Miss Lucy
← All judgments

A.P.Indstl.Infrastructure Corpn.Ltd vs Chinthamaneni Narasimha Rao & Ors

Supreme Court15 September 2011Anil R. Dave · Mukundakam Sharma

Ratio decidendi

The rule this decision rests on

Where a writ petition challenging land acquisition proceedings is filed after the award has been made and possession of the land has been taken by the government authorities, the court should be loath to quash the proceedings and should exercise restraint in interfering, particularly when the petition is filed with gross or substantial delay—such as more than two years after the declaration under Section 6 of the Act—even if the petitioner challenges the validity of that declaration itself.

Written by Miss Lucy from the judgment below, not taken from a headnote.

Judgment

As delivered

1

NON-REPORTABLE

IN THE SUPREME COURT OF INDIA

CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NOs. 304-305 OF 2005

A.P. Industrial Infrastructure .....Appellant.

Corpn. Ltd.

Versus

Chinthamaneni Narasimha Rao & Ors. .....Respondents

J U D G M E N T

ANIL R. DAVE, J.

1. Being aggrieved by the Judgment and Order dated 23rd July,

2001 in Writ Appeal No. 1337 of 1999 and Review W.A.M.P. No.

1822 of 2002 in Writ Appeal No. 1337 of 1999 dated 01st October,

2004 passed by the High Court of Judicature of Andhra Pradesh at

Hyderabad, these appeals have been filed by the original petitioners-

respondents herein, whose lands have been acquired by the State for a

public purpose.

2 2. The facts giving rise to the present litigation in a nutshell are as

under:

A notification under Section 4(1) of the Land Acquisition Act,

1894 (in short the `Act') was issued on 27th August, 1993 for

acquisition of land admeasuring 101 acres and 33 cents in and around

Eluru town for a public purpose for setting up an Auto Nagar so as to

develop the said land for industrial purpose. On 20th September, 1993

and 21st September, 1993, the said notification was published in two

daily newspapers whereas on 29th September, 1993 the substance of

the said notification was published in the locality where the land was

situated. Looking into the urgency, under the provisions of Section 17

of the Act, an inquiry under Section 5 A of the Act was dispensed

with. Thereafter notification with regard to the declaration under

Section 6 of the Act was published on 8th October, 1993. A Writ

Petition No. 5036 of 1994 was filed on 18th September, 1995

challenging the validity of the proceedings on the ground that the

provision of Section 17 of the Act could not have been invoked for

dispensing with the enquiry under Section 5A of the Act and in the

said petition, the High Court of Andhra Pradesh had passed an interim

order whereby the authorities were restrained from taking possession

3

of the land in question. Ultimately the said petition was finally

disposed of on 18th September, 1995 whereby the declaration under

Section 6 had been quashed and it was directed to hold an enquiry

under Section 5A of the Act.

In pursuance to the above order passed by the High Court,

necessary enquiry under Section 5A of the Act was made, objections

were invited and ultimately it was decided to acquire only 54 acres

and 54 cents land out of the land in question admeasuring 101 acres

and 33 cents. Declaration under Section 6 of the Act was thereafter

published on 7th August, 1996.

After making declaration under Section 6 of the Act, Award

was made on 7th January, 1998 and possession of the land in question

was taken on 9th March, 1998. After possession of land in question

was taken by the Land Acquisition Officer from the owners of the

land, on 16th July, 1998, the Land Acquisition Officer handed over

possession of the land in question to the present appellant-Corporation

for a public purpose, for which the land in question had been acquired.

It is pertinent to note that after declaration under Section 6 of

the Act made on 7th August, 1996 and after taking possession of the

4

land in question on 9th March, 1998, writ petition No. 32806 of 1998

was filed in the High Court of Andhra Pradesh challenging the

validity of declaration under Section 6 of the Act on the ground that

the declaration was not made within the period prescribed under

Section 6 of the Act.

By an order dated 27th August, 1999, the learned Single Judge

dismissed the aforesaid writ petition after recording the fact that

award was made on 7th January, 1998 and possession of the land in

question had been handed over to the present appellant on 9th March,

1998. Moreover, the learned Single Judge also held that the

declaration under Section 6 was made within the period stipulated

under Section 6 of the Act.

Being aggrieved by the dismissal of the petition, the land

owners-the present respondents filed Writ Appeal no. 1337 of 1999.

The said Writ Appeal was allowed by an order dated 23rd July, 2001

whereby the order passed by the learned Single Judge dated 27th

August, 1999 was quashed and set aside as it was held by the Division

Bench of the High Court that the declaration under Section 6 of the

Act was made beyond the period prescribed under Section 6 of the

Act.

5

Being aggrieved by the said Judgment and Order, A.P.

Industrial Infrastucture Corporation- the present appellant filed a

Review petition being Review WAMP No. 1822 of 2002 in Writ

Appeal No. 1337 of 1999 on 29th August, 2001 which was also

dismissed by the Division Bench of the High Court by the impugned

judgment and order on 01st October, 2004.

3. Being aggrieved by the above judgment and orders passed by

the Division Bench of the High Court these appeals have been filed by

the A.P. Industrial Infrastructure Corporation Ltd., which is an

undertaking owned by the Government of Andhra Pradesh for whose

benefit the land in question had been acquired.

4. The learned counsel appearing for the appellant mainly made

two submissions: the first is with regard to the delay caused in filing

the petition or initiation of litigation challenging the validity of the

acquisition proceedings and the Second is with regard to delay caused

in making the declaration under Section 6 of the Act. According to

him the declaration was made within the period prescribed under

Section 6 of the Act.

6 5. On the other hand, the learned counsel appearing for the land

owners supported the reasons given by the Division Bench of the

Andhra Pradesh High Court and submitted that the declaration under

Section 6 was made beyond the period prescribed under Section 6 of

the Act.

6. We have heard the learned counsel at great length. Several

judgments were cited by the learned counsel so as to substantiate their

cases. In our view there was substantial delay caused in filing the

petition before the Andhra Pradesh High Court whereby the land

acquisition proceedings had been challenged by the land owners and,

therefore, we would not like to go into other reasons and other

submissions which pertain to delay causing making declaration under

Section 6 of the Act.

7. It is not in dispute that Notification under Section 4 of the Act

was issued on 27th August, 1993 and it was lastly published, in the

locality where the land is situated, on 29th September, 1993. We have

already referred to the earlier litigation and the objections filed by the

land owners and decision with regard to the land acquisition officer

and the Government Authorities for not acquiring the entire land,

7

which was sought to be acquired at an earlier stage. Ultimately the

land admeasuring 54 acres and 54 cents had been acquired out of the

land in question admeasuring 101 acres and 33 cents . It is not in

dispute that the Declaration under Section 6 was made on 7th August,

1996 and an award was made on 7th January, 1998. Though there is

some dispute with regard to the fact of taking possession of the land, it

is an admitted fact that atleast paper possession of the land in question

was taken on 9th March, 1998 and possession was handed over to the

appellant on 16th July, 1998.

8. Thus, it is an admitted fact that declaration under Section 6 of

the Act was made on 7th August, 1996 and the Award was made on 7th

January, 1998. A petition challenging the validity of the declaration

under Section 6 of the Act on the ground that it was declared beyond

the period specified under Section 6 of the Act was filed in

November, 1998. In our opinion, the petition had been filed at a

belated stage. If the land owners were really aggrieved by the

declaration under Section 6 of the Act, they ought to have challenged

the same immediately after the declaration under Section 6 was made.

For the reasons best known to them, they waited for more than two

years. Award was made on 7th January, 1998 and even possession was

8

taken on 9th March, 1998 and on 16th July, 1998, the possession was

also handed over to the present appellant so that it can use the land in

question for a public purpose for which it had been acquired.

9. The learned Single Judge duly recorded the fact that possession

of the land in question was taken from the land owners on 9th March,

1998.

10. We see no reason for the land owners to wait for a few years for

challenging the declaration made under Section 6 of the Act on the

ground of delay. If the land owners had been really aggrieved, they

ought to have challenged the proceedings immediately after

declaration made under Section 6 of the Act.

11. This Court has held in several judgments that if the land owners

are aggrieved by the acquisition proceedings, they must challenge the

same atleast before an award is made and the possession of the land in

question is taken by the government authorities.

It has been held in Swaika Propeties (P) Ltd. & Another vs.

State of Rajasthan & Others [(2008) 4 SCC 695] as under:

9 "6. This Court has repeatedly held that a writ petition

challenging the notification for acquisition of land, if filed

after the possession having been taken, is not maintainable.

In Municipal Corpn. of Greater Bombay v. Industrial

Development Investment Co. (P) Ltd. (1996) 11 SCC 501

where K. Ramaswamy, J. speaking for a Bench consisting

of His Lordship and S.B. Majmudar, J. held: (SCC p. 520,

para 29)

"29. It is thus well-settled law that when there

is inordinate delay in filing the writ petition and

when all steps taken in the acquisition

proceedings have become final, the Court

should be loath to quash the notifications. The

High Court has, no doubt, discretionary powers

under Article 226 of the Constitution to quash

the notification under Section 4(1) and

declaration under Section 6. But it should be

exercised taking all relevant factors into

pragmatic consideration. When the award was

passed and possession was taken, the Court

should not have exercised its power to quash

the award which is a material factor to be taken

into consideration before exercising the power

under Article 226. The fact that no third-party

rights were created in the case is hardly a

ground for interference. The Division Bench of

the High Court was not right in interfering with

the discretion exercised by the learned Single

Judge dismissing the writ petition on the

ground of laches."

Similarly, in the case of State of Rajasthan & Ors. vs. D.R.

Laxmi & Ors. [(1996) 6 SCC 445] following the decision of this

10

Court in the case of Municipal Corporation of Greater Bombay

(supra) it was held :

".... When the award was passed and possession was taken,

the Court should not have exercised its power to quash the

award which is a material factor to be taken into

consideration before exercising the power under Article

226. The fact that no third party rights were created in the

case, is hardly a ground for interference. The Division

Bench of the High Court was not right in interfering with

the discretion exercised by the learned Single Judge

dismissing the writ petition on the ground of laches. ...."

To the similar effect is the judgment of this Court in Municipal

Council, Ahmednagar & Another vs. Shah Hyder Beig & Ors. [(2000) 2

SCC 48] wherein this Court, following the decision of this Court in C.

Padma and Others vs. Dy. Secy. to the Govt. of T.N. and Others

[(1997)2 SCC 627] held: (Shah Hyder case SCC p. 55, para 17)

"17. In any event, after the award is passed no writ petition

can be filed challenging the acquisition notice or against

any proceeding thereunder. This has been the consistent

view taken by this Court and in one of the recent cases (C.

Padma v. Dy. Secy. to the Govt. of T.N. [(1997) 2 SCC

627]...."

11 12. Therefore, we are not referring to the other judgments,

which have been cited by the learned counsel on the subject of validity of

declaration made under Section 6 of he Act for the reasons that we are

convinced that there was gross delay in challenging the validity of the

acquisition proceedings.

13. It is also pertinent to note that according to the appellant,

possession of the land in question had been handed over to the appellant-

Corporation on 16th July, 1998 and in view of the said fact, this Court had

granted interim stay in favour of the appellant on 10th January, 2005 and

an application made by the land owners for vacating the said stay had

been rejected and it was directed to maintain status quo.

14. Looking to the facts of the present case and in the light of the

law laid down by this Court, which has been referred to hereinabove, we

firmly believe that the petition filed by the land owners was at a belated

stage. For the said reason, we do not desire to interfere with the

acquisition proceedings, which had been challenged after more than two

years of declaration under Section 6 of the Act and on that ground alone

we feel that appeals deserve to be allowed.

12 15. The impugned judgment and orders passed by the Division

Bench of the High Court of Andhra Pradesh is quashed and set aside. The

appeals are allowed with no order as to costs.

...............................................J.

(Dr. MUKUNDAKAM SHARMA)

..............................................J.

(ANIL R. DAVE)

New Delhi

September 15, 2011.

This page reproduces a public judgment and a summary of it. It is research material, not legal advice, and it is no substitute for advice from an advocate on your own facts.

Research this judgment with Miss Lucy

Ask what it holds, what has followed it, and what it means for your matter — in plain English, with the citations.

Try Miss Lucy free