that bias/prejudice was sought to be
inferred merely on the basis of certain scathing observations
expressed by the learned Arbitrators while appreciating evidence
the evidence of Mr. Yogesh Mehra and contending that Mr.
Yogesh Mehra, on the other hand, had been observed to be a
truthful witness in the minority Award. It was submitted that the
very premise for inferring bias was tenuous. Further, the issue in
substance pertains to appreciation of evidence that had been
undertaken by the Arbitrators by advancing reasons in support of
their conclusions. The intensity of review under Section 34/37 of
the Act, 1996 was not of such amplitude that it would be
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 196 jt-comap-315, 314 & 316 -19.doc
permissible for this Court to re-appreciate evidence.
236. Mr. Kamdar also highlighted that in Paragraph 22 of
the Affidavit in Rejoinder (in Notice of Motion (L) No. 84 of
2019 dated 20.02.2019 filed by Ajay Mehra it had been
pertinently averred that the Appellant was already apprehensive of
the alleged prejudice and personal bias of the majority of the
Arbitral Tribunal by 11.12.2015 i.e. during the pendency of the
arbitral proceedings itself.
237. In this context, it was submitted that in terms of
Section 13(2) of the Act, 1996 such a challenge ought to have
been raised at that stage itself before the Arbitrators, failing which
such a challenge is deemed to have been waived. Reliance was
placed upon the decision of this Court reported as (2015) 7
BomCR 141 M/s Visakha Petroleum Products Pvt. Ltd. v. B.L
Bansal and Ors.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 197 jt-comap-315, 314 & 316 -19.doc
238. On the issue of award of Costs, Mr. Kamdar submitted
that issues of such nature could hardly be urged under Section
34/37 of the Act, 1996 given the limited nature of such
jurisdiction. It was submitted that the issue of costs in the case at
hand is determined by Section 31A of the Act, 1996. It was
highlighted that Clause 18(3) of the IPLA expressly contemplated
that a party which prevails on the merits of the proceedings is
entitled to an award of costs and reasonable expenses. It was
pointed out that the Tribunal did not award the costs prayed for
but a substantially less amount bearing into consideration the
expenses incurred by the Appellant's-herein. The approach
adopted by the Tribunal was stated to be fair and reasonable.
239. It was urged that that the directions issued by the
majority Arbitrators directing the Mehra brothers to bear the costs
of proceedings was logical in as much as they were in the de-facto
control of the management of WWIL during period of actionable
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 198 jt-comap-315, 314 & 316 -19.doc
breaches. Further, a direction to WWIL to expend the costs would
in effect imply saddling Enercon GmbH (the successful Claimant)
with such liability as it owns shareholding in WWIL to the tune of
56%.
SUBMISSIONS OF MR. JANAK DWARKADAS, SENIOR ADVOCATE APPEARING ON BEHALF OF THE CONTESTING RESPONDENTS- ENERCON GMBH AND WPG IN COMMERCIAL APPEAL NO.S 316 OF 2019
240. Mr.Janak Dwarkadas, learned Senior Counsel
embarked upon the task of persuading us that the IPLA executed
between Dr. Wobben and Yogesh Mehra on 30.09.2006 at
Aurich, Germany was a concluded contract capable of binding the
signatory - parties and not a mere draft as contended by the
Appellants-herein. He also dealt with the submissions made by
Mr. Andhyarujina that the transfer of technology for various
WTG's under the TKHA/STKHA was a transfer in perpetuity
and not a mere license for a limited duration, therefore royalties
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 199 jt-comap-315, 314 & 316 -19.doc
not being payable.
241. Mr. Dwarkadas traced the fruition of the commercial
relationship between Enercon GmbH and the Mehras from the
very inception leading to surrection of Enercon (India) Ltd.
242. The learned Senior Counsel drew attention of the
Court to the contents of the TKHA executed between the parties
on 12.01.1994 wherein Enercon GmbH agreed to provide
Enercon (India) Ltd. with the 'right and license' to use the
technical know-how for the manufacture of certain WTG's (E-26
and at least two other ranges/models). It was highlighted that as
per Article 4 Enercon GmbH was entitled to receive a royalty at
the rate of 5% on the sale of WTG's and components over a
period of seven years not exceeding 2.5 Million Deutsche Mark.
As per Article 6.1, Enercon (India) Ltd. was prohibited from sub-
licensing or transferring the technical know-how to any party. The
TKHA would expire in ten years from the effecting date or seven
years from the date of commercial production.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 200 jt-comap-315, 314 & 316 -19.doc
243. It was pointed out that Enercon GmbH agreed to
supply E-30 and E-40 WTG's and at least two other
ranges/models to Enercon (India) Ltd. by expanding the scope of
products as defined in the TKHA by entering into a STKHA on
19.05.2000. Mr. Dwarkadas submitted that the Arbitral Tribunal
rightly held that Enercon GmbH fully complied with its
stipulated obligations of supplying the know-how of WTG's in as
much as technology in respect of E-26, E-30 and four ranges of
E-40 WTG's (E-40/6.44/E1, E-40/6.44/E2, E-40/6.44/E-3B and
E-40/6.44/E2B).
244. By November 2002 the royalty amount of 2.5 Million
Deutsche Mark had been generated, and the TKHA (as amended
by the STKHA) expired on 12.01.2004.
245. In view of the expiry of these agreements the parties
commenced negotiations to enter into a further agreement to
govern the supply of technical know-how in future. However,
during the interregnum, in anticipation of a formal agreement
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 201 jt-comap-315, 314 & 316 -19.doc
which was on the horizon, Enercon GmbH also provided the
technology in respect of E-33, E-48 and E-53 models of WTG's.
246. Mr. Dwarkadas referred to the observations made by
the Tribunal in its Award with respect to the contention canvassed
by the Appellants -herein that the TKHA contemplated a transfer
of technology in perpetuity and after its expiry Enercon (India)
Ltd. would be at liberty to utilize the said technology without
further payment of royalty. The Appellants had sought to urge
before the Tribunal and also before this Court that the regulatory
framework of RBI prevailing in the country compulsorily
mandated permanent transfer of technology to foster
indeginization, failing which approvals would not be granted. The
Tribunal had repelled this contention by observing that no
authoritative rule/policy to fortify such an assertion was produced,
and therefore the contention that the TKHA was required to be
interpreted in light of the regulatory backdrop was liable to be
rejected. The Tribunal proceeded to interpret the agreement de
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 202 jt-comap-315, 314 & 316 -19.doc
hors the regulatory backdrop and arrived at the conclusion that
the TKHA (as amended by STKHA) did not amount to a transfer
but was a permanent license which applied only to E-26, E-30
and E-40 models of WTG's.
247. It was urged by Mr Dwarkadas that perusal of the
correspondence between Mr. Yogesh Mehra and the
representatives of Enercon GmbH would reveal that no claim was
ever made at the relevant time that Enercon (India) Ltd. was
entitled to further WTG's under the TKHA (as amended by
STKHA) and thus the question of paying royalties would not
arise. It was highlighted by the learned Senior Counsel that Mr.
Yogesh Mehra merely attempted to negotiate in this regard citing
considerations of commercial viability, however, no assertion of the
right to receive technology for further WTG's without payment of
royalty was ever made. In this regard, reference was made to the
communication dated 29.10.2004 authored by Mr. Yogesh Mehra
and addressed to Dr. Wobben. Our attention was also drawn to a
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 203 jt-comap-315, 314 & 316 -19.doc
communication dated 11.02.2005 wherein the representatives of
Enercon GmbH expressed gratitude to Mr Yogesh Mehra for
having accepted that the royalty fee would be adopted as it was
adopted before for the two new WTG models. It was submitted
that overwhelming evidence led before the Arbitral Tribunal
establishes that Mr. Yogesh Mehra reconciled to the fact that
royalties would be payable and the only bone of contention that
survived was its quantum and method for computation. We were
referred to the discussion of the Tribunal in this regard as
contained in paragraphs 93 & 96 of the majority Award. The
portions of the same are reproduced hereinbelow:
"93. But the draft contained no provision for a royalty on the new models. On 19 October 2004, Mr. Kettwig wrote to say that he and Dr. Wobben were considering a royalty of 4% or 5%. On 29 October 2004 Mr. Mehra sent a five-page letter to Dr Wobben arguing his case for no royalty. The letter is well argued and courteous, ("I totally leave the decision to you,
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 204 jt-comap-315, 314 & 316 -19.doc
and whatever your decision, ultimately I shall follow!"). For present purposes, its significance is that at no point did Mr. Mehra suggest, as is now the Respondents' case, that WWIL was already entitled free of charge to the technology for the new models. The letter accepts that it is a matter of negotiation and leaves the decision to Dr. Wobben.
...
96. In his oral testimony at the Hearing, Mr Mehra found it difficult to explain why he had never told Dr Wobben or anyone at Enercon that WWIl was actually entitled to the E-33 and E-48 technology for free (to say nothing of the yet undeveloped E-53) because it had already been permanently transferred under the TKHA. Nor could he explain why he had said nothing to dispute Mr Monnerjahn's letter of 11 February 2005. The best he could offer by way of explanation was:
"My discussions with Dr Wobben were as a businessman. I never took the chance to
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 205 jt-comap-315, 314 & 316 -19.doc
explain my legal right... There was a huge amount of trust and understanding on both sides."
248. Mr. Dwarkadas urged that the approach adopted by
the learned Arbitrators authoring the majority Award in arriving at
the conclusion that the IPLA executed on 30.09.2006 was a
concluded contract, could hardly be termed as perverse and the
same was based on cogent reasons. The Tribunal analysed the
vast volume of documentary and ocular evidence to support its
findings.
249. For our benefit, Mr. Dwarkadas compartmentalized
the lengthy deliberation of the learned Arbitrators on this issue
into three broad heads, evidence (oral and documentary) with
respect to events preceding 29-30.09.2006, evidence (oral and
documentary) with respect to what transpired on the fateful dates
of 29-30.09.2006 at Aurich, Germany and the evidence (oral and
documentary) of the subsequent events which would throw light
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 206 jt-comap-315, 314 & 316 -19.doc
on the intent/understanding of the parties as to what they
executed on 30.09.2006.
250. It was urged that it was not the case that the Tribunal
arrived at conclusions sans any reasoning or without reference to
material in support of the same. In this context, it was submitted
that it was settled beyond pale of controversy that the jurisdiction
of Courts under Sections 34/37 of the Act, 1996 would not
enwomb within its fold re-appreciation of evidence.
251. With a view to satisfy us that the approach adopted by
the learned Arbitrators penning the majority Award was
unexceptionable, Mr. Dwarkadas extensively took us through the
observations comprised in the Award.
252. The Tribunal comprehensively took into account the
sequence of events that transpired during the protracted period of
negotiations. As noted by us earlier, the discussions between the
parties now centred on the method of computing the royalties in
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 207 jt-comap-315, 314 & 316 -19.doc
future. It seems that some headway was made on 23.05.2006
when non-binding Heads of Agreement on a Proposed Intellectual
Property License Agreement (HoA) was executed at Aurich,
Germany. The said document was expressed to represent the final
views of the parties on the terms of a new agreement. A draft of
the IPLA was attached to the same. Clause 5.1 of the draft IPLA
contemplated royalty of 5% on the net sales value of products sold
by WWIL. The net sales value was elaborately defined to mean -
"the net ex-factory sales price of the Products, exclusive of excise duties, minus the cost of the standard bought out Wind Energy Technology components and the landed costs of imported Wind Energy Technology components, irrespective of the source of procurement, including ocean freight, insurance, custom duties and the like."
The HoA recorded that the services of Mr. N. P. Sarda,
Partner of Deloitte Haskins and Sells (DHS) be commissioned to
seek their views on a formula for calculating royalties that would
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 208 jt-comap-315, 314 & 316 -19.doc
be in consonance with the requirements of Indian law.
253. Mr. Dwarkadas highlighted that in furtherance
thereof, Mr. Yogesh Mehra corresponded with Mr. Sarda and
elicited his opinion on a formula provided by him in his letter
dated 23.06.2006. The formula sent by Mr. Mehra upon which
opinion of Mr. Sarda was sought is extracted hereunder :
"Net Ex-Factory Sales Price of the Wind Energy Converters, excluding Excise duty, Taxes, Levies , Cess etc. LESS:
Landed cost of all imports, other than capital equipment and the cost of standard bought out components and raw material procured locally"
254. It was pointed out by the learned Senior Counsel that
the Tribunal noticed that this was not the formula as comprised in
the draft IPLA on which it had been agreed that opinion of Mr.
Sarda be sought. Rather it was a formula of Mr. Mehra's own
devising. It included deductions which did not form part of the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 209 jt-comap-315, 314 & 316 -19.doc
RBI formula. On 16.06.2006, Mr. Sarda is stated to have replied
by reciting the RBI formula and certifying that the formula
proposed by Mr. Mehra fell within it. The Tribunal in paragraph
107 observed that Enercon GmbH did not notice this discrepancy
at this stage and the same caused difficulties later.
255. Taking his argument forward, Mr Dwarkadas
delineated the succession of events to follow that would ultimately
culminate to the fateful visit of Mr Yogesh Mehra at Aurich,
Germany. It was highlighted from the Award that during the
months to follow there was exchange of drafts of the proposed
IPLA. A meeting was scheduled in Germany for 17-20th
September, 2006 for finalising the IPLA. On 15.09.2006, a final
version of IPLA was sent by electronic mail by Ms. Fritsch-
Nehring to Mr. Yogesh Mehra for his perusal. It was also stated
therein that Dr. Wobben had desired that he would like to first
discuss the final version of the IPLA before any discussion takes
place on other issues. Since the finalised draft of the IPLA was
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 210 jt-comap-315, 314 & 316 -19.doc
only sent at the last moment, Mr. Yogesh Mehra postponed his
trip to Germany with a view to consider the said draft.
256. Mr. Yogesh Mehra arrived in Bremen (Germany) on
the morning of 29.09.2006. Dr. Wobben received him at the
Airport and accompanied him to the Hilton Hotel. Discussions on
the proposed IPLA ensued. They were joined at lunch by Mr.
Kettwig. The Tribunal noticed the evidence of Mr. Kettwig where
he testified that he sensed the discussions had not gone smoothly
and he could feel some tension. Dr. Wobben had frustratingly
informed Mr. Kettwig in the presence of Mr. Mehra that Mr.
Mehra also wanted a further document to set out certain principles
that would be reflected when it came to subsequently finalising
other contracts. However, this was on a clear understanding that
the IPLA was to be entered into without change and the Agreed
Principles related to other agreements which would be shortly
entered into. However, it is common ground that no document
was signed on this date.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 211 jt-comap-315, 314 & 316 -19.doc
257. The Tribunal was of the considered view that the
evidence furnished by Mr. Kettwig appeared to be reliable vis a vis
the version of events disclosed by Mr. Yogesh Mehra. The
Tribunal observed that the objections/reservations expressed by
Mr. Mehra to the drafts of IPLA shared with him earlier by
Enercon GmbH had been firmly dealt by Dr. Wobben in August
2006. The stand of the parties had hardened. It was improbable
that Dr. Wobben would now have made a 'U-turn' on the issues
canvassed by Mr. Mehra during negotiations which took place
29.09.2006.
258. The Tribunal noticed that Mr. Kettwig stated in
evidence that to the best of his recollection, Mr. Mehra had
brought with him a draft of Agreed Principles in hard copy. The
Agreed Principles were predominantly drafted by Mr. Mehra in
advance of the meeting rather than being drafted together in the
meeting. Mr. Kettwig further deposed that Mr. Mehra accepted at
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 212 jt-comap-315, 314 & 316 -19.doc
the meeting that he would enter into the IPLA the next day, and
this was unaffected by the Agreed Principles. Per contra, Mr.
Mehra claimed in his evidence that the draft of Agreed Principle
had not been brought by him. He stated that this document had
been typed on the computer in the Bremen Hotel. On this aspect,
the Tribunal observed that Mr. Kettwig was neither a lawyer nor
fluent in English, unlike Mr. Mehra. The language of the Agreed
Principles suggested that its substance was derived from Mr.
Mehra and his legal advisors in India. It was further held that Mr.
Mehra understood that the Agreed Principles would have no effect
upon the IPLA and that the IPLA was expected to be executed by
the parties during his stay in Aurich, Germany.
259. The Tribunal observed that Mr. Kettwig was not an
astute lawyer. He could thus could not visualise the effect of the
words- "Draft enclosed" comprised in the document-Agreed
Principles and that these words could later be construed to be
inconsistent with Enercon's intention of executing the IPLA
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:00 ::: Jdk/pdp 213 jt-comap-315, 314 & 316 -19.doc
without any amendment. It was held that evidence of relevant
surrounding circumstances emerging from the contemporaneous
correspondence between parties and the evidence of Mr. Kettwig
established that both sides clearly understood that before any
discussion of other agreements took place IPLA, had to be
executed.
260. In support of his contentions, Mr Dwarkadas drew
strength from the findings of the Tribunal where the learned
majority Arbitrators observed that it was highly implausible that
the parties would sign the IPLA (twice in the case of Dr. Wobben
as he appended his signatures on behalf of Enercon GmbH as well
as WPG) and initial every page merely to identify it as the latest
draft under discussion. The Tribunal noticed that such an
approach had not been adopted by the parties before with respect
to other documents that were available for similar treatment.
261. The Tribunal also held that the assertion of Mr.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 214 jt-comap-315, 314 & 316 -19.doc
Kettwig that after the execution of IPLA; which had been pending
since a long time, Mr. Mehra appeared rather emotional, was
supported by the contents and tenor of a letter authored by Mr.
Mehra on that very day viz. 30.09.2006. The letter was addressed
to Dr. Wobben and was penned by Mr. Mehra at his hotel before
leaving for India.
262. The contents of the said letter have been extracted by
us in para 50 above, however, for the sake of appreciating the
submissions of Mr Dwarkadas, we reproduce its contents again.
"Dear Dr. Wobben, Today when I reached back to Bremen, and before I leave back to India Mr. Wobben, in the last 13 years since I first met you, I have never felt so de-motivated lost, confused and empty! Mr. Wobben, my this trip to Germany was besides of course to clarify al the points of the agreements, was to also find some solutions to my problems which you had also promised to do. But I am sorry to state that I go back without any solutions!
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 215 jt-comap-315, 314 & 316 -19.doc
Mr. Wobben, you asked me to trust you, which I have always done-
(1) I signed the agreement, without even reading it, only because I trust you.
(2) I did not even speak when Mr. Kettwig decided to write the royalty figure at 5%, because I trusted you, to be fair, because you always told me, that you wanted to make Enercon India Ltd. financially strong. Now with this, it reduces the profitability of Enercon India Ltd by 40% straight away. [I have never said no to paym (sic.) of royalty, only I thought you will be fair and just].
This royalty, is when the agreements do not ev (sic.) provide for any other technologies. In fact it does not even provide for the E-82! (3) I trusted you, when you told me, that I should not pursue the 'UBS' proposal, because you did not feel comfortable, I dropped the idea totally, because you promised me that we would find a solution to my 'family' issues. But I go back again without any solution! Respected Mr. Wobben, it hurt me, when Mr. Kettwig mentioned today, that the value of Enercon's
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 216 jt-comap-315, 314 & 316 -19.doc
operations in India should be of a value of 250 Million Euro. If you believe that this is correct, than [sic] I personally take responsibility of the fact that, I failed, and for which I am willing to resign. Mr. Wobben, you asked me to be truthful and open to you, which I always will be, and I thought I must write to you on exactly how I feel, because one thing for sure, is if I am not motivated, how can I motivate my team in India? If I cannot do that, all I can say is it is not fair for Enercon India! Dear Mr. Wobben, you have always been my source for inspiration and you have always motivated me, to be able to do my best! Mr. Wobben, I go back to India a disappointed man, as I have no face to show to my family, whom I promised, and who have always supported me for the last 13 years! Mr. Wobben, the decision is in your hands and please do not ask me to talk to anyone else about the issue, because I will not! At the end all I want to say is I trust you. Do not let me down! Regards! Yogesh Mehra."
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 217 jt-comap-315, 314 & 316 -19.doc
263. The Tribunal observed that this reproachful letter was
inconsistent with Mr. Mehra's claim that only a draft had been
signed. None of this recrimination would have made sense if
everything was still open to negotiation. The Tribunal did not
accept the explanation tendered by Mr. Mehra in evidence that
that the agreement which referred in his letter to have signed was
the Agreed Principles and not the IPLA and that he was not to be
taken literally.
264. Perusal of the majority Award reveals that the Tribunal
also formed an adverse opinion on the credibility of Mr. Mehra,
especially in view of his vacillating stand before different forums.
Learned Senior Counsel placed emphasis on the observations of
the Tribunal where the Tribunal noticed that in July 2008 Mr.
Mehra had stated on solemn affirmation in the criminal
proceedings initiated in India before the Court of Magistrate that
he had been coerced into signing the Agreed Principles. It was
observed that there were no allegations of coercion made before
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 218 jt-comap-315, 314 & 316 -19.doc
the Tribunal and rather it was claimed that almost immediately
upon his arrival in Germany Dr. Wobben accepted his objections
to the IPLA and agreed that it should be renegotiated at some
indeterminate future date.
265. The Tribunal was of the considered view that it
appeared that Mr. Mehra was unwilling to execute the IPLA,
however after extensive rounds of deliberations and sustained
obstinacy of Dr. Wobben, he succumbed to sign the IPLA. He
later regretted the execution of the IPLA as Dr. Wobben did not
favourably accede to his proposal of floating an IPO to raise
additional money and neither did Dr. Wobben purchase additional
shareholding from the Mehra's on the tentative terms indicated
earlier during the course of negotiations. In the considered view of
the Tribunal, Mr. Mehra sought to retrace his acts by belatedly
propounding the version that he had merely signed a draft when
he sent an electronic-mail dated 03-11-2006 expressing his
disappointment at the withdrawal of the offer to purchase
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 219 jt-comap-315, 314 & 316 -19.doc
additional shareholding.
266. It was pointed out by Mr Dwarkadas that the Tribunal
also attached significance to the circumstance that the parties
appended their signatures at the spot where they are expected to
be placed when a contract is to be signed with an intent to create
legal obligations and not for the purpose of mere identification for
future reference. It held that though the surrounding
circumstances that the IPLA is referred as a draft in the Agreed
Principles and that the IPLA as executed omitted certain annexes
which had been referred to in the body of the document, were
relevant, yet other circumstances as alluded to by the Tribunal
tilted the scales in favour of the conclusion that the IPLA had been
executed as a concluded contract.
267. Mr Dwarkadas drew attention of the Court to
paragraphs 122, 126, 127, 131, 133 to 139 of the majority Award.
Though we have already ventured to pithily summarise the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 220 jt-comap-315, 314 & 316 -19.doc
reasons upon which the conclusions of the learned Arbitrators
were premised, however, for the sake of completeness, we
reproduce the said paragraphs herein under:
"122. The Tribunal does not accept Mr Mehra's evidence and prefers the evidence of Mr Kettwig. The IPLA had been discussed at length and in detail. Dr Wobben had dealt firmly with Mr Mehra's comments in August 2006 and was expecting that Mr Mehra had come to Aurich to sign the IPLA. That Dr Wobben should now have made a Uturn on Mr Mehra's points seems to the Tribunal highly improbable and is contrary to all other credible evidence. Nor is it probable that Dr Wobben would have been willing to re-open discussion about the 5% royalty agreed in the HoA. There is no credible evidence for this either.
126. The Tribunal has already rejected Mr Mehra's evidence that Dr Wobben agreed that the IPLA required amendment. It finds that Dr Wobben left the meeting having insisted that whatever Mr Mehra and Mr Kettwig put into the Agreed Principles. It should have no effect upon the IPLA, which should be executed as it stood before Mr Mehra left
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 221 jt-comap-315, 314 & 316 -19.doc
Germany. As has already been said, the IPLA had been drafted by in-house lawyers, tax advisers and patent lawyers over a lengthy period. Mr Kettwig was not a lawyer. It was one thing for Dr Wobben to entrust him with the drafting of a non-binding agreement stating the principles upon which the parties were to negotiate agreements still in draft. It was quite another for Mr Kettwig to be authorized to negotiate and agree the terms of a document in English which would amend the finalized IPLA. The Tribunal therefore rejects Mr Mehra's evidence and finds that he understood that the Agreed Principles would have no effect upon the IPLA and that the IPLA was expected to be executed by the Parties during his stay in Aurich.
127. There are various technical points which the Claimants make about the Agreed Principles (e.g. that it was expressed to be made between the shareholders in WWIL and not between the parties to the IPLA) but the Tribunal considers that in the circumstances in which it was drafted and signed, the Agreed Principles could not reasonably have been regarded as having any binding legal effect at all. They were principles,
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 222 jt-comap-315, 314 & 316 -19.doc
not contractual terms. The document was not an independent agreement but an agreement about the contents of agreement which, it was agreed, were still to be negotiated. It contained a statement that the agreed principles "shall be finally incorporated into"
four listed documents, including "IPLA 'Draft enclosed'". Much has been made of this language; and Mr Kettwig, if he had been an astute lawyer, might have foreseen that these words, which were true at the time he took part in drafting the Agreed Principles, could later be said to be inconsistent with Enercon's intention to have the IPLA executed without amendment. The Tribunal considers, however, that what mattered was the intention of the parties, objectively ascertained. The evidence of the relevant surrounding circumstances clearly shows that both sides understood that, before any discussion of other agreements took place, a binding IPLA in the form of the final draft was to be executed by the parties.
131. The Tribunal considers that the suggestion that the parties should have signed the document (in the case of Dr Wobben, twice, on behalf of WPG and Enercon) and initialled every page merely to identify
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 223 jt-comap-315, 314 & 316 -19.doc
it as the latest draft under discussion is highly implausible. It had never been done before by these parties; and was not thought necessary in the case of the drafts of any of the other agreements to which the Agreed Principles were to apply, all of which were available for the same treatment.
133. The Tribunal considers that this reproachful letter is inconsistent with Mr Mehra's evidence that Dr Wobben had immediately accepted that the IPLA needed amendment and that there had been no binding agreement between the parties. Mr Mehra felt strongly that Dr Wobben had behaved unfairly in insisting that he sign the IPLA and in particular in demanding a royalty of 5% "when the agreements do not even provide for any other technologies." The reference to the E-82 is clearly about the IPLA and not Agreed Principles. None of this recrimination would have made any sense if Mr Mehra really thought that everything was still open to negotiation, with the IPLA unexecuted. It is unclear what he meant by saying that he had signed the agreement "without even reading it". He had certainly read every word of the Agreed Principles and he had had a
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 224 jt-comap-315, 314 & 316 -19.doc
fortnight to study the final draft of the IPLA. Perhaps he meant that he did not check whether the execution copy of the IPLA which he signed corresponded with the final draft he had been sent. Perhaps he was a little overwrought".
134. Mr Mehra has tried to explain away his letter, and in particular his statement that he has "signed the agreement" by saying that he meant the Agreed Principles. But that does not explain why, if he had got his way, he was so upset at having done so. Nor does it explain why he said he had not read it. All he can offer is that since he obviously had read it, his statement was "not to be taken literally."
135. The account given by Mr Mehra in his evidence in these proceedings may be compared with the solemn affirmation which he made to the magistrate in July 2008 in India to support a criminal charge of financial fraud which he laid against Enercon, its officers and advisers. Their fraud, he alleged was achieved by:
"inducing and coercing me into signing the "Agreed Principles" dated 29.09.2006 and thereafter mala fide treating a Draft Intellectual
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 225 jt-comap-315, 314 & 316 -19.doc
property License Agreement (IPLA) enclosed thereto as a final and binding agreement, with a view to lowering the profit margin of the Company."
136. Mr Mehra does not now say that he was coerced into signing the Agreed Principles. He accepts that in fact they were his idea. But the allegation is revealing, because, as his letter to Dr Wobben makes clear, coercion is what he was complaining about. He was angry that Dr Wobben had insisted that if the collaboration between Enercon and WWIL was to continue, he had sign the IPLA. This was the coercion that he meant, but Mr Mehra could not say so because it would have been inconsistent with his claim that the IPLA had never been executed at all.
137. In his oral evidence, Mr Mehra was asked what he meant by saying that he had been coerced.
"The Chairman: I think you were asked whether it was true that there had been coercion upon you to sign the agreed principles? A. Well, coercion in the sense there was a lot of pressure when I landed on 29 September 2006.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 226 jt-comap-315, 314 & 316 -19.doc
We have had the discussions and everything was to be done then and there. There was an atmosphere of a lot of tension of course at that point in time.
The Chairman: That, you say, was coercion? A Well, there was pressure,"
138. This evidence is not consistent with Mr Mehra's claim that almost immediately upon his arrival in Germany Dr Wobben accepted his objections to the IPLA and agreed that it should be renegotiated at some indeterminate future date. But the Tribunal considers that it is a great deal nearer the truth. Mr Mehra did not want to sign the IPLA but was put under pressure to do so, to which, with great regret, he succumbed.
139. That night in the Hilton in Bremen Mr Mehra knew perfectly well that he had signed the IPLA and that it had been duly executed. It was only afterwards that, in his own mind, he rewrote the history of what had happened in Germany".
268. With respect to the issue of payment of royalties by
Enercon (India) Ltd. post the execution of IPLA, it was submitted
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 227 jt-comap-315, 314 & 316 -19.doc
by Mr Dwarkadas that the same were unilaterally deposited by
Enercon (India) Ltd. without offering a working sheet of
calculations to suggest the basis of arriving at the figures. Further,
Enercon GmbH has only retained these amounts under protest
and not accepted/acquiesced that they satisfy their rightful claims.
269. Learned Senior Counsel supported the approach
adopted by the majority Arbitrators in quantifying the royalties
and damages. It was pointed to us that the Tribunal proceeded to
act upon the evidence of Mr Nicholas Good; an expert produced
by the Claimants. As a matter of fact, the quantum computed by
Mr Mark Taylor; the expert witness produced by the Appellants
herein was far exceeded the sum suggested by Mr Good.
270. Concluding his submissions, Mr Dwarkadas
submitted that once the learned Tribunal had found that the IPLA
was a concluded contract capable of binding parties, it committed
no error in consequently directing the return of documents and
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 228 jt-comap-315, 314 & 316 -19.doc
materials containing confidential technology as the same clearly
fell in purview of clause 2.11 of the IPLA.
271. Having endowed our anxious consideration to the
submissions canvassed before us, we now proceed to render our
findings on the issues raised during the course of hearing.
FAILURE TO GRANT OPPORTUNITY TO ADDRESS CLOSING ORAL SUBMISSIONS
272. The contention raised by the Appellants on this aspect
is anchored to the proviso appended with Section 24 of the
Arbitration and Conciliation Act, 1996 which mandates that the
Arbitral Tribunal would be obliged to grant oral hearings at an
appropriate stage of proceedings if the same are requested, unless
the parties by agreement have chosen to exclude such hearing.
273. In order to appreciate the rival submissions of the
learned Counsels in this regard, it would be opposite to examine
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 229 jt-comap-315, 314 & 316 -19.doc
the manner in which proceedings were undertaken by the learned
Arbitrators.
274. The chronology of proceedings has been exhaustively
catalogued in paragraphs 25 to 83 of the majority Award. We
extract certain relevant events in the itinerary upon which we
propose to advert our consideration.
275. On 31.07.2014, the parties signed the Terms and
Conditions for the arbitration.
276. On 05.09.2015, the Claimants served an Application
for interim relief, seeking disclosure of various classes of
documents, access to manufacturing sites and to books and
records.
277. On 30.09.2014, the Claimants served their Statement
of Claim.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 230 jt-comap-315, 314 & 316 -19.doc
278. On 13.10.2014, the Respondents served a Response to
the Claimants' Application for interim relief.
279. On 03.11.2014, the Claimants served a Reply to the
Respondents' Response.
280. On 24.11.2014, the Respondents served a Surrejoinder
to the Claimants' Reply.
281. On 13.12.2014, the Tribunal held an oral hearing
concerning the Claimants' Application of 05.09.2014 at the Hong
Kong International Arbitration Centre, Hong Kong, China. The
Claimants were represented by Mr. David Joseph, QC and the
Respondents by Mr Darius Khambatta, SC.
282. On 22.12.2014, the Respondents served their Defence
and Counterclaim.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 231 jt-comap-315, 314 & 316 -19.doc
283. On 09.03.2015, the Claimants served a Reply and
Defence to Counterclaim.
284. On 07.04.2015, the Respondents served a Reply to
the Defence to Counterclaim.
285. On 27.04.2015, the parties each served Requests for
the Production of Documents.
286. On 22.06.2015, the Tribunal issued Procedural
Order No 2, ruling upon the disputed Requests for the Production
of Documents.
287. On 15.09.2015, the Claimants served witness
statements made by Stefan Knottnerus-Meyer, Hans-Dieter
Kettwig and Nicole Fritsch-Nehring. The Respondents served
witness statements made by Girish Paliwal, Yogesh Mehra and
Kaushik Khona.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 232 jt-comap-315, 314 & 316 -19.doc
288. On 25.09.2015, the Claimants served expert witness
reports by Anke Nestler, Nicholas Good, Shashank Karnad and
Salman Khurshid. The Respondents served expert witness reports
by Mark Taylor and Khizer Ahmed, an additional witness
statement by Kaushik Khona and a corrigendum to his earlier
statement by Yogesh Mehra.
289. On 03.11.2015, the Claimants served rebuttal witness
statements by Hans-Dieter Kettwig, Nicole Fritsch-Nehring, Dr
Warner Popkes and Jost Backhaus and rebuttal expert witness
reports by Salman Khurshid, Nicholas Good and Shashank
Karnad. The Respondents served rebuttal witness statements by
Girish Paliwal, Yogesh Mehra and Kaushlik Khona and rebuttal
expert witness reports from Labanyendu Mansingh, Khizer
Ahmed, Rahul Surana and Mark Taylor.
290. On 26.11.2015, the Tribunal held a procedural
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 233 jt-comap-315, 314 & 316 -19.doc
meeting by telephone conference-call with the parties to discuss
the forthcoming oral hearing. The parties also submitted to the
Tribunal their opening submissions in writing.
291. On 27.11.2015, the Tribunal issued Procedural Order
No. 4 setting out the arrangements agreed during the procedural
meeting of 26.11.2015. Since the learned Counsels appearing on
behalf of the appellants have referred this Court to the contents of
this Procedural Order, we reproduce the same in its entirety
hereinunder.
"PROCEDRUAL ORDER NO 4
This order is made following the procedural hearing by telephone on 26 November 2015.
It is ordered that:
1. The hearing commencing on 30 November 2015 shall comprise the hearing of the oral evidence and my oral submissions.
2. The time at the hearing is to be split equally between the parties, save as otherwise allowed at the discretion of the Tribunal. It is a matter for the parties how they allocate their time at the hearing. It
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 234 jt-comap-315, 314 & 316 -19.doc
is envisaged that the parties are like to wish to make oral opening statements of 30 to 40 minutes.
3. The sitting hours for Monday 30 November will be as follows:
(start) 10.00 - 11.30 (morning break) (restart) 11.45 - 1.15 (lunch break) (restart) 2.00 - 3.30 (afternoon break) (restart) 3.45 - 5.15 (finish)
4. At the end of each day, the Tribunal will consider whether the next day should commence at 9.30 a.m.
5. The order of the evidence will be as follows:
1. Ms. Fritsch-Nehring
2. Mr Kettwig
3. Mr. Popkes
4. Mr Backhaus
5. Mr Knottnerus-Meyer
6. Mr Yogesh Mehra
7. Mr Girish Paliwal
8. Mr Kaushik Khona
9. Dr Nestler
10. Mr Surana
11. Mr Salman Khurshid
12. Mr L Mansingh
13. Mr Khizer Ahmed
14. Mr Shashank Karnad
15. Mr Nicholas Good
16. Mr Mark Taylor
6. The Claimants do not maintain an application that the Respondents must elect whether to call either the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 235 jt-comap-315, 314 & 316 -19.doc
evidence of Mr L Mansingh or Mr Khizer Ahmed.
For the avoidance of doubt, the Claimants will not be expected to put matters to one expert that have been put to the other.
7. At the end of the hearing, the Tribunal will make provision for brief written closing to follow and provide direction as to the form that these will take.
8. *[The parties each have a liberty to apply to the Tribunal for another hearing of oral closing submissions, such application to be determined at the discretion of the Tribunal.]
*This point is not agreed. The Respondents' position is that, " It is our understanding that it is open to us to request for an oral hearing in a second session if we so require. The Respondents very clearly wish for the opportunity to make oral arguments, even after the written submissions. That is what they want and will request. It is our understanding that the Presiding Arbitrator did not shut out this point." The Claimants do not believe that this was the outcome of the hearing. The Claimants believe that the Tribunal's view and decision is that the Claimants and Respondents each have 5 days at the hearing to use as they see fit, and that the current hearing constitutes the parties' opportunity to cross-examine and make any oral submissions that they wish to make, to be followed by brief written closing arguments in a form directed by the Tribunal. If the Tribunal is to hear from the parties further, it should be
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 236 jt-comap-315, 314 & 316 -19.doc
because the Tribunal itself identifies that it will assist the Tribunal."
292. A hearing took place at the International Disputes
Resolution Centre, 70 Fleet Street, London EC4Y IEU, United
Kingdom on 30.11.2015 and 1, 2, 3, 4, 7, 8, 9 and 10 December
2015 ( the "Hearing"). The parties were represented as stated in
Part II above. Mr Joseph, QC (for the Claimants) and Mr
Khambatta, SC (for the Respondents) made opening statements;
and the following factual and expert witnesses were cross-
examined: Nicole Fritsch-Nehring, Hans-Dieter Kettwig, Warner
Popkes, Jost Backhaus, Stefan Knottnerus-Meyer, Yogesh Mehra,
Girish Paliwal, Kaushik Khona, Anke Nestler, Rahul Surana,
Salman Khurshid, Labanyendu Mansingh, Khizer Ahmed,
Shashank Karnad, Nicholas Good and Mark Taylor.
293. On 11.12.2015, the Tribunal issued Procedural Order
No 5 by which the evidential record was declared closed, save for
the issue of whether the Mehra directors had been in breach of
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 237 jt-comap-315, 314 & 316 -19.doc
fiduciary duty and/or the SHA is connection with transactions
between WWIL and Vish Wind Infrastrucre LLP and other
entities ("the Vayuu Companies") which they controlled. The
Order set out an agreed timetable for the disposal of this issue and
the closing statements in the arbitration. We have already
reproduced Procedural Order No.5 in its entirety at paragraph 217
of our Judgment and, therefore, we refrain from doing the same
again.
294. On 13.12.2015, in accordance with the timetable in
Procedural Order No 5, the Claimants applied for the production
of documents relating to the Vayuu Companies and injunctive
relief pursuant to section 17 of the Indian Arbitration and
Conciliation Act 1996.
295. On 15.12.2015, Mr Darius Khambatta, learned Senior
Counsel and Dr Abhinav Chandrachud, learned Counsel
informed the Tribunal that they were no longer representing the
Respondents.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 238 jt-comap-315, 314 & 316 -19.doc
296. On 16.12.2015, AZB Partners informed the Tribunal
that they were no longer representing the Respondents.
297. On 22.12.2015, Mr Yogesh Mehra, on behalf of the
Respondents, requested the Tribunal to extend the period for a
reply to the application for document production and injunctive
relief for four weeks.
298. On 24.12.2015, the Tribunal issued Procedural Order
No. 6 by which (subject to receiving certain undertakings from the
Mehra directors) it extended the period for a reply to the
Claimants' application until 21.01.2016 and made further
adjustments to the timetable laid down in Procedural Order No 5.
299. On 06.01.2016, Hariani & Co informed the Tribunal
that they were now representing the Respondents.
300. On 07.01.2016, the Respondents applied for a further
extension of 12 weeks to reply to the Claimants' application.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 239 jt-comap-315, 314 & 316 -19.doc
301. On 09.01.2016, the Claimants opposed the grant of a
further extension.
302. On 03.02.2016, the Tribunal made Procedural Order
No. 7, by which it extended to 26.02.2016 the time for the
Respondents to reply to the Claimants' application and made
other adjustments to the timetable in Procedural Order No 5.
303. On 09.02.2016, the Respondents applied for further
extensions of the timetable in Procedural Order No. 7. The
Claimants opposed the requested extensions.
304. On 14.02.2016, the Tribunal gave directions by which
it modified but substantially maintained the timetable in
Procedural Order No. 7.
305. On 18.02.2016, the Respondents applied for
extensions of the timetable in Procedural Order No. 7, as
modified.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 240 jt-comap-315, 314 & 316 -19.doc
306. On 14.04.2016, the Respondents applied for an
extension of the time for filing closing submissions and for a
further oral hearing.
307. On 15.04.2016, the Respondents submitted a further
factual witness statement by Kaushik Khona.
309. On 18.04.2016, the Respondents submitted an expert
witness report by D. Vaidyanathan.
310. On 20.04.2016, the Claimants notified the Tribunal
that they did not wish to cross-examine Kaushik Khona or D.
Vaidyanathan.
311. On 20.04.2016, the Tribunal directed that the
evidence of Kaushik Khona and D. Vaidyanathan be admitted into
the evidential record, that the evidential record be declared closed,
that the time for exchange of closing submissions be extended to
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 241 jt-comap-315, 314 & 316 -19.doc
13.05. 2016 and that the hearing provisionally fixed by Procedural
Orders Nos 5 and 7 for 27-28.04.2016 be cancelled.
312. On 22.04.2016, the Respondents made a further
application for extension of the time in which to serve closing
submissions and for an oral hearing.
313. On 22.04.2016, the Tribunal refused the
Respondent's application of 22.04.2016 and directed that no
further submissions on the timetable should be made, with the
provisional hearing of 27-28.04.2016 remaining cancelled.
314. On 11.05.2016, the Respondents notified the Tribunal
that their closing submissions would not be ready until
25.03.2016.
315. On 13.05.2016, the Claimants served their closing
written submissions.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 242 jt-comap-315, 314 & 316 -19.doc
316. On 25.05.2016, the Respondents served their closing
written submissions.
317. At the outset, we notice that upon the completion of
pleadings and exchange of statements of witnesses, the Tribunal
accorded an opportunity for an oral hearing to the parties in
London before the commencement of evidential hearings.
'Opening statements' /submissions were addressed by learned
Counsels representing the parties.
318. During the course of recording evidence, whilst Mr.
Yogesh Mehra was under cross-examination, financial statements
of Vish Wind were required to be produced under the directions
of the Tribunal. The documents revealed high value transactions
between WWIL and Vish Wind, which also took the learned
Counsels representing the Appellants-herein by surprise. The
relevant extracts from the transcript of Day 9 of the Proceedings
dated 10.12.2006 are reproduced herein below.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 243 jt-comap-315, 314 & 316 -19.doc
"Enercon & Wobben v WWIL & Ors. [Master] Day 9
207: 1 Housekeeping 2 THE CHAIRMAN: Well, now, Let's discuss where we go from 3 here.
4 Do you want to deal now with the question of the 5 breach of fiduciary claim, or do you want to leave that 6 over to tomorrow morning?
7 MR KHAMBATA: Let me put it this way: I still haven't 8 received any instructions on that aspect. 9 THE CHAIRMAN : Yes.
10 MR KHAMBATA: I am not sure I will receive them by tomorrow 11 morning either, I must be candid with the bench. But 12 let me give the client a chance overnight, if he has any 13 instructions. I think I must give him that sort of 14 time, since we do have tomorrow.
15 MR CHAIRMAN: Very well, yes.
16 MR KHAMBATA: I should also make one thing clear, and 17 I think it is better I do it today, rather than 18 tomorrow. We did request your Lordships for time to 19 make oral closing submissions, either at a separate 20 session or, as your Lordship decided, within these
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 244 jt-comap-315, 314 & 316 -19.doc
21 10 days.
22 THE CHAIRMAN: Yes.
23 MR KHAMBATA: I must confess that if I don't have adequate 24 instructions on this aspect of the matter, I pretty much 25 can't make any oral closing submissions on the related
208: 1 party issue at all.
2 THE CHAIRMAN: No. 3 MR KHAMBATA: Because I don't want to sort of improvise.
4 That is out of the question.
5 THE CHAIRMAN : No. 6 MR KHAMBATA: In which case, I am perfectly willing to make 7 some closing oral submissions on other aspects of the 8 case, would you like to do it that way or - I am perfectly happy to do it that way, or to file detailed 10 written submissions -
11 THE CHAIRMAN : Yes.
12 MR KHAMBATA: - on the state of the record as it is now.
13 THE CHAIRMAN: Yes, which would you prefer? Do you want to 14 be able to have the opportunity, say, to lunchtime 15 tomorrow to address us on the other -
16 MR KHABATA: On some parts of the evidence. 17 THE CHAIRMAN : Is that what you would prefer? 18 MR KHAMBATA: Could I take that decision and tell
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 245 jt-comap-315, 314 & 316 -19.doc
19 your Lordships tomorrow morning.
20 THE CHAIRMAN : All right.
21 MR KHAMBATA: Because I will have to see (1) whether I get 22 any instructions and, if I don't, whether it is really 23 worth my while, not addressing that aspect and 24 addressing other aspects.
25 THE CHAIRMAN: Yes, I see."
(Emphasis Supplied)
319. We may observe that at this stage of proceedings the
learned Senior Counsel representing the Appellants-herein before
the Arbitral Tribunal did remind the learned Arbitrators that a
request had been made on their behalf to address closing oral
submissions, however in wake of the recent developments he was
not prepared to make closing oral submissions on the aspect of
related party transactions at all owing to absence of adequate
instructions. The learned Senior Counsel proposed that either he
could address the Tribunal by making closing oral submissions on
other aspects of the case or he could file detailed written
submissions. The learned Senior Counsel thereafter requested the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 246 jt-comap-315, 314 & 316 -19.doc
learned Arbitrators to defer the proceedings till next morning in
order to enable him to decide the course he intended to adopt after
receiving instructions, if any. Upon his request, the proceedings
stood adjourned for next morning i.e. 11.12.2015.
320. The crucial events which transpired on the next
session held on 11.12.2015 come to the fore from a perusal of the
relevant transcript that was prepared and the contents of which in
all fairness have never been disputed. The relevant portions of the
transcript of Proceedings dated 11.12.2015 are extracted
hereunder.
"...
The Chairman : "I assume we are not necessarily committed to an oral hearing at all?".
Mr Khambata : No, I understand.
The Chairman : It may be that no one wants to cross examine and then we just do it.
Mr Joseph: I think Lord Hoffmann, you are absolutely right. We are not committing ourselves, and I think, maybe we said closing
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 247 jt-comap-315, 314 & 316 -19.doc
submissions, if any are requested, or something along those lines.
The Chairman : Yes.
Mr Khambata : Yes, that would give us the opportunity to go back and make an appropriate application for oral submissions.
Mr Joseph : If any is required and that again would not commit the Tribunal to acceding to the request, if the request were made.
Mr Khambata : Of course not. Of course not.
..." (Emphasis Supplied)
321. The inescapable conclusion which emerges from the
perusal of the said transcript is that Mr. Khambatta, learned Senior
Counsel representing the Appellant's-herein before the Arbitral
Tribunal did concede that he was not necessarily committed to
address closing oral submissions and more significantly acceded
the position that in the eventuality such a request were made, it
would lie within the discretion of the Tribunal to accept such a
request or not. We regret that we are unable to subscribe to the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 248 jt-comap-315, 314 & 316 -19.doc
submission urged by Mr. Mehta that such statements made by
learned Counsels during a polite verbal interchange with the
Bench could not be construed as a waiver. As a matter of fact, it
would rather be inconceivable to contend the same in the case at
hand in as much as the Appellant's-herein were ably represented
by an eminent Senior Counsel who is expected to make statements
upon instructions with utmost responsibility. The Courts of
Justice, including such private dispute resolution mechanisms,
proceed to act upon the statements made by the learned Counsels
during the course of proceedings, as agents of the parties who they
represent.
322. We find that it was under these attending
circumstances that the Tribunal proceeded to pass Procedural
Order No.5 on 11.12.2015 fixing a proposed calendar enumerating
the timeline to be adhered by the parties. Item No.9 of the
Procedural Order No. 5 clearly recorded the fact that opportunity
for Closing Oral Submissions would be accorded only if
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 249 jt-comap-315, 314 & 316 -19.doc
determined to be necessary by the Tribunal. It is palpable from the
opening lines of the Order itself that it was formulated upon clear
agreement between the parties as expressed by their lawyers. The
said position stands corroborated by the verbal interchange
between the learned Arbitrators and the counsels, as
contemporaneously recorded in the transcripts we referred above.
We have already noticed that Mr. Khambatta, learned Senior
Counsel did accede to the position that in the eventuality a request
for oral submissions was made, it would lie within the discretion of
the Tribunal to accept such a request or not. The submission of
Mr. Mehta that the relevant entry contained at S.No. 9 of
Procedural Order No. 5 was not based on consensus arrived at
between the parties but in the nature of directions cannot be
countenanced. It assumes significance that no demur was raised on
this count was raised at that time or immediately thereafter. As
taken note of by us in the preceding paragraphs, on an earlier
occasion when objections were expressed by the Appellant's-herein
at the time of recording Procedural Order No.4, a note of
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 250 jt-comap-315, 314 & 316 -19.doc
disagreement faithfully reflecting the said objections was inserted
therein. We find no objections or a challenge having been
contemporaneously mounted upon Procedural Order No. 5 to
suggest that it was premised upon the incorrect understanding of
the statements made by legal practitioners during the Proceedings.
We extrapolate the said Procedural Order in its entirety.
"The following Timetable is agreed between the parties:
Sr. No. Particulars Date 1 Claimants to file an Application 13 Dec 2015 under Sec 17 of the Arbitration & Conciliation Act 1996 2 Respondents to file their Reply 19 Dec 2015 to the Claimants Application under Sec 17 of the Arbitration & Conciliation Act 1996 3 Respondents to respond to the 15 Dec 2015 Claimants request for production of documents set out at Annex A 4 Tribunal to make a ruling on the 23 Dec 2015 Claimants Application (i) under sec. 17 of the Arbitration and Conciliation Act 1996 & (ii) in relation to any disputed item in Annex A
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 251 jt-comap-315, 314 & 316 -19.doc
5 Respondents to provide any 4 January 2016 documents/information in accordance with (3) and (4) Above 6 An Application to the Tribunal, 18 January 2016 if either party seeks to adduce further evidence responsive to the Vish Wind Infrastructure LLP documents or the new documents produced at (5) above 7 An Application to cross examine 25 January 2016 or respond to the evidence adduced pursuant to (5) above 8 Exchange of Closing Written 16 March 2016 submissions 9 Any oral evidence in 27 & 28 April 2016 accordance with (7) above in and London. Closing oral submissions if any are requested and if determined necessary by the Tribunal." (Emphasis Supplied)
323. It had been urged by Mr. Shyam Mehta and Dr.
Birendra Saraf, learned Counsels for the Appellants that the
transcript of Proceedings for Day 10 dated 11.12.2015 must be
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 252 jt-comap-315, 314 & 316 -19.doc
read in backdrop of the Proceedings conducted on Day 9 dated
10.12.2015 wherein request for oral hearing had been made by
Mr. Khambatta, the learned Senior Counsel representing the
Appellants-herein before the Tribunal and therefore waiver of the
right to oral hearing ought not to be lightly inferred from the
statements exchanged on the subsequent date i.e. Day 10 of
evidential hearings on 11.12.2015.
324. As discussed by us in paragraphs 318-319, a careful
reading of the transcript of Proceedings dated 10.12.2015 would
reveal that the learned Senior Counsel representing the
Appellants-herein did remind the learned Arbitrators that a
request had been made on their behalf to address closing oral
submissions, however in wake of the recent developments he was
not prepared to make closing oral submissions on the aspect of
related party transactions at all owing to absence of adequate
instructions. The learned Senior Counsel proposed that either he
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 253 jt-comap-315, 314 & 316 -19.doc
could address the Tribunal by making closing oral submissions on
other aspects of the case or he could file detailed written
submissions. The transcripts suggest that even on the said date the
learned Senior Counsel had himself offered the alternative
recourse of submitting Written Submissions instead of closing oral
hearing. It would thus emerge that he had no instructions to adopt
a hardened position committed to an Oral hearing. Further, as
held by us the Procedural Order No. 5 was made the following day
i.e on 11.12.2015 upon the consent of parties, and the same is
consistent with the contents of the verbal interchange that took
place between the learned Arbitrators and the Counsels which was
contemporaneously recorded in a transcript. The contents of the
transcript of Proceedings dated 11.12.2015 clearly establish that
the prior intention to the contrary, even if any, stood superseded
by the unequivocal and unambiguous submission by the learned
Senior Counsel to the discretion of the Tribunal to determine the
requirement of Closing Oral Hearing.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 254 jt-comap-315, 314 & 316 -19.doc
325. We may also note that even the Solicitors that were
inducted subsequently and entered appearance on behalf of the
Appellants-herein on 07.01.2016 did not assert an indefeasible
right to make Closing Oral Submissions. Rather consistently
intent was expressed to apply to the Tribunal and ' to take leave' to
make such submissions. Various communications addressed by
their Solicitors to the Tribunal including the communication
dated 09.02.2016, 14.04.2016, 22.04.2016 and 11.05.2016
evidence that in view of the concessions made by erstwhile
counsel(s) they clearly understood the purport of Procedural
Order No. 5 to mean that the ' discretion now vested with the
Tribunal' to rule upon a request for closing oral submissions. As
rightly pointed by Mr. Chinoy, it was only on 25.05.2016 that the
Solicitors representing the Appellants-herein belatedly for the first
time asserted that they had a right to closing oral hearing in terms
of proviso to Section 24(1) of the Arbitration and Conciliation
Act, 1996 and that the parties had not excluded such a right. The
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 255 jt-comap-315, 314 & 316 -19.doc
said request was promptly rejected by the Tribunal on 26.05.2016
by highlighting that the Procedural Order No. 5 was made by
consent of parties and it expressly recorded the fact that closing
oral submissions would be granted only if requested and
determined to be necessary by the Tribunal.
326. This Court has microscopically examined the calendar
of proceedings, transcripts of discussions and various Procedural
Orders passed by the Tribunal in order satisfy its conscience and
ascertain if the Appellant's-herein were deprived of any legitimate
right(s) to present their case and if closing oral submissions, under
the circumstances, were wrongly denied.
327. We find that the procedure adopted by the Tribunal
was transparent and reasonable. Repeated accommodations were
granted in favour of the Appellants-herein by the extending time-
lines. The Tribunal was considerate to accede to such requests in
view of the fact that the legal team of Counsels and Solicitors
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 256 jt-comap-315, 314 & 316 -19.doc
representing the Appellants-herein withdrew from the case on 15-
16.12.2015.
328. Procedural Order No. 5 was subsequently modified by
Procedural Order No. 7 dated 03.02.2016 at the instance of the
Appellants-herein. The date of exchange of Closing Written
Submissions was extended from 16.03.2016 to 22.04.2016.
329. However, even after Procedural Order No. 7 further
extensions were sought by the Solicitor's vide communication
dated 09.02.2016 addressed to the learned Arbitrators. Extension
of time till 30.06.2016, inter alia, was sought for filing closing
written submissions. Vide communication dated 14.02.2016 the
Tribunal responded to the Solicitors representing the Appellants-
herein and underscored the need for submission of closing written
submissions in the prescribed time so that the Tribunal could
determine the request of granting closing oral submissions, if any.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 257 jt-comap-315, 314 & 316 -19.doc
330. The issue precipitated further and vide
communication dated 18.02.2016 the Solicitors persisted with
their request seeking extension of time for submitting closing
written submissions and asserting that the same causes " severe
prejudice".
331. It was owing to such repeated requests for extensions
that the dates of 27-28 April 2016 initially reserved for possible
Closing Oral Submissions had to be cancelled by the Tribunal
vide communication dated 20.04.2016 as the Appellants-herein
had already indicated they were not in the position to submit their
Closing Written Submissions in the stipulated time and had thus
sought further extensions. The Tribunal extended the time for
exchange of Closing Written Submissions to 13.05.2016.
332. We note that the Appellants-herein ultimately
submitted their Closing Written Submissions only on 25.05.2016
again breaching the extended deadline fixed for 13.05.2016. It is
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 258 jt-comap-315, 314 & 316 -19.doc
evident that under such circumstances the Tribunal no longer had
the opportunity to peruse the written submissions in advance and
determine the necessity, if any, of permitting Closing Oral
Hearing.
333. As a matter of fact, the laxity on part of the Appellants
themselves in failing to submit the Closing Written Submissions in
the prescribed time disabled/precluded the Tribunal from
determining the request of Closing Oral Hearing after having had
the benefit of perusing the closing written submissions, as was
contemplated under Procedural Order No. 5 (as amended by
Procedural Order No.7). Thus, the grievance expressed by Mr.
Mehta that the Tribunal erred in hastily rejecting the request for
closing oral hearing without considering the closing written
submissions cannot be accepted.
334. We may note that what would be the scope and
amplitude of 'oral hearing', as envisaged under Section 24 of the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 259 jt-comap-315, 314 & 316 -19.doc
Arbitration and Conciliation Act, 1996 was not argued before us.
The Tribunal in its ruling dated 26.05.2016 observed that oral
hearings were provided to the parties in December 2014 and
November-December 2015. It was further observed that Section
24 of the Act, 1996 could not be construed in a manner that a
party could virtually dictate to the Tribunal the number of
hearings it necessarily desired.
335. We observe that whatever be the amplitude of rights
conferred under proviso to Section 24 of the Act, 1996, yet the
said proviso itself recognizes waiver of such rights by agreement.
In the case at hand, we have already found that the learned Senior
Counsel representing the Appellants-herein consciously waived
the absolute right/prerogative vested under proviso to Section 24
of the Act and surrendered the same to the by subjecting it to the
discretion of the Tribunal. In view of such express surrender by the
learned Counsels representing both the parties, it legitimately fell
within the province of discretion of the Arbitral Tribunal as
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 260 jt-comap-315, 314 & 316 -19.doc
envisaged under Section 24(1) of the Act, 1996 to determine the
necessity of closing oral submissions. Thus, we conclude that there
is no infraction of proviso to Section 24 of the Act, 1996.
336. This Court has examined this cardinal issue
from another alternate standpoint to judge whether the
Appellants-herein suffered any possible prejudice stemming from
absence of such hearing and if the same resulted in violation of the
principles of natural justice. Having perused the exhaustive
Closing Written Submissions submitted on behalf of the
Appellants-herein before the Tribunal, we find that all issues,
including the issue of Third Party transactions-Vish Wind were
comprehensively contested. No prejudice could be demonstrated.
337. At any rate, the moot question- 'Whether 'oral
hearing' as contemplated under proviso to Section 24 of the Act,
1996 would necessarily enwomb within its fold the unfettered
right to insist upon addressing such closing oral submissions, need
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 261 jt-comap-315, 314 & 316 -19.doc
not be gone into as the same has not been argued and more
significantly even if such a right exists in law the same
unquestionably stood extinguished by agreement.
WHETHER THE DISPUTES RELATABLE TO THE SHA WHICH INCLUDED THE `VISH WIND' TRANSACTIONS WERE ARBITRABLE
338. The Supreme Court in paragraph 144 of its judgment
dated 14.02.2014 (paragraph 153 of the report of its decision as
contained in SCC) passed directions to refer all disputes arising
between parties in relation to various agreements, inter alia, the
SHA to arbitration. We have already recorded in paragraphs 18-32
of this judgment the spate of litigation which ensued between the
parties ultimately culminating before the Supreme Court wherein
these directions came up to be passed. For instilling clarity in our
discussion, we reproduce paragraph 144/153 herein-under.
"153. For the reasons recorded above, Civil Appeal No.2087 of 2014 @ SLP (C) No.10906 of 2013 is
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 262 jt-comap-315, 314 & 316 -19.doc
dismissed. The findings recorded by the Appellate Court that the parties can proceed to arbitration are affirmed. The findings recorded by the Trial Court dismissing the Application under Section 45 are set aside. In other words, the Application filed by the Respondents for reference of the dispute to arbitration under Section 45 has been correctly allowed by the Appellate Court as well as by the High Court. The findings of the High Court are affirmed to that extent. All the disputes arising between the parties in relation to the following agreements viz. SHA, TKHA, SSHAs and STKHA, Agreed Principles and IPLA, including the controversy as to whether IPLA is a concluded contract are referred to the Arbitral Tribunal for adjudication."
(Emphasis Supplied)
339. At the outset, we must observe that the directions are
clear and unambiguous.
340. It has been urged by Dr Saraf, learned Counsel
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 263 jt-comap-315, 314 & 316 -19.doc
appearing on behalf of the Appellant's-herein that the arbitral
clause comprised under the SHA (Clause 16) contemplated
reference of disputes arising thereunder for arbitration before the
Indo-German Chamber of Commerce. On the strength of this
circumstance, it was submitted that the Supreme Court would
never have intended to subject the disputes arising under the SHA
to be part of the reference for arbitration made by it under the
IPLA. As noted by us in paragraphs 170-175, Dr. Saraf had
labored to highlight that what had arisen for the consideration of
the Supreme Court was the application under Section 45 of the
Act, 1996 filed by Enercon GmbH in the 'Daman Suit'and it was
arbitral clause under the IPLA which had sought to be invoked.
341. We have endowed anxious consideration to the
submissions of Dr. Saraf with regard to the interpretation of the
directions of the Supreme Court comprised in Paragraph 153 of
the report of its judgment. A meaningful reading of the decision of
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 264 jt-comap-315, 314 & 316 -19.doc
the Supreme Court in its entirety makes it evident that the Court
proceeded to comprehensively refer the entire spectrum of
disputes for arbitration in view of the fact that the said disputes
had been precipitating for nearly a decade before different forums
and inordinate delays had occasioned. As is pellucid from a bare
perusal of paragraph 154 of the judgment, in the peculiar facts of
the present case, with a view to mitigate further delays, the Court
itself proceeded to nominate the Third Arbitrator.
342. The Supreme Court in paragraph 80 (SCC) of the
report of its judgment also noticed the circumstance that each of
the agreements- IPLA, HoA, SHA, TKHA comprised arbitral
clauses and thus there was a clear 'intention to arbitrate'.
Significantly, the Court observed that the parties were involved in
"unnecessarily complicated and convoluted proceedings". In
paragraph 94 (SCC) the Court expressed its disapproval to the
approach adopted by the Appellant's-herein in lingering on with
the disputes and remarked that the attitude of the Appellants-
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 265 jt-comap-315, 314 & 316 -19.doc
herein was to avoid arbitration at all costs.
343. In this context, the submission of Mr. Kadmar cannot
be brushed aside that the directions passed by the Supreme Court
in the case at hand were somewhat akin to its approach in an
earlier pronouncement reported as (2013) 1 SCC 641 Chloro
Controls India Private Ltd. v. Severn Trent Water Purification Inc ,
which was incidentally cited by the all the three learned Senior
Counsels before the Supreme Court in another context.
344. The Supreme Court in Chloro Control's case (Supra)
pertinently observed that when several parties are involved in a
dispute, it is usually considered desirable that the dispute should
be dealt with in the same proceedings rather than a series of
separate proceedings as it saves time, money and avoids possibility
of conflicting decisions [Paragraphs 86-89]. Significantly, a keen
perusal of the dictum in Chloro Control's case (Supra), in
particular paragraphs 150-153, would evince that even in the said
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 266 jt-comap-315, 314 & 316 -19.doc
case Court had taken note of the fact different arbitral forums were
prescribed under different agreements. Repelling this perceived
road-block the Court proceeded to make a composite-reference
arbitration in the said case as it was observed that in essence there
was an underlying intent under the various agreements to settle
the disputes by arbitration and as long as the alternative recourse
contemplated under some of the agreements had not been opted
by the parties, such a reference could always be made under the
mother/principal agreement.
345. We find that the Terms and Conditions of Tribunal's
Appointment also expressly contained reference to the directions
passed by the Supreme Court in its judgment dated 14.02.2014.
346. It had also been initially submitted during the course
of hearing by Dr. Saraf that the Supreme Court in its judgment
dated 14.02.2014 granted stay of various proceedings pending
before different Courts, however, the Court in its wisdom
consciously chose not stay the CLB proceedings. It was sought to
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 267 jt-comap-315, 314 & 316 -19.doc
be submitted that the disputes stemming from the SHA were
subject matter of the proceedings before the CLB and the said
circumstance would evidence that the Supreme Court did not
intend to bundle the disputes relatable to the SHA to the present
arbitration under the aegis of the IPLA. Countering the said
submission, it was pointed out on behalf of the Respondents-
herein that at the relevant time of passing judgment when the
Supreme Court was in seisin of the matter proceedings before the
CLB had already concluded and statutory appeals u/s 10F
Companies Act, 1956 were pending before the Bombay High
Court. Thus, there was no occasion to stay proceedings before the
CLB. In view of the said clarification, Dr. Saraf molded his initial
submission and contended that nonetheless, the Supreme Court
could have granted stay of the proceedings in Appeal. In this
regard it was highlighted by Mr. Kamdar that the ambit of CLB
proceedings was not restricted to merely disputes under SHA but
also enwombed within its fold disputes arising from unauthorized
amendment of Articles of Association and other breaches of other
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 268 jt-comap-315, 314 & 316 -19.doc
statutory rights/duties under the Companies Act, 1956 that were
not the subject matter of arbitration . Therefore, the two
proceedings though admittedly having some overlap could be
permitted to operate concurrently in their own spheres.
347. We hasten to observe that the directions comprised in
paragraph 153 of the judgment of the Supreme Court are categoric
and unambiguous. The attending circumstances in which the said
directions were passed have already been adverted by us in the
paragraphs 340-344 of this judgment. This Court cannot be
expected to second-guess the reasons which may have impelled the
Supreme Court not to injunct the proceedings in Section 10F
Company Appeals pending before this Court. It cannot be ruled
out that the Supreme Court was of the considered view that the
ambit of the Company Law Board proceedings was wider and
beyond the disputes relatable to SHA and therefore, it would have
been inappropriate to interfere with the said proceedings. In this
context, it would be pertinent to note that the CLB vide its Order
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 269 jt-comap-315, 314 & 316 -19.doc
dated 29.10.2007 whilst rejecting the Company Application No.
484 of 2007 preferred under Section 8 of the Act, 1996 by the
Appellant's-herein seeking reference to arbitration in terms of the
SHA, itself observed in paragraph 10 of its Order that some of the
allegations before the CLB could not be traced to the terms of
SHA. At any rate, the unequivocal directions contained in
paragraph 153 of the judgment of the Supreme Court cannot be
dislodged by a tenuous process of drawing a speculative inference
from what the Court did not choose to do. Such a process of
interpretation would be hazardous, to say the least and cannot be
countenanced.
348. It would be pertinent to highlight that, as a matter of
fact, the plea that the Supreme Court did not refer the disputes
relatable to the SHA was never raised by the Appellant's-herein
before the Arbitral Tribunal at any stage of the proceedings. The
Tribunal was merely called upon to exercise its discretion not to
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 270 jt-comap-315, 314 & 316 -19.doc
pronounce upon the matters relatable to SHA as the same were
also pending adjudication before the CLB and would result in
duplication of proceedings/possibility of conflicting findings. It
assumes significance that that what was urged before the Tribunal
was the plea that exercise of such jurisdiction would result in
duplication of proceedings and not that the Tribunal inherently
lacked jurisdiction as the Supreme Court did not intend to refer
disputes arising from the SHA. Reference was made by Mr.
Kamdar to paragraphs 83-85, 150 of the Statement of Defence,
Paragraphs XII (A)-(D) of the Written Opening Submissions and
Paragraph 139 of the Written Closing Submissions to demonstrate
the nature of objections raised before the Tribunal.
349. We may note that the entire thrust of arguments
before this Court has been that the judgment of the Supreme
Court dated 14.02.2014 did not intend to clothe the Arbitral
Tribunal the jurisdiction to deal with disputes relatable to SHA.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 271 jt-comap-315, 314 & 316 -19.doc
The alternative contention of Dr. Saraf that even if the
jurisdiction to deal with such disputes was conferred upon the
Arbitral Tribunal by the Supreme Court yet, the Tribunal ought to
have refrained from exercising such jurisdiction was not developed
before us and no material in support thereof was placed.
350. The plea that at an earlier stage of proceedings before
the CLB Enercon GmbH had itself resisted the application
preferred by the Appellants-herein for reference to arbitration
pales into insignificance in view of the supervening circumstance
that ultimately the Supreme Court directed all the disputes,
including those arising under the SHA to be referred for
arbitration.
351. In view of the discussion as contained in the
preceding paragraphs, this Court is of the considered view that the
disputes relatable to SHA were required to be adjudicated by the
learned Arbitrators in terms of the directions of the Supreme
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 272 jt-comap-315, 314 & 316 -19.doc
Court in its judgment dated 14.02.2014 and no exception can be
taken on that count.
WHETHER THE AWARD QUA VISH WIND TRANSACTIONS IS LIABLE TO BE SET ASIDE OWING TO INSUFFICIENT PLEADINGS
352. It had been contended by Mr. Shyam Mehta, learned
Senior Counsel appearing on behalf of the Appellants that the
majority Arbitrators fell in grave error by proceeding to make an
Award with respect to Third Party transactions, more specifically,
the sale of development rights by Vish Wind to WWIL in view of
the fact that necessary averments in the pleadings of the Claimants
were clearly lacking which resulted in a complete failure to raise
the foundation of claim with respect to Third Party transactions.
353. In order to appreciate the submissions of Mr. Mehta,
we embark upon our quest to ascertain the nature of claims raised
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 273 jt-comap-315, 314 & 316 -19.doc
by the Respondents-herein (Claimants) before the Arbitral
Tribunal at different stages of the proceedings and whether the
same were backed by statement of material facts/concrete
particulars in support thereof.
354. We commence by analysing the Statement of Claim;
which triggered the pleadings. As highlighted by Mr. Chinoy, in
Para 96.2 and Para 96.3 of Part H of the Statement of Claim it had
been specifically claimed that Vaayu Companies had been set up
for exploiting the technology of the Claimant's and value was
transferred from WWIL to such companies. The relevant portions
of the same have been reproduced by us earlier while taking note
of the submissions addressed by Mr. Chinoy. However, for the sake
of coherence, we extract the same hereunder.
Para 96.2 of Part H of the Statement of Claim
"...set up the Vaayu Companies for the purpose of receiving and exploiting the Claimants technology
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 274 jt-comap-315, 314 & 316 -19.doc
and/or have assisted the Vaayu Companies in receiving and/or exploiting the Claimants technology and/or have transferred value from WWIL to the Vaayu companies, such also constitutes breaches of Mr Yogesh Mehra and/or Ajay Mehra's obligations under the SHA and/or Indian law, including their duties of good faith, which has caused loss to the claimants and for which the claimants are entitled to damages to be assessed and/or an account of profits, plus interest...".
(Emphasis Supplied)
Para 96.3 of Part H of Statement of Claim
"...The loss caused to Enercon by Mr Yogesh Mehra and/or Mr Ajay Mehra's breach of their duties under the SHA and/or under Indian Law, including their obligations of utmost good faith, trust, confidence and commitment towards Enercon, include the damage caused to the value of Enercon's shareholding in WWIL and Enercon is entitled to Damages (to be assessed) plus interest, in regards to this loss. Further and alternatively, Enercon
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 275 jt-comap-315, 314 & 316 -19.doc
is entitled to an account of profits plus interest, in relation to Mr Yogesh Mehra and/or Mr Ajay Mehra's breach of their duties of utmost good faith, trust, confidence and commitment towards Enercon..."
(Emphasis Supplied)
The Prayer Clause (I)(c) comprised in the Statement of Claim
reads as follows:
"(1) In respect of Mr Yogesh Mehra and Mr Ajay Mehra's breaches of the SHA :
(a) .. .. ..
(b) .. .. ..
(c) An order that Yogesh Mehra and Mr Ajay Mehra pay damages (to be assessed) and/or an account of profits for their breaches of the SHA and/or duties arising as a matter of Indian Law."
(Emphasis Supplied)
355. A keen perusal of the Statement of Claim also reveals
that the Claimant's furnished a list of 33 entities appended as
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:01 ::: Jdk/pdp 276 jt-comap-315, 314 & 316 -19.doc
'Annex B' to the Statement of Claim. The Claimants suspected
unauthorized dealings of WWIL with these entities. The said
entities were collectively referred as the " Vayuu
Companies/Partnerships". We note that Vish Wind Infrastructure
LLP figures at S.No. 12 of the said list.
356. We observe that the Statement of Claim did contain a
generic averment to the effect that the Mehra's had transferred
value from WWIL to the Vaayu Companies in breach of their
obligations under the SHA and/or Indian Law. Further, it had
been prayed that the Mehra brothers be held liable to pay damages
and/or account for the profits made by such transfer.
However, the Statement of Claim fell short of
disclosing any concrete particulars of the manner of such
unauthorized transfer of value was effected. As observed by us
earlier in paragraph 205, the Statement of Claim merely voiced
the apprehensions under which the Claimant's were laboring as
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 277 jt-comap-315, 314 & 316 -19.doc
they were in dark about the affairs of WWIL. Perhaps as a mark of
abundant caution, they did make speculative pleadings to this
effect so as to leave room for the possibility of exploring the issue
further. As events would subsequently unravel, the instinctive
premonition and apprehension of the Claimant's did turn out to
be correct.
357. As demonstrated by Mr. Chinoy, actionable
information with regard to such transactions had started to trickle
in sometime around September 2015 in view of the disclosures
made by the Appellants-herein pursuant to Procedural Order
No.2 dated 22.06.2015 passed by the Tribunal. Documents prima
facie revealed that transactions to the tune of Euro 124 million
had taken place between WWIL and Vish Wind. It was pointed
out that even at this stage, financial statements of the Vaayu
Companies were withheld by the Mehra's.
358. The Claimant's pursued their apprehension of
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 278 jt-comap-315, 314 & 316 -19.doc
unauthorized value transfer from WWIL in favour of Third
(Related) Party entities and subjected the documents received
through the process of disclosures to forensic scrutiny by Experts.
The report prepared by Mr. Nicholas Good lent credence to the
fears of the Claimant's and brought to notice past transactions to
the tune of Euro 124 million as described above. It is stated that
the said Report was also submitted before the Tribunal.
359. Armed with this material gained from disclosures
made during the course of Arbitral Proceedings, the Claimants
now proceeded to positively aver concrete/material particulars in
support of their claims with respect to value transfer having been
made to third (related) parties. We advert our consideration to
Para 114 of the Opening Written Submissions submitted by the
Claimants on 25.11.2015.
"114...In setting up the Vaayu Companies and procuring that WWIL transact with related companies, including but not limited to the Vaayu Companies, Mr
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 279 jt-comap-315, 314 & 316 -19.doc
Yogesh Mehra and/or Ajay Mehra have breached their obligations under the SHA and/or Indian Law including clauses 2.7 & 4.1 of the SHA and/or their duties of good faith towards Enercon. Accordingly Mr Yogesh Mehra and Mr Ajay Mehra should pay damages and/or account for profit in respect of transactions undertaken by WWIL with these related companies. By way of example it has now been seen that WWIL has purchased from related companies land or land rights at a cost of Euro 124 million in recent years. No valid consent from Enercon has been obtained for these transactions by which very large sums have been paid to entities which Yogesh Mehra or his family own or have a significant interest in. It amounts to self dealing on the part of Mr Yogesh Mehra and/or Ajay Mehra and/or consists of breaches by Mr Yogesh Mehra and Mr Ajay Mehra of clauses 2.7 and 4.1 of the SHA and/or their duties of good faith towards Enercon and they are obliged to account for all profits they have earned. The same legal principles apply with respect to benefits received from loans made by WWIL to related companies."
(Emphasis Supplied)
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 280 jt-comap-315, 314 & 316 -19.doc
360. We observe that the deficiency in initial pleadings viz.
the Statement of Claim was overcome at a later stage in the form
of Written Submissions and other applications preferred by the
Claimants detailing the Third (Related) Party transactions with a
greater degree of specificity. The requisite particulars of material
facts that are necessary to crystalise a claim, actionable in law, had
finally begun to surface.
361. The Appellant's-herein also took cognizance of the
issue of unauthorized value transfer in favour of Vish Wind that
had been raised by the Claimants and proceeded to expressly
denounce the same in their Opening Written Submissions.
Attention of this Court was drawn by Mr. Chinoy to the relevant
portions on this aspect contained at Paragraphs 87, 88(iii)(iv) and
Para 89(iii) of the Opening Written Submissions submitted before
the Tribunal on behalf of the Appellants. It had been contended
that there has been no transfer of value from WWIL to the Vaayu
Companies. The perceived lacunae in the Report submitted by Mr.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 281 jt-comap-315, 314 & 316 -19.doc
Good were sought to be highlighted. They also defended the
purchase of Development rights by WWIL from the related
companies as being backed by independent valuation reports.
362. During the course of cross-examination of Mr. Yogesh
Mehra, substantial discoveries on this issue were made when he
finally produced financial statements of Vish Wind pursuant to
the directions of the Tribunal. As pointed out by Mr. Chinoy, the
documents brought to fore the following material facts.
-'Vish Wind' had a subscribed capital of Rs. 500,000 [Euro 7500], which had been subscribed by the Mehras.
-From 2007 'Vish Wind' had borrowed substantial sums interest free from WWIL; with Euro 650,000 being owing in 2008. These funds were used for purchasing land.
-In 2010-11 'Vish Wind' had sold development Rights to WWIL for Euro 50 million, as against the total operating expenses incurred of Euro 463,000. The Profit & Loss account showed a profit of over Euro 49 million.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 282 jt-comap-315, 314 & 316 -19.doc
-In 2011-12 'Vish Wind' had sold Development Rights to WWIL for Euro 49 million against total expenses incurred of Euro 1.4 million.
-The contracts for the sale of Development Rights were signed by Yogesh Mehra for 'Vish Wind' and by Mr Ajay Mehra for WWIL.
-That 'Vish Wind' had no employees, no business and virtually no money apart from the loans received from WWIL.
363. In view of the dramatic developments that had
transpired during the course of evidential hearings, Procedural
Order No. 5 came up to be passed on 11.12.2015 wherein,
significantly, the Tribunal categorically recorded at Sr.No.6 the
fact that it proposed to give ample opportunity to the parties to
adduce further evidence with respect to Vish Wind Infrastructure
LLP. For the sake of clarity, we again reproduce the contents of
Procedural Order No. 5.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 283 jt-comap-315, 314 & 316 -19.doc
"The following Timetable is agreed between the parties:
Sr.No. Particulars Date
1. Claimants to file an Application 13 Dec 2015 under Sec 17 of the Arbitration & Conciliation Act 1996
2. Respondents to file their Reply to 19 Dec 2015 the Claimants Application under Sec 17 of the Arbitration & Conciliation Act 1996
3. Respondents to respond to the 15 Dec 2015 Claimants request for production of documents set out at Annex A
4. Tribunal to make a ruling on the 23 Dec 2015 Claimants Application (i) under sec. 17 of the Arbitration and Conciliation Act 1996 & (ii) in relation to any disputed item in Annex A
5. Respondents to provide any 4 January 2016 documents/information in accordance with (3) and (4) Above
6. An Application to the Tribunal, if 18 January 2016 either party seeks to adduce further evidence responsive to the Vish Wind Infrastructure LLP documents or the new documents
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 284 jt-comap-315, 314 & 316 -19.doc
produced at (5) above
7. An Application to cross examine 25 January 2016 or respond to the evidence adduced pursuant to (5) above
8. Exchange of Closing Written 16 March 2016 submissions
9. Any oral evidence in 27 & 28 April accordance with (7) above and 2016 in London.
Closing oral submissions if any are requested and if determined necessary by the Tribunal."
364. We observe that it assumes significance that no
objection/demur was raised at this stage to resist the proposed
reception of evidence with respect to Vish Wind on any ground
including non-arbitrability of this claim or the alleged
insufficiency of pleadings. As a matter of fact, the Procedural
Order No. 5 was passed with the consent of parties. Even if the
opening written submissions submitted on behalf of the
Claimant's were not sufficient to dispel any doubt in the minds of
the Appellant's-herein, Procedural Order No. 5 furnished a clear
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 285 jt-comap-315, 314 & 316 -19.doc
signal that the issue of Vish Wind transactions fell within the
judicial calculus and realm of adjudication . Rather, the Appellants-
herein positively ventured to lead evidence in terms of such liberty
provided under Procedural Order No.5 by submitting the
statements of Mr. Kaushik Khona and Mr. D Vaidyanathan to
explain/justify these Third (Related) Party transactions.
365. Further, the Closing Written Submissions submitted
by both the parties also unequivocally evidence detailed exchange
of submissions on the aspect of the Third (Related) Party
transactions, including Vish Wind transactions. As noted by us
earlier, reference was made by Mr. Chinoy to the Closing
Submissions dated 13.05.2016 tendered by the Claimants wherein
this issue was explored at Part VI(F) whereas the Closing
Submissions of the Appellants-herein dated 25.05.2016 also
elaborately dealt with the said issue in Paragraphs 153-220.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 286 jt-comap-315, 314 & 316 -19.doc
366. The inexorable conclusion that follows from the
circumstances alluded to by us in the preceding paragraphs is that
the Appellants-herein were sufficiently alerted that value transfer
to Third (Related) Party entities including 'Vish Wind' was an
integral issue falling within the purview of adjudication in the
present Arbitration. It is true that the concise statement of
facts/particulars upon which such claim was founded was not
discernible in the initial pleadings i.e. Statement of Claim at the
commencement of proceedings. The concrete particulars
ultimately emerged to the fore during the course of the
proceedings under the circumstances we have elaborately noted in
our discussion above. The comprehensive Written Submissions
submitted by the parties at the opening and closing stage
extensively deal with the Vish Wind transactions. The said
submissions have all the trappings of the 'pleadings' that are filed
before the Arbitral Tribunal. Procedural Order No.5 passed by the
Tribunal with the consent of parties was a ' drum-beat
proclamation' to all concerned, including the present Appellants,
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 287 jt-comap-315, 314 & 316 -19.doc
that the issue of Vish Wind transactions was well within the
domain of adjudication. It was in this view of the matter that the
Appellants even embarked to lead evidence with respect to such
transactions and attempted to render them innocuous.
367. We do not accept the contention canvassed on behalf
of the Appellants that the evidence was led on their behalf to
merely as a mark of abundant caution dispel the prejudice created
in the minds of the learned Arbitrators by the fact that such
transactions dramatically surfaced. To our mind, this is over-
simplification. It has not been explained what other evidence
would have been led before the Arbitral Tribunal if the Statement
of Claim contained express reference to the transaction of purchase
of development rights from Vish Wind. No prejudice is suffered
by the Appellants from the failure on part of the Respondents-
herein to have amended their Statement of Claim.
368. We hold that there existed no element of surprise and
the circumstance of absence of sufficient pleadings in the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 288 jt-comap-315, 314 & 316 -19.doc
Statement of Claim by itself would not result in jettisoning such a
claim from judicial calculus in view of the host of subsequent
events which unequivocally demonstrate the conscious awareness
exhibited by the Appellant's that the issue was very much under
the lens of adjudication.
369. Learned Counsels appearing on behalf of the parties
cited precedents galore in support of their respective contentions
on this aspect. There is no quarrel with the settled propositions
propounded therein. Suffice would it be to observe that the
signature tune of the pronouncements on the subject of the effect
of insufficiency of pleadings is that the decision of the Court
would ultimately rest on the peculiar factual setting of each case.
However, the guiding principles which can be discerned from a
studied analysis of these decisions are culled out and concatenated
by us.
370. In each case the Court embarks upon the exercise to
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 289 jt-comap-315, 314 & 316 -19.doc
ascertain if a new case is sought to be projected later that is wholly
inconsistent/destructive to the case set up earlier or whether the
additional plea/issue sought to be adjudicated in the absence of
requisite pleadings is merely incidental/in consonance to the case
set up by a party. The Courts must then examine whether the
parties contesting the dispute understood that such a plea/issue
was under adjudication. Adjudication of such a plea/issue in the
final judgment must not result in springing a surprise for the rival
litigant. The Court must bear into consideration the circumstance
whether the parties ventured to lead evidence on such a plea/issue.
The possibility of any prejudice stemming from the absence of
requisite pleadings must be weighed. It is upon a holistic appraisal
of the above noted considerations that a Court is required to
decide whether such a plea/issue ought to be adjudicated.
371. Tested on these anvils, we are of the considered view
that the majority Arbitrators fell in no error in proceeding to
adjudicate the issue of purchase of development rights by WWIL
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 290 jt-comap-315, 314 & 316 -19.doc
from Vish Wind. We regret our inability to subscribe to the views
expressed by Mr. Justice Raveendran on this issue in his dissenting
Opinion dated 26.08.2016
372. There can be no cavil to the principle that
adjudication of disputes in a formalised Trial governed under the
Civil Procedure Code, 1908 or under an alternative dispute
resolution mechanism, must conform to norms of fairness and
procedures must be devised in aid of achieving such an object.
We are in agreement with Mr. Mehta, learned Senior Counsel
appearing on behalf of the Appellants that though the Civil
Procedure Code, 1908 does not apply in proprio vigore to such sui
generis proceedings yet the salutary principles of fairplay inspired
from the Code must be adopted.
373. No universal generalization can be made. Everything
depends on the subject matter. In deciding a controversy, the
Arbitrator works in an environment which is quite different from
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 291 jt-comap-315, 314 & 316 -19.doc
that of a judge. He is not bound by the technical rules of
pleadings and evidence. The rules of pleadings that he uses in the
arbitral process are different from the foot-rules and set squares
that we use in the judicial process. From the arbitrator what is
wanted is a practical decision on disputes (1933 AC 502 (at 616)
Abasalam Ltd. Vs. Great Western (London) Gardin Village
Society). He knows that businessmen want to do business and
not to argue about it. He gives not judicial justice, but rough
justice of the world. Because he is not bound by the Codeless
myriad of precedents. Many have found salvation in the faith they
repose in this private domestic forum for settlement of disputes.
374. Before concluding, we note another incidental issue
which was raised before us by the learned Counsels appearing on
behalf of the Appellants. It was submitted that even the relief
granted by the majority Arbitrators upon adjudicating the issue of
Vish Wind transactions fell beyond the purview of the prayer
clause comprised in the Statement of Claim. It was highlighted
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 292 jt-comap-315, 314 & 316 -19.doc
that the majority Award directed the Mehra brothers
(Respondents-therein) to pay WWIL; a co-respondent, a sum of
Rs. 677,24,56,570/- . It was pointed that the relief claimed in the
prayer was sought in favour of the Claimant itself i.e. Enercon
GmbH and not for the benefit of WWIL. It was contended that
such an exercise undertaken by the Tribunal in the guise of
granting a relief under the residual head of 'further and other
reliefs' was impermissible.
375. The majority Arbitrators in paragraphs 298-299 of
their Award record express reasons for adopting such a course. We
reproduce the same hereunder.
"298. Enercon's claim is first pleaded as damages payable by the Mehra directors directly to Enercon. It also pleads an alternative claim for such further or other relief as the Tribunal considers appropriate (paragraph 18 of its application of 13 December 2015 and paragraph 323.4 of its closing written submissions dated 13 May 2016, as also its Statement of Claim of 30 September 2014, at paragraph 102(M).). In the Tribunal's view, given that WWIl is
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 293 jt-comap-315, 314 & 316 -19.doc
only part owned by Enercon (hence Enercon's pecuniary disadvantage resulting from the Mehra directors' wrongdoing is not the same as that of WWIL) and further that WWIL remains the person most immediately affected by such wrongdoing, the liability of the Mehra directors is best discharged by requiring them to hold in full for the benefit of WWIL the advantage gained by their wrongdoing. In deciding upon such relief in favour of WWIL (as distinct from direct relief in favour of Enercon), the Tribunal sees no material disadvantage to Enercon;
and, as for the Mehra directors, no possible prejudice or other unfairness, whether as a matter of pleading, the form of relief or otherwise.
299. The Tribunal therefore finds that the Mehra directors are accountable to WWIL for the €97 million profit which Vish Wind made on the development rights transactions. It is no answer that the Mehra directors personally have not received the whole profit but have diverted some of it, via Vish Wind, to other members of their family. They are liable for the whole profit because they have deprived WWIL of the opportunity to earn the whole profit. The rule is conveniently summarised in Lewin on Trusts:
"the trustee cannot avoid the rules concerning accountability for profits by arranging for the profit to be taken by his company (or a company in which he has a substantial interest) which is a mere cloak for the trustee, or which is formed by the trustee for the purpose of taking the profit, or which could have been taken by the trustee but which is arranged by him to be taken by the company ... No piercing of the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 294 jt-comap-315, 314 & 316 -19.doc
corporate veil is involved. Rather the principle is that in the circumstances stated above the trustee continues to have a liability of his own which is not eliminated by the interposition of the company. In such a case the trustee will be personally accountable for the full amount of the profit, not merely a part proportionate to his interest in the company.""
376. This Court finds no perversity in the approach
adopted by the Arbitral Tribunal in directing the Mehra brothers
to recompense WWIL; the independent jural entity from whose
exchequer the funds had been diverted. Rather such a course is
fair and inures to the advantage of the Mehras as they are
themselves shareholders to the tune of 44% in WWIL. The
premise for granting such relief remains the same i.e. the breach of
SHA by the Mehra's by indulging in Vish Wind transactions. In
that sense, the relief ultimately granted is not radically different
from what had been sought. Only the beneficiary to such relief has
been transposed by the Tribunal. No prejudice could be
demonstrated by this exercise of moulding relief.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 295 jt-comap-315, 314 & 316 -19.doc
NATURE OF RIGHTS STEMMING FROM THE TKHA (AS AMENDED BY THE STKHA) AND WHETHER THE IPLA WAS A CONCLUDED CONTRACT
377. Before proceeding to render our findings on the
above-captioned set of issues we feel constrained to observe at the
very outset that the determination of the said issues essentially
rests upon the analysis of the conduct of the parties,
correspondences exchanged between them and construction of
terms comprised in certain agreements. These matters fall within
the realm of appreciation of evidence. The intensity of review
enjoyed by the Courts while entertaining a challenge under
Section 34/37 of the Arbitration and Conciliation Act, 1996 does
not enwomb within its fold re-appreciation of evidence and lightly
substituting the view adopted by a Tribunal by exercising powers
akin to a Court of Appeal. Reliance was placed by Mr. Kamdar
upon the recent pronouncement of the Supreme Court reported as
(2019) 4 SCC 163 - MMTC Limited v. Vedanta Limited. ::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 296 jt-comap-315, 314 & 316 -19.doc
378. This Court has ventured to microscopically examine
the Award passed by the majority Arbitrators in paragraphs 38-
100 of this judgment and has also endowed anxious consideration
to the erudite views comprised in the dissenting Opinion dated
26.08.2016 authored by Mr. Justice Raveendran in paragraphs
101-122. We have also noticed the observations of the Tribunal
while the same were referred to by learned Counsels during the
course of arguments. With a view to avoid prolixity, we eschew the
exercise of again highlighting in extensio the approach adopted by
the learned Arbitrators while appreciating evidence.
379. We must confess that on the issue whether the IPLA
was a concluded contract or remained in the realm of an inchoate
draft, the reasons advanced by the learned Arbitrators in support
of their respective conclusions are equally persuasive and
compelling. However, in our view, the scales of justice tilt heavily
in favour of the conclusion that the parties intended to create
binding legal obligations by virtue of the fact that the parties chose
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 297 jt-comap-315, 314 & 316 -19.doc
to append their complete signatures at the specific portions
reserved at the last page meant for the execution of the document .
Dr. Wobben appended his signatures at two separate points, on
behalf of Enercon GmbH as well as for WPG whereas Mr. Yogesh
Mehra put his signatures in complete on behalf of Enercon (India)
Ltd. The fact that seasoned businessmen appended their complete
signatures at the spot reserved for execution of the document
excludes the hypothesis that the same was done merely for the
purpose of identification. Further, it assumes significance that as
highlighted above, Dr. Wobben appended his complete signatures
at two separate points. Such degree of formality is plainly
inconsistent with the plea advanced by the Appellants that the
signatures were appended for the purpose of identification of the
draft. For the purpose of identification for future reference, it
would have sufficed, for instance, to have appended signatures or
initials at the bottom of each page. It is interesting to note that at
the bottom of every page the parties have appended their
incomplete signatures, however, in contra-distinction complete
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 298 jt-comap-315, 314 & 316 -19.doc
signatures have been appended at the sport reserved for execution
of the document.
380. It is true that there were blank spaces in the IPLA and
the cover page bears the date of 29.09.2006, whereas the opening
recital in the Agreement reflects the date of 17.09.2006. Further,
the relevant Annexes were not drawn up. It is also a fact that the
Agreed Principles, though formulated on 29.09.2006, but
according to parties admittedly executed on 30.09.3006 contain
reference to a draft IPLA. We find that the majority Award has
adopted a satisfactory line of reasoning and dealt with these
circumstances in light of the ocular evidence led before it.
381. The fact that Enercon GmbH did not scrupulously
ensure, as it is ideally expected to be ensured in commercial
transactions of such value, that the blank voids in the Agreement
are filled, annexures are duly drawn up and the old pages reflecting
the prior dates when the said Agreement was expected to be
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 299 jt-comap-315, 314 & 316 -19.doc
executed be replaced with new pages bearing the actual date of
execution, is perhaps attributable to the fact that Enercon GmbH
was not entering into an Agreement with a stranger.
382. The IPLA was being executed with an old business
confidante with whom relations had not embittered by then. Mr.
Mehra himself admits in his evidence that there was lot of trust
involved. It assumes significance that the IPLA was executed with
Enercon (India) Ltd.; an entity in which Enercon GmbH itself
controlled 56% shareholding. The execution of the Agreement
had got delayed owing to the protracted negotiations.
383. Once the opportune moment arrived and Mr. Yogesh
Mehra ultimately consented to entering the IPLA, the copy of the
Agreement lying handy seems to have been utilized. Effort was
made not to defer matters any further by waiting for a corrected
copy. It appears that under these attending circumstances, the
representatives of Enercon GmbH were slack in their approach
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 300 jt-comap-315, 314 & 316 -19.doc
and did not act promptly to crease out the said anomalies They
ultimately suffered the price for this protracted dispute wherein
these lapses could be telescoped and exploited by the Mehras.
384. Similarly, it is evident that Mr. Kettwig did not
meticulously ensure that the draft of Agreed Principles formulated
by Mr. Mehra on advise of his lawyers was suitably amended as it
contained reference to IPLA as a draft and the same no longer
remained a draft. In this context, the Tribunal has correctly
observed that Mr. Kettwig was not an astute lawyer and could not
visualize the effect of the words- "Draft enclosed" comprised in the
document-Agreed Principles and that these words could later be
construed to be inconsistent with Enercons intention of executing
the IPLA without any amendment.
385. Reliance was placed by Mr. Andhyarujina upon the e-
mail communication dated 24.11.2006 addressed by Ms. Nicole
Fritsch to Mr. Yogesh Mehra apologizing for the delay in
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 301 jt-comap-315, 314 & 316 -19.doc
circulating the outstanding drafts. It was pointed out that the
subject of the e-mail contained reference to other agreements
including the Final IPLA. We may observe that this discrepancy
highlighted by Mr. Andhyarujina stands answered upon the
perusal of the e-mail dated 29.01.2007 addressed by Ms. Nicole
Fritsch to Mr. Yogesh Mehra which contained the drafts of
amended SHA, Corporate Name User Agreement and Successive
Technology License Agreement . Conspicuously, there was no
draft of any amended IPLA as the same had already been executed.
386. As already observed by us at the outset, this Court while
exercising jurisdiction under Section 37 of the Arbitration and
Conciliation Act, 1996 cannot usurp the task of re-appreciating
the evidence as we have been invited to undertake.
387. The Tribunal in paragraphs 148-155 of its Award also
repelled the alternate contention that even if the IPLA was a
concluded contract capable of binding parties yet the same is liable
to be avoided and not enforced in view of
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 302 jt-comap-315, 314 & 316 -19.doc
uncertainty/vagueness.We concur with the findings of Tribunal.
388. It is settled beyond pale of controversy that the Courts
ought not to readily declare the solemn contracts entered into
between parties void for apparent vagueness or uncertainty which
may otherwise be capable of being removed by a process of proper
interpretation.
389. The Tribunal rightly observed that there was no
dispute that the signatures were appended by the parties on the
IPLA on 30.09.2006 and therefore the same was liable come in
effect from the same date as mandated by Clause 1.1 of the
agreement itself. The fact that the cover sheet and the introductory
recital contains other dates was explainable as Mr. Mehra was
initially expected to visit Germany on 17.09.2006 for signing this
agreement and in view of the same the opening recitals contained
reference to execution of the agreement on 17.09.2006. The said
inaccuracies and clerical discrepancies did not make the date of
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 303 jt-comap-315, 314 & 316 -19.doc
commencement of IPLA uncertain.
390. With regard to the argument of absence of discernible
identity of patents and trademarks licensed, it was correctly
observed by the Tribunal that it was a matter of construction that
license must have extended to include all Indian patents and
trademarks to Enercon's name. Such patents and trademarks were
clearly identifiable as being available on the face of public record.
It was observed that there was no evidence to suggest the reason
why parties would have wished to exclude certain
patents/trademarks from the license. In wake of the finding that
the the patents which formed the subject matter of the agreement
were capable of being identified, it could be no longer be
contended that the date of expiry of the agreement could not be
ascertained.
391. Similarly, we are also in agreement with the
conclusions expressed by the Tribunal in paragraphs 156-190 of
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 304 jt-comap-315, 314 & 316 -19.doc
its Award on the issue of nature of rights stemming from the
TKHA (as amended by the STKHA).
392. The Tribunal rightly observed that in view of the fact
that it had held that the IPLA was a concluded contract capable of
binding the signatories thereto, it was not necessary to opine upon
the rights of the parties flowing from the TKHA as the same had
expired and at any rate stood superseded by the IPLA. However, in
view of the fact that a substantial amount of time had been
dedicated to this issue during the proceedings and expert evidence
had been led by the parties, the Tribunal chose to render its
findings on this aspect of the matter. We may observe that this was
the correct course to adopt for another reason. If a Court exercising
jurisdiction under Section 34/37 of the Act, 1996 were to
ultimately hold that the IPLA was not a concluded contract, then
the issue of nature of rights as emerging from the TKHA (as
amended by the STKHA) would naturally assume significance and
the findings of the trier of fact on such an issue would be desirable.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 305 jt-comap-315, 314 & 316 -19.doc
393. It had been contended before us by Mr. Andhyarujina
that the TKHA resulted in outright transfer of rights in perpetuity.
Emphasis was laid upon the meaning of the term ' transfer' as
contained under Article 3.1 of the TKHA and the regulatory
backdrop of RBI in which it was required to be interpreted. It was
submitted that the approvals accorded by the RBI were predicated
on the premise that the transfer of technology was in perpetuity
and the same would stand absorbed/indigenized. Thus, the
Appellants-herein were entitled to manufacture WTG's comprised
under the TKHA/STKHA and no longer be required to pay
royalty to the Claimants (Respondents-herein) upon the expiry of
the agreement or in the case of reaching the ceiling cap of two
million five hundred thousand Deutsche Mark; which limit had
reached in the year 2002 itself.
394. It would be pertinent to highlight that despite a
pointed query from the Mr. Andhyarujina in this regard, no clear
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 306 jt-comap-315, 314 & 316 -19.doc
policy document could be produced which would establish that
one-time transfer of technology in perpetuity was a sine qua non
for obtaining the approvals from the RBI. Similar was the position
before the learned Tribunal.
395. We may pause for a moment and note that the debate
on this count is essentially academic for the reason that Tribunal
has already held, by a different interpretative process, that the
TKHA contemplated a license to use the technical know-how of
the technology comprised therein, however, the same was not
limited for a period of 10 years as was suggested by the Claimants
(Respondents-herein). It was observed that that the right to utilise
the technical know-how transcended beyond the period of expiry
of the TKHA. The process of reasoning chartered by the Tribunal
to arrive at these conclusions has already been alluded to by us
above in paragraphs 63 to 66 and is unassailable. The
Respondents-herein have not sought to challenge these
observations or pointed any infirmity in the said findings.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 307 jt-comap-315, 314 & 316 -19.doc
396. The real issue sought to be urged by Mr.
Andhyarujina is that the transfer of technology of the various
models of WTG's in favour of the Appellants-herein was pursuant
to the stipulated contractual obligations upon the Claimants
(Respondents-herein) under the TKHA (as amended by the
STKHA). It was thus contended that no royalties in their respect
were payable any longer as the ceiling limit of 2.5 million
Deutsche Mark had been reached in the year 2002 itself.
397. We note that this contention was also raised before the
Tribunal. The Tribunal, however, repelled the contention of the
Appellants-herein that the TKHA (as amended by the STKHA)
enwombed within its fold the right to manufacture E-48 and E-53
models of the WTG's.
398. It had been contended on behalf of the Appellants-
herein that the STKHA had contemplated supply of atleast two
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 308 jt-comap-315, 314 & 316 -19.doc
other ranges/models in addition to E-26, E-30 and E-40. It was on
strength of this recital comprised in STKHA that Mr.
Andhyarujina submitted that the Appellants manufactured E-48
and E-33 WTG's as a matter of right under the TKHA regime (as
amended by STKHA) itself. In this context, it was submitted that
it was inconceivable that Enercon GmbH would transfer
confidential and valuable Technical Know-How of WTG's in mere
anticipation of a formal agreement. We note that before the
Tribunal a slightly different claim seems to have been staked, in as
much as the Tribunal records that it was urged that in addition to
E-26, E-30 and E-40 WTG's, the right to manufacture E-48 and
E-53 WTG's was claimed under the TKHA regime (as
amended by STKHA) and not E-33 WTG as contended by
Mr. Andhyarujinja.
399. Upon adverting our thoughtful consideration to the
rival submissions in this regard and having perused the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 309 jt-comap-315, 314 & 316 -19.doc
correspondence exchanged between the parties we are of the
considered view that the findings of the Tribunal are based upon
sound appreciation of evidence. The Tribunal aptly observed that
the transfer of technology for E-33, E-48 and E-53 models of
WTG's was initiated by Enercon GmbH only after the expiry of
the TKHA and STKHA in January 2004. The said transfer was
made in anticipation of a fresh agreement that would be shortly
formalised between the parties after negotiations. At this stage, we
may observe that Enercon GmbH was not dealing with a stranger
but with a corporate entity in which it itself had a 56% controlling
stake. The relations between Enercon GmbH and Mehra's had not
embittered as yet. Sale of the new WTG's in the Indian market
would have fetched further revenue for Enercon GmbH, and as a
matter of commercial prudence, Enercon GmbH would not have
wanted to defer the opportunity of exploiting the Indian market
by awaiting formalization of an agreement. Viewed in the light of
these attending circumstances, we do not find it unbelievable that
the technology was passed on to the Appellants without having
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 310 jt-comap-315, 314 & 316 -19.doc
first entered a formal agreement. It assumes significance that a
perusal of the correspondence exchanged between the parties
during the course of negotiations nowhere reflects that Mr. Yogesh
Mehra claimed that he was as a matter of right entitled to the
technology of E-33, E-48 and E-53 WTG's in terms of the TKHA
(as amended by the STKHA) and thus there would be no question
of payment of royalties. The Tribunal correctly held that the right
to receive technical know-how and manufacture atleast two other
ranges/models stood satisfied upon the receipt of technical know-
how of E-40/644/E2, E-40/644/E3B and E-40/644/E2B, as
explained by Mr. Kettwig in his evidence. In order to fortify its
conclusions, the Tribunal placed reliance upon the
communication addressed by Mr. Yogesh Mehra dated 17-10-
2008 wherein he listed each of the E-40's separately as a model for
which technology had been supplied to WWIL. The position was
similarly stated by him in the draft of the new TKHA prepared by
him and shared with Enercon GmbH on 14-10-2004.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 311 jt-comap-315, 314 & 316 -19.doc
400. The conclusions reached by the Arbitral Tribunal are
supported by reasons, and the reasons are anchored on the material
available on record. No perversity is palpable in the approach of
the learned Arbitrators on this count. The Court is bound by the
arbitrator's finding of fact and cannot review them unless they are
unsupported by evidence or it appears that there is no evidence to
support it. As long as the view taken by the Tribunal is plausible,
it is not open to the Court to examine the adequacy of the
evidence.
401. On the issue of restitution of royalties, it had been
submitted by Mr. Andhyarujina that the said amounts were
transferred under bona fide mistake and no further royalties were
payable. In view of the fact that we have already held that the
IPLA had been entered into as a concluded contract and royalties
were payable thereunder, the question of directing restitution
would not arise. All consequences that flow from the execution of
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 312 jt-comap-315, 314 & 316 -19.doc
the IPLA are liable to be enforced. The said consequences include
return of documents and materials containing confidential
technology in terms of Clause 2.11 of the IPLA. In this context,
we note that we have also negatived the contention that the
Appellant's-herein were entitled to E-33, E-48 and E-53 WTG's
under the TKHA regime (as amended by the STKHA) and that no
further royalties in their respect were payable.
WHETHER THE MAJORITY AWARD IS VITIATED BY BIAS/PREJUDICE
402. Dr. Saraf, learned Counsel appearing on behalf of the
Appellants, contended during the course of arguments that the
majority Award stood vitiated from the root to the fruit in view of
the underlying bias permeating the Award.
403. At the outset, we may observe that bias/prejudice was
sought to be inferred merely on the basis of certain observations
expressed by the majority Arbitrators while appreciating evidence
the evidence of Mr. Yogesh Mehra. We have already reproduced
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 313 jt-comap-315, 314 & 316 -19.doc
the observations of the learned Arbitrators in paragraphs 185 and
187 of our judgment while extensively noting the submissions of
Dr. Saraf on this aspect. Dr. Saraf further submitted that Mr.
Yogesh Mehra on the other hand had been observed to be a
truthful witness in the minority Award.
404. We are unable to accept the contention canvassed by
Dr. Saraf on this score. The very premise for inferring bias seems
rather tenuous and on a slippery slope. Every adjudicator has his
own distinct style of penning his views that in turn is shaped by a
conundrum of considerations including the legal system he
belongs. It is indeed a stark reality that the language employed by a
Judge/Arbitrator does, at times, gets influenced by the glaring facts
of the case and the evidence led before him. However, the use of
strong language or deprecating the conduct of a litigant by itself
does not necessarily furnish a firm basis to infer bias/prejudice.
405. Similarly, the fact that it was observed that there were
delays in disposal of certain proceedings in Indian Courts can also
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 314 jt-comap-315, 314 & 316 -19.doc
not lead to the conclusion of a "general territorial bias", as
suggested by Dr. Saraf. The said observations were made by the
Tribunal in the context of dealing with a contention raised by the
Appellant's-herein requesting the Tribunal not to exercise
jurisdiction with respect to disputes relatable to the SHA as the
same were pending consideration of the CLB. We find that no
umbrage can be taken from the observations that are factually
correct and this Court is unable to perceive bias of any nature from
the Tribunal having ventured to narrate the naked truth.
406. The Supreme Court, in its decision reported as (1976)
1 SCC 800 - Gulam Mustafa and Others v. The State of
Maharashtra and Others in a slightly different context of
allegations of malafide exercise of powers by a public authority,
aptly observed that such a plea is the easiest to make and the most
difficult in law to make out. It was further observed that it is the
last refuge of a losing litigant. To our mind, these luminous
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 315 jt-comap-315, 314 & 316 -19.doc
observations of Krishna Iyer, J apply with equal force to the
allegations of bias/prejudice cast against adjudicators. There is no
quarrel with the general principles of law enunciated in the
decisions pressed into service by Dr. Saraf. However, the factual
conspectus of inferring bias is naturally different in every case
under consideration.
407. The fact that a witness was found unworthy of credit
by the majority Arbitrators whereas the minority found such a
witness to be truthful are matters which in substance pertain to the
realm of appreciation of evidence.
408. Mr. Kamdar highlighted before us that in Paragraph
22 of the Affidavit in Rejoinder (in Notice of Motion (L) No. 84
of 2019 dated 20.02.2019 filed by Ajay Mehra it had been averred
that the Appellant was already apprehensive of the alleged
prejudice and personal bias of the majority of the Arbitral Tribunal
by 11.12.2015 i.e. during the pendency of the arbitral proceedings
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 316 jt-comap-315, 314 & 316 -19.doc
itself. In this context it was submitted that in terms of Section
13(2) of the Act, 1996 such a challenge ought to have been raised
at that stage itself before the Arbitrators, failing which such a
challenge is deemed to have been waived. Reliance was placed
upon the decision of this Court reported as (2015) 7 BomCR 141 -
M/s Visakha Petroleum Products Pvt. Ltd. v. B.L Bansal and Ors.
409. Per Contra, Dr. Saraf in his rejoinder submissions
sought to clarify this aspect by submitting that the perception of
bias/prejudice that had started germinating in the minds of the
Appellants in the month of December 2015 ultimately crystallized
after having read the Final Award. It is in this view of the matter
that such a plea was never raised before the Tribunal. Reliance was
placed by Dr. Saraf to a decision of this Court reported as 2015 2
Mah LJ 38 - Inox Leisure Ltd. v. Goa State Infrastructure
Corporation Ltd.
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 317 jt-comap-315, 314 & 316 -19.doc
410. We find that it would no longer be necessary for us to
decide upon the objection raised by Mr. Kamdar in view of the fact
that we have held that there is no reasonable basis to infer any
bias/prejudice in the case at hand.
WHETHER THE DIRECTIONS AGAINST THE MEHRA'S FOR PAYMENT OF COSTS OF PROCEEDINGS ARE PERVERSE
411. Dr. Saraf, learned Counsel appearing on behalf of the
Appellants did not raise challenge to the quantum of costs of
proceedings assessed by the Tribunal. It was however contended
that the majority Arbitrators fell in error by directing the Mehra
brothers instead of WWIL to expend the costs of proceedings. Our
attention was drawn to the observations in paragraphs 306-307 of
the majority Award wherein it was observed by the learned
Arbitrators themselves that there was no personal liability of
Mehra brothers with regard to the debts of WWIL.
412. It is true that the learned Arbitrators did opine in
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 318 jt-comap-315, 314 & 316 -19.doc
paragraphs 306-307 of their Award that there was no personal
liability of the Mehra brothers. However, we find that the said
observations were in the context of payment of the debts owed by
WWIL viz. payment of royalties and failure to pay for the goods
that had been supplied to WWIL. Under the agreements,
including the IPLA the obligation to pay royalties and make
payment for the components etc. was upon WWIL. Thus, the said
liability could not have been shifted upon the Mehra brothers.
413. Apropos, the issue of payment of costs of proceedings
the majority Arbitrators fell in no error to direct the Mehra
brothers to expend such costs rather than foisting such liability
upon WWIL. We say so because the directions issued by the
majority Arbitrators directing the Mehra brothers to bear the costs
of proceedings was logical in as much as they were in the de-facto
control of the management of WWIL during period of actionable
breaches. Further, a direction to WWIL to expend the costs of
proceedings would in effect imply saddling Enercon GmbH (the
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 319 jt-comap-315, 314 & 316 -19.doc
successful Claimant) with such liability as it owns shareholding in
WWIL to the tune of 56%. No exception can be taken to the
approach of the majority Arbitrators in this regard.
414. In view of the discussion comprised in the preceding
paragraphs, we are of the considered view that the appeals are
liable to be dismissed and are dismissed accordingly. The majority
Award is liable to be upheld in its entirety.
415. There shall be no order as to costs.
N. M. JAMDAR,J. CHIEF JUSTICE
416. After decision was pronounced in open Court,
dismissing the three captioned appeals, at an oral request made by
the counsel for the parties, with consent, it is directed that the
interim order dated 24.04.2018, as modified by the order dated
27.04.2018 passed by the learned Single Judge in Notice of
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 ::: Jdk/pdp 320 jt-comap-315, 314 & 316 -19.doc
Motion (L) No. 1035 of 2018 in Arbitration Petition No. 205 of
2016, shall continue for a period of further six weeks from today.
N. M. JAMDAR,J. CHIEF JUSTICE
::: Uploaded on - 24/06/2019 ::: Downloaded on - 25/06/2019 02:45:02 :::
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free