Agra Development Authority, Agra vs Anek Singh
- Neutral2022 INSC 611
- SCR[2022] 4 SCR 110
Ratio decidendi
The rule this decision rests on
Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 provides for deemed lapse of land acquisition proceedings only where the acquiring authority has failed, due to inaction for five or more years prior to the commencement of the Act, to take possession of the land and to pay compensation; the word "or" in Section 24(2) between possession and compensation must be read as "nor" or "and", such that lapse occurs only when neither possession has been taken nor compensation paid, and not when one of these has been accomplished. Where possession of the land has been taken by the acquiring authority, there is no lapse of acquisition proceedings under Section 24(2) even if compensation has not been paid or deposited in court, and a landowner who has been tendered compensation under Section 31(1) of the Land Acquisition Act, 1894 cannot claim that the acquisition has lapsed by virtue of non-payment or non-deposit. Non-deposit of compensation with the court does not result in lapse of land acquisition proceedings; the consequence of non-deposit for a majority of landholdings is that all landowners as on the date of notification under Section 4 of the 1894 Act are entitled to compensation under the 2013 Act, not that the acquisition lapses. Section 24(2) applies only to proceedings pending on 1 January 2014 and does not revive stale or time-barred claims, reopen concluded proceedings, or allow landowners to question the legality of concluded acquisition proceedings on the ground of the mode of taking possession or mode of deposit of compensation.
Written by Miss Lucy from the judgment below, not taken from a headnote.
Judgment
As delivered
CIVIL APPEAL NO. 2914 OF 2022
Agra Development Authority, Agra ..Appellant
Versus
Anek Singh and others ..Respondents
JUDGMENT
M. R. Shah, J.
1. Feeling aggrieved and dissatisfied with the impugned
judgment and order passed by the High Court of Judicature at
Allahabad in Civil Miscellaneous Writ Petition No.13927 of 2016
by which the High Court has allowed the said writ petition
preferred by the respondents herein original writ petitioners and
has held that the acquisition proceedings with respect to the land
in question shall be deemed to have lapsed under Subsection (2)
of Section 24 of the Right to Fair Compensation and Signature Not Verified Digitally signed by
Transparency in Land Acquisition, Rehabilitation and Jatinder Kaur Date: 2022.05.20 17:14:34 IST Reason:
Resettlement Act, 2013 (hereinafter referred to as ‘the Act 2013’),
1 the Agra Development Authority, Agra has preferred the present
appeal.
2. We have heard learned counsel for the respective parties.
We have perused and considered the impugned judgment and
order passed by the High Court.
3. Before the High Court it was the specific case on behalf of
the Agra Development Authority – appellant herein that as such
the possession of the land in question was already taken over
and even the name of the Authority was mutated in the revenue
records. It was also the specific case on behalf of the Authority
that possession of the land in question was with them but the
original writ petitioners illegally occupied it again. It was also the
case on behalf of the Authority that the development works have
already been carried out on the land in question and the entire
compensation had already been deposited with the Special Land
Acquisition Officer. It was also the case on behalf of the
Authority that the original writ petitioners deliberately did not
take the compensation for the remaining plot measuring 6 Biswa
and 15 Biswansi and therefore, on account of the fault of the writ
petitioners, the acquisition proceedings cannot lapse. However,
by the impugned judgment and order the High Court has held
2 and declared that the acquisition proceedings with respect to the
land in question shall be deemed to have lapsed under sub
section (2) of Section 24 of the Act, 2013 on the ground that the
amount of compensation was not actually paid to the land
owners. While holding so the High Court has relied upon and
considered the decision of this Court in the case of Pune
Municipal Corporation and another versus Harakchand
Misirimal Solanki and others reported in (2014) 3 SCC 183. 3.1 Thus, while passing the impugned judgment and order the
High Court has solely relied upon the decision of this Court in
the case of Pune Municipal Corporation (supra) and other
decisions in which the decision in the case of Pune Municipal
Corporation (supra) was followed. (Para 12 of the impugned
judgment and order)
However, the decision of this Court in the case of Pune
Municipal Corporation (supra) has been subsequently over
ruled by the Constitution Bench of this Court in the case of
Indore Development Authority versus Manoharlal and others,
3 2020) 8 SCC 129. In paragraph 366 it is observed and held as
under:
“366. In view of the aforesaid discussion, we answer the questions as under:
366.1. Under the provisions of Section 24(1)(a) in case the award is not made as on 112014, the date of commencement of the 2013 Act, there is no lapse of proceedings. Compensation has to be determined under the provisions of the 2013 Act.
366.2. In case the award has been passed within the window period of five years excluding the period covered by an interim order of the court, then proceedings shall continue as provided under Section 24(1)(b) of the 2013 Act under the 1894 Act as if it has not been repealed.
366.3. The word “or” used in Section 24(2) between possession and compensation has to be read as “nor” or as “and”. The deemed lapse of land acquisition proceedings under Section 24(2) of the 2013 Act takes place where due to inaction of authorities for five years or more prior to commencement of the said Act, the possession of land has not been taken nor compensation has been paid. In other words, in case possession has been taken, compensation has not been paid then there is no lapse. Similarly, if compensation has been paid, possession has not been taken then there is no lapse.
366.4. The expression “paid” in the main part of Section 24(2) of the 2013 Act does not include a deposit of compensation in court. The consequence of non deposit is provided in the proviso to Section 24(2) in case it has not been deposited with respect to majority of landholdings then all beneficiaries (landowners) as on the date of notification for land acquisition under Section 4 of the 1894 Act shall be entitled to compensation in accordance with the provisions of the
4 2013 Act. In case the obligation under Section 31 of the Land Acquisition Act, 1894 has not been fulfilled, interest under Section 34 of the said Act can be granted. Nondeposit of compensation (in court) does not result in the lapse of land acquisition proceedings.
In case of nondeposit with respect to the majority of holdings for five years or more, compensation under the 2013 Act has to be paid to the “landowners” as on the date of notification for land acquisition under Section 4 of the 1894 Act.
366.5. In case a person has been tendered the compensation as provided under Section 31(1) of the 1894 Act, it is not open to him to claim that acquisition has lapsed under Section 24(2) due to nonpayment or nondeposit of compensation in court. The obligation to pay is complete by tendering the amount under Section 31(1). The landowners who had refused to accept compensation or who sought reference for higher compensation, cannot claim that the acquisition proceedings had lapsed under Section 24(2) of the 2013 Act.
366.6. The proviso to Section 24(2) of the 2013 Act is to be treated as part of Section 24(2), not part of Section 24(1)(b).
366.7. The mode of taking possession under the 1894 Act and as contemplated under Section 24(2) is by drawing of inquest report/memorandum. Once award has been passed on taking possession under Section 16 of the 1894 Act, the land vests in State there is no divesting provided under Section 24(2) of the 2013 Act, as once possession has been taken there is no lapse under Section 24(2).
366.9. Section 24(2) of the 2013 Act does not give rise to new cause of action to question the legality of concluded proceedings of land acquisition. Section 24 applies to a proceeding pending on the date of enforcement of the 2013 Act i.e. 112014. It does not revive stale and timebarred claims and does not
5 reopen concluded proceedings nor allow landowners to question the legality of mode of taking possession to reopen proceedings or mode of deposit of compensation in the treasury instead of court to invalidate acquisition.
366.8. The provisions of Section 24(2) providing for a deemed lapse of proceedings are applicable in case authorities have failed due to their inaction to take possession and pay compensation for five years or more before the 2013 Act came into force, in a proceeding for land acquisition pending with the authority concerned as on 112014. The period of subsistence of interim orders passed by court has to be excluded in the computation of five years.”
4. In view of the above Constitution Bench decision of this
Court in the case of Indore Development Authority (supra) and
the earlier decision of this Court in the case of Pune Municipal
Corporation (supra) has been specifically overruled by this
Court, which has been relied upon by the High Court while
passing the impugned judgment and order, the same passed by
the High Court is unsustainable and it deserves to be quashed
and set aside.
4.1 In view of the decision of this Court in the case of Indore
Development Authority (supra) and considering the facts and
circumstances narrated hereinabove, it cannot be said that the
6 acquisition proceedings with respect to the land in question is
deemed to have lapsed under the provisions of the Act, 2013.
5. In view of the above discussion and for the reasons stated
above present appeal succeeds. The impugned judgment and
order passed by the High Court is hereby quashed and set aside.
Consequently, the writ petition preferred by the original writ
petitioner before the High Court stands dismissed.
In the facts and circumstances of the case, there shall be no
order as to costs.
…………………………………J. (M. R. SHAH)
…………………………………J. (B.V. NAGARATHNA) New Delhi, May 20, 2022.
7
This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.
Research this judgment with Miss Lucy
Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.
Try Miss Lucy free